AI summarySolihull Cabinet approves Solihull Energy Ltd Business Plan 2026-27, notes July 2026 network handover and clean 2024/25 accounts showing £0.074m pre-tax profit.
Money£0.074m pre-tax profit; £0.112m MTFS provision2024/25 audited profit; 2026/27 MTFS loss mitigation sum
What happens nextHandover July 2026; customers connect May-June 2026Phase 1 customers begin receiving heat and power
Who it affectsNot stated
What was decided
Cabinet approved the Solihull Energy Ltd Business Plan 2026-27, which sets out a transitional year as the network moves into operation and the full plan presented in 2027. Report P4, P16, P19
Cabinet noted the formal handover of the energy network from Vital Energi to Solihull Energy Ltd is planned for July 2026, reprogrammed from April 2026 due to gas and electricity easement works. Report P5, P32, P33
Cabinet noted the 2024/25 financial outturn, which received a clean audit opinion and showed a net pre-tax profit of £0.074m, and the filing of the Annual Report and Financial Statements. Report P6, P41, P42
Why
Cabinet approval of the business plan is required by the governance arrangements for the council-owned Special Purpose Vehicle, and no alternative options were considered. Report P7, P45
The plan supports the council's ambitions on net zero, economic growth and town centre viability, and helps meet a 2041 net zero target for Solihull. Report P51, P52, P53, P56, P57
The business plan was endorsed by the ESCo Board, the Solihull Energy Shareholder Panel and the UKC Portfolio Board before going to Cabinet. Report P28, P29
What happens next
Subject to approval, the Business Plan 2026-27 will be adopted and published; construction has restarted and connections to Phase 1 customers are being scheduled for May and June 2026. Report P30, P34, P35, P36
Key outputs for 2026-27 include completing the energy centre, launching the operate and maintain stage, finalising billing, progressing Green Heat Network Fund and WMCA retrofit pilot bids, and preparing for Heat Network Zoning Regulations. Report P25
A 2027 Business Plan will be a fuller refresh once the network is operational, grant outcomes are known and a decarbonisation study is complete. Report P19
The money
£0.074m Net pre-tax profit in audited 2024/25 Solihull Energy accounts Report P42
£18.7m Total construction phase cost of the project, funded by grant and Council borrowing Report P70
£0.112m Sum built into the Council's Medium Term Financial Strategy for 2026/27 to mitigate the forecast operational deficit Report P72
£0.150m Forecast underspend on The Council House/Civic Suite and The Core utility budgets in 2026/27 as a network customer Report P73
Options considered
Chosen: Approve the Solihull Energy Ltd Business Plan 2026-27. Cabinet approval is required for the business plan; no alternative options were identified Report P4, P45
Implications
Financial: The 2026/27 operational forecast for Solihull Energy Ltd shows a deficit, driven by lower utility prices and the part-year effect of customers joining the network in the first quarter; £0.112m has been set aside in the MTFS. Report P71, P72
Financial: Lower energy prices are expected to reduce the Council's own utility budgets at The Council House/Civic Suite and The Core by around £0.150m in 2026/27. Report P73
Legal: Officers confirm there are no legal implications arising from approving the Business Plan; statutory accounts and audit obligations under the Companies Act 2006 have been met. Report P40, P41, P42, P74
Risk: Top strategic risks include utility price volatility, new policy and regulation (including Heat Network Zoning), new technology, lower than expected customer connections, and limited in-house resource at Solihull Energy Ltd. Report P77, P78, P79, P80
Climate: Phase 1 is expected to save 22,633 tCO2e over 40 years and aims to supply at least 50% of heat from low carbon sources, supporting the Council's 2041 net zero target. Report P21, P57
Equalities: A Council Fair Treatment Assessment has been carried out and will be kept under review through the operate and maintain stage. Report P82, P83, P84, P85
Who and where
Solihull Energy Ltd, the Council-owned Special Purpose Vehicle running the network Report P7
Four public sector buildings and two education campuses in Solihull town centre connecting in Phase 1 Report P8
Vital Energi Limited, the Design, Build, Operate and Maintain contractor Report P66
Future customers including commercial buildings along Homer Road, masterplan developments and educational establishments Report P27
Solihull town centre businesses and residents, through decarbonisation and energy cost effects Report P52, P53
Timeline
February 2020: EDMG Scrutiny Board and Full Cabinet endorsed the Outline Business Case Report P60
11 July 2022: Solihull Energy Limited incorporated under the Companies Act 2006 Report P38
March 2023: Resources and Delivering Value Scrutiny Board considered and Cabinet endorsed the Full Business Case Report P62
October 2023: Cabinet endorsed Solihull Energy Ltd to enter a contract with Vital Energi Limited Report P66
April 2025: Cabinet approved the 2025-2028 Business Plan and related items Report P11, P67
Late December 2025 to early March 2026: Construction side of the project hibernated while gas and electricity easements were progressed Report P33
10 December 2025: Solihull Energy Directors approved the audited 2024/25 accounts Report P42
31 December 2025: Deadline for filing audited accounts with Companies House, met ahead of time Report P42
12 March 2026: Cabinet decision date on the Business Plan 2026-27 Report P29
May and June 2026: Phase 1 customers begin to receive heat and/or power from Solihull Energy Ltd on a phased basis Report P35
July 2026: Formal handover of the Solihull energy network from Vital Energi to Solihull Energy Ltd (reprogrammed from April 2026) Report P5, P32
Plain English for the jargon
SPV (Special Purpose Vehicle): A separate company set up by the Council for a specific purpose; here, Solihull Energy Limited runs the heat network
DBOM: Design, Build, Operate and Maintain contract held with Vital Energi Limited
GHNF: Government's Green Heat Network Fund, a grant programme the project is applying to
WMCA: West Midlands Combined Authority, which runs a Building Retrofit pilot scheme the project is engaging with
Heat Network Zoning: Government regulations that will require heat networks in designated zones
MTFS: Medium Term Financial Strategy, the Council's medium-term budget and spending plan
tCO2e: Tonnes of carbon dioxide equivalent, a standard unit for greenhouse gas emissions
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
(i) That the Solihull Energy Ltd Business Plan 2026-27 be approved; (ii) That the Cabinet notes the formal handover of the Solihull energy network to Solihull Energy Ltd is planned for July 2026; and (iii) That the 2024/25 financial outturn position for Solihull Energy and the resulting audit and filing of the Annual Report & Financial Statements be noted.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
The purpose of this report is to seek Cabinet approval of the Solihull Energy Business plan 2026 – 2027.
Cabinet is asked to note the formal handover date of the Solihull energy network from Vital Energi to Solihull Energy Ltd, the position with the preparation, audit, and filing of the 2024/2025 Solihull Energy Annual Report & Financial Statements, and the 2024/2025 financial outturn position for Solihull Energy.
2. Decision(s) Recommended
That Cabinet approves the Solihull Energy Ltd Business Plan 2026-27.
That Cabinet notes the formal handover of the Solihull energy network to Solihull Energy Ltd is planned for July 2026.
That Cabinet notes the 2024/25 financial outturn position for Solihull Energy and the resulting audit and filing of the Annual Report & Financial Statements. 3. Matters for Consideration
Background
3.1.1 Solihull Energy Limited, a Council-owned Special Purpose Vehicle (SPV), is responsible for constructing and managing the Solihull Town Centre Low Carbon Energy Network.
3.1.2 The Solihull Town Centre Low Carbon Energy Network aims to decarbonise heat in the town centre and provide affordable low carbon energy. Phase 1 will connect four public sector buildings and two education campuses, with heat and power supplied from a centrally located energy centre.
3.1.3 Key objectives of the network include:
To deliver carbon savings for the network customers. To deliver carbon savings for the Council. To deliver a financial surplus to the Council over the project's 40-year lifetime. To be financially sustainable and provide reinvestment for growth of the network. To provide learning and demonstrate best practice for future low carbon energy schemes.
3.1.4 The existing Solihull Energy Business Plan (2025 -2028) was presented to Cabinet in April 2025 and was approved.
3.1.5 The 2023/2024 accounts were also presented at the same meeting with Cabinet, noting the position with the preparation, audit, and filing of the 2023/24 Solihull Energy Annual Report & Financial Statements, and the 2023/24 financial outturn position for Solihull Energy
3.1.6 The 2026-27 Business Plan in Appendices 1,2 & 3 provides the strategic approach, key milestones, financial position, future pricing strategy and expansion plans for the energy network, highlighting Solihull Energy Ltd’s commitment to delivering carbon reduction and financial sustainability.
2026/27 Solihull Energy Business Plan
3.2.1 The 2026-27 Business Plan provides an update on construction and key activities over the last year and looks ahead to the next 12 months.
3.2.2 It is a one-year Business Plan as 2026-27 is a transitional year for the company as it moves into the operational phase and there are a number of factors that will have a material impact on future financial forecasts.
3.2.3 These include:
• Confirmation/timing of new connections • The outcome of funding bids • The impact/timing of Heat Network Zones regulations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.