Cabinet, Thursday 25 June 2026 at 6.00pm

Council Plan Milestones 2026/27

Noted Executive 3 papers

AI summarySolihull Cabinet notes a delayed Council Plan refresh and agrees 24 updated milestones for 2026/27, with the refreshed plan now due in February 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRefresh timeline moved to February 2027
MoneyNo sums stated; delivery primarily from existing approved budgets
What happens nextQuarterly milestone reporting continuesQ1 to Q3 2026/27 before February 2027 plan refresh
Who it affectsCouncil directorates and Solihull residentsSeven ambitions and four enabling statements updated

What was decided

Cabinet noted the revised timeline for refreshing the Council Plan, which will now be published in February 2027 rather than the usual summer window. Report P19, P20, P21

Cabinet agreed the updated Council Plan milestones for 2026/27, taking the total from 27 in 2025/26 to 24 for the new year. Report P4, P23, P24

Why

The May 2026 all-out elections and the September 2026 Corporate Peer Challenge made the usual summer refresh impractical, so the timetable has been aligned with the Medium-Term Financial Strategy cycle. Report P19, P20

Of the 27 previous milestones, 21 were updated, 6 dropped and 3 new ones added after assessment by Senior Responsible Officers and review by the Corporate Leadership Team. Report P14, P23

Alternative options considered by the Corporate Leadership Team for refresh timing and milestone monitoring were not viewed as offering the same advantages as the preferred approach. Report P26, P28

What happens next

Senior Responsible Officers will rate financial and delivery status of each milestone each quarter using the Red Amber Green dashboard reviewed by the Assistant Directors Group and the Corporate Leadership Team. Report P15, P52

The Council Plan refresh will be developed with the usual member and stakeholder consultation and published in February 2027. Report P20

Resources and Delivering Value Scrutiny Board will continue to scrutinise Council Plan delivery, having last reviewed 2025/26 progress on 16 March 2026. Report P16, P41

Options considered

  • Chosen: Delay the Council Plan refresh to align with the Medium-Term Financial Strategy cycle and the September 2026 Corporate Peer Challenge, with milestones updated to 2026/27. All-out elections in May 2026 made the usual summer timetable unreasonable and the new timetable allows peer challenge findings to inform the refresh. Report P19, P20, P26, P28

Implications

  • Financial: Milestones are mainly delivered from existing approved budgets, but transformation, regeneration and climate work will need further investment through separate business cases; some milestones are expected to deliver efficiency savings, cost avoidance and demand management reflected in the MTFS. Report P44, P45, P46
  • Risk: Risks include slippage in transformation, uncertainty over external funding, and cost pressures from inflation and market conditions, managed through existing programme and financial monitoring. Report P47, P52
  • Legal: The Council Plan sets strategic priorities but is not itself legally binding; each milestone will be subject to specific legal duties when delivered. Report P49, P50
  • Equalities: Delivery carries a Public Sector Equality Duty under the Equality Act 2010, supported by Fair Treatment Assessments across relevant programmes. Report P53

Who and where

  • Solihull residents, including children and young people with SEND and adults using social care services Report P34, P35, P43
  • Council directorates responsible for delivering the seven ambitions Report P11, P32, P33, P34, P35, P36, P37, P38
  • Partner organisations including the West Midlands Combined Authority, the Integrated Care Board and community partners in Chelmsley Wood, Smith's Wood, Kingshurst and Arden Cross Report P32, P36, P57, P58

Timeline

  • 8 July 2025: Solihull Council Plan 2025-30 approved by Council Report P6
  • 16 March 2026: Resources and Delivering Value Scrutiny Board scrutinised 2025/26 Council Plan progress Report P16, P41
  • May 2026: All-out elections held for Solihull Council Report P19
  • September 2026: Corporate Peer Challenge findings expected Report P19
  • October / November 2026: Families First reforms to be implemented Report P34
  • December 2026: Draft Local Plan to be submitted Report P38
  • Q1, Q2 and Q3 of 2026/27: Quarterly milestone reporting to continue Report P20
  • February 2027: Council Plan refresh to be published Report P20
  • March 2027: Priority areas for corporate transformation to be agreed Report P33

Plain English for the jargon

  • MTFS: Medium-Term Financial Strategy, the council's financial planning document that allocates resources to priorities.
  • RAG: Red Amber Green rating system used to assess delivery and financial status of programmes.
  • CLT: Corporate Leadership Team, the council's senior management group.
  • CPC: Corporate Peer Challenge, an external review of council performance and governance.
  • SEND: Special Educational Needs and Disabilities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that: 1. the timeline for a Council Plan refresh be noted. 2. the updated Council Plan milestones for 2026-27 be agreed.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Cabinet

Executive summary

This report sets out the timeline for a Council Plan refresh and the updated Council Plan milestones for the municipal year 2026- 27.

2. Decision(s) Recommended

To note the timeline for a Council Plan refresh.

To agree the updated Council Plan milestones for 2026-27.

3. Matters for Consideration

The Solihull Council Plan 2025-30 was approved by Council on 8 July 2025. It sets the strategic direction for the Council and sets out the key things that we want to deliver in line with our vision: “Solihull – a great place to live, work, invest and enjoy”. The plan sits alongside the Medium-Term Financial Strategy (MTFS), which allocates and aligns financial resources to Council priorities.

The Council Plan covers the major steps that we need to take in order to achieve our ambitions, and how we will take those steps. It is structured around 7 ambitions and 4 enabling statements which outline out how we will work to deliver those ambitions – these ways of working apply to everything we do:

• Achieve financial sustainability

• Deliver our transformation programme • Take preventative action and reduce inequalities

• Work with partners to get the best for Solihull

The high-level ambitions in the Council Plan are cascaded down through the Council. Each directorate has a plan or series of plans which will consider how Council Plan and directorate priorities are achieved, how statutory responsibilities are delivered, and how this translates into targets for services.

The Plan on a Page (Appendix A) summarises the main components of the plan.

4. How is Council Plan delivery assessed?

For 2025/26, following consultation with Resources and Delivering Value Scrutiny Board on Council priorities, the Corporate Leadership Team (CLT) agreed 27 Council Plan milestones, which were grouped under the 7 Council Plan ambitions. The milestones represent specific, tangible things that we will do within the given financial year to move us towards achieving our ambitions.

Each quarter, Senior Responsible Officers rate the financial and delivery status of each milestone and identify any associated risks. A Red Amber Green (RAG) rating system is used to assess the delivery and financial status of each programme, including risk outlook and any associated issues, alongside qualitative commentary. This information is collated into a dashboard which is subject to quarterly review and challenge by the Assistant Directors Group and the CLT.

Progress made in delivering against the Council Plan is scrutinised annually by Resources and Delivering Value Scrutiny Board, most recently on 16 March 2026.

In a typical year, the Council Plan is refreshed and published in the summer months, after which new milestones are agreed and reported on. This process ensures that Council Plan milestones are aligned with a refreshed plan.

5. Council Plan refresh

In view of the all-out elections for Solihull Council in May 2026, and the need to plan for different outcomes and scenarios, the CLT agreed that it would not be reasonable to work towards the typical timetable for a Council Plan refresh in the summer months. That decision also presented the opportunity to align the future timetable for a Council Plan refresh with the Medium-Term Financial Strategy cycle and ensure that any findings from Solihull’s Corporate Peer Challenge (CPC) in September 2026 could be taken into consideration.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 133 KB Download
PDF
Appendix BAppendix B 338 KB Download
PDF
Council Plan Milestones 2026/27Report 228 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
JH
Jackie HillOfficer, expected
RW
Rachael WardOfficer, expected
KG
Councillor Karen Grinsell Leader, Lead Member for Children & EducationCommittee Member, present
HD
Councillor Heather Delaney Deputy Leader, Economy, Business & Skills PortfolioCommittee Member, present
TD
Councillor Tony Dicicco Adult Social Care and Health PortfolioCommittee Member, present
KH
Councillor Ken Hawkins Environment & Infrastructure PortfolioCommittee Member, apologies
AM
Councillor Andy Mackiewicz Climate Change & Planning PortfolioCommittee Member, present
MP
Councillor Mark Parker Housing PortfolioCommittee Member, present
DP
Councillor Dave Pinwell Resources PortfolioCommittee Member, present
WQ
Councillor Wazma Qais Communities PortfolioCommittee Member, present
SG
Councillor Samantha Gethen Reform UK Group Leader (Non-Voting Member)Committee Member, in attendance
AA
Councillor Ade Adeyemo Liberal Democrat Group Leader (Non-Voting Member)Committee Member, in attendance

All 17 on the meeting page

More from Solihull Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... Approved Open
17 Sep 2026 Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... Agreed Open
17 Sep 2026 Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... Decided Open
23 Jul 2026 Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... Approved Open
23 Jul 2026 Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... Agreed Open