Inspiring Innovation - Quarterly Update

Decided Executive 2 papers

AI summarySomerset Council Executive reviewed the Q4 2025/26 update on the Inspiring Innovation transformation programme, covering Wave 1 delivery, Wave 2 development, culture work and a target £135m financial benefit by 2030.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo formal resolution; Executive noted the update
Money£45m investment, £135m target benefitAcross five-year programme, 3:1 return target
What happens nextNext quarterly updateConsolidated programme risk report to follow
Who it affectsAll council services and residentsWhole-council transformation programme

What was decided

The Executive reviewed and commented on the Inspiring Innovation Programme quarterly update for Q4 of 2025/26. Report P1, P5

No new decisions were taken; the report is an update on Wave 1 delivery, Wave 2 development and Wave 3 long-term planning. Report P2, P13

The Executive noted five additional transformation business cases approved by Full Council on 4 March 2026 are now in Wave 1 delivery. Report P11, P24

Why

The programme was established in July 2025 to change how the council works, deliver services and leads change, aiming to improve services, enhance workforce experience and support long-term financial sustainability. Report P7

Transformation is identified as a key mitigating action for the council's strategic risk on medium-term financial sustainability, against a forecast budget gap growing from £25.000m in 2026/27 to £88.368m by 2030/31. Report P56, P59

Sustainable improvement depends on strengthening organisational culture, leadership capability and the emerging Council Vision, alongside delivering individual projects. Report P3, P44

What happens next

Wave 1 projects continue in delivery across Adults and Housing, Children's Services, Place, Finance and Cross-Cutting themes. Report P17, P18, P22

Around 11 active Wave 2 opportunities are being developed into early business cases for 2027/28, with each proposal subject to governance and capacity checks before moving to delivery. Report P18

A consolidated programme risk report on principal delivery risk IIPROG001 will be reported to Scrutiny and Executive at the next quarterly update. Report P57

The money

  • £45m Investment funds allocated across the five-year programme, primarily via Flexible Use of Capital Receipts Report P47
  • £135m Minimum financial benefit the programme must deliver to achieve a 3:1 return on investment by 31 March 2030 Report P50
  • £25.000m Forecast cumulative MTFP budget gap in 2026/27 Report P59
  • £88.368m Forecast cumulative MTFP budget gap by 2030/31 Report P59
  • £20.260m Expected one-off investment in Adult Social Care and Housing transformation Report P49
  • £23.0m Total Adult Social Care and Housing transformation opportunities reflected in the MTFP Report P49
  • £7.5m Adult Social Care and Housing expected recurrent transformation opportunity Report P21, P49
  • £1.8m My Life My Future programme savings Report P21
  • £4.0m Prevention and Demand Management savings Report P21
  • £6.3m Working Age Adults savings Report P21
  • £0.6m Reducing Homelessness savings, plus £1.6m cost avoidance Report P21

Options considered

  • Chosen: Review and comment on the Inspiring Innovation Programme quarterly update. Standard quarterly scrutiny of programme progress by the Executive Report P5

Implications

  • Financial: Programme investment of £45m over five years is primarily funded through Flexible Use of Capital Receipts from asset sales, with recurrent savings accruing across the life of the MTFP. Report P47, P48
  • Financial: Target 3:1 return on investment requires delivery of at least £135m of financial benefit by 31 March 2030. Report P50
  • Risk: Inspiring Innovation is a mitigating action for strategic risk ORG009 on medium-term financial sustainability. Report P56
  • Risk: Principal programme risk IIPROG001 on transformation delivery was reviewed by the Board in April 2026, with existing mitigations judged sufficient at this stage. Report P57
  • Staffing: A Leadership and Management Development Programme is out to procurement, aiming to upskill over 800 managers with Newton support. Report P44
  • Staffing: A 'Change Makers' network is being set up with an initial estimate of up to 30 colleagues, with plans to expand to up to 300 once established. Report P44
  • Other: Officers report no legal, procurement, HR, equalities, community safety, climate change, health and safety, health and wellbeing or social value implications from this update report. Report P60, P62, P64, P65, P67, P68, P70, P72, P74

Who and where

  • Adults and Housing service users, including working-age adults and those at risk of homelessness Report P25, P26, P27
  • Children in care, foster carers and children with special educational needs Report P30, P32
  • Council workforce, including over 800 managers targeted by the leadership development programme Report P44
  • Somerset Council as a whole, given the transformation is structured across five themes Report P17

Timeline

  • July 2025: Inspiring Innovation whole-council transformation programme established Report P7
  • 7 January 2026: Previous quarterly update considered by the Executive Report P10, P75
  • 11 February 2026: Electronic briefing on AI and Data Science provided to Members Report P42
  • January to March 2026: Period covered by this Quarter 4 update Report P1, P10
  • 4 March 2026: Full Council approved five additional transformation business cases as part of the 2026/27 budget Report P11, P76
  • 1 April 2026: Staff survey launched as first stage of the culture diagnostic Report P44
  • 29 April 2026: Scrutiny Committee for Corporate and Resources scheduled to consider the update Report P53
  • May 2026: Planned use of an AI tool to support in-depth staff interviews for the culture diagnostic Report P44
  • 6 May 2026: Executive considered the Q4 update at this meeting
  • 31 March 2030: Deadline for achieving the 3:1 return on investment with at least £135m of financial benefit Report P50

Plain English for the jargon

  • MTFP: Medium Term Financial Plan, covering 2026/27 to 2030/31 in this report.
  • Wave 1: Approved transformation projects now in delivery, including business cases approved by Full Council on 4 March 2026.
  • Wave 2: Around 11 active opportunities being developed into business cases for 2027/28, subject to governance checks.
  • Wave 3: Medium to long-term council-wide redesign shaped by the emerging Council Vision and priorities.
  • FUoCR: Flexible Use of Capital Receipts, the mechanism allowing the council to fund genuinely transformative work from asset sales.
  • RoI: Return on investment, with the programme targeting a 3:1 ratio by 2030.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item153

Resolved

The Executive reviewed and commented on the Inspiring Innovation Programme quarterly update report.
Word for word from the decision Somerset published for this meeting. Source: democracy.somerset.gov.uk

Follow this further

Built from Somerset's papers

What the report saysPro

Report to Executive, 12 pages

Executive summary

This report provides the Quarter 4 (January–March 2026) update on the Council’s Whole‑Council Transformation Programme, Inspiring Innovation.

Since the previous update in January 2026, five more transformation business cases have been approved by Full Council in March 2026 and are now in delivery as part of Wave 1, alongside existing transformation activity. At the same time, a structured process for developing Wave 2 opportunities has been set up, and initial planning for Wave 3 is starting, targeting long-term council-wide changes aligned with the organisation’s emerging vision. This update report highlights achievements during quarter four of the 2025/26 period. This includes delivery against ongoing 2025/26 transformation projects, the development and approval of priority wave 1 business cases for 2026/27, as well as the identification of wave 2 transformation opportunities for 2027/28.

The report also highlights progress in cultural development, leadership capability and the emerging Council Vision, recognising that sustainable improvement depends on strengthening organisational capability as well as delivering individual projects.

These activities demonstrate our integrated approach to managing delivery, opportunity identification, and transformation development concurrently and our continued commitment to delivering swift and effective transformation and change. Recommendations

Executive Committee is asked to review and comment on the Inspiring Innovation Programme quarterly update report.

Reasons for Proposals

This report provides an update to the Executive on the progress of the Inspiring Innovation Programme. Established in July 2025, this whole council transformation programme aims to fundamentally change how we work, deliver services, and lead change. It brings together people, technology, and new ways of working to unlock potential and deliver better outcomes at lower costs. The Programme’s objectives are to improve services, enhance workforce experience, and support long-term financial sustainability.

Report Author: Sara Cretney, Service Director, Strategy, Performance and Communications / Inspiring Innovation Programme Director Contact Details: 01823 357780, [email protected] Main report and supporting information

Background and purpose of report

1. This report covers quarter four (January – March) of the 2025/26 period. In the last update report to Executive in early January, significant progress was described including the appointment and onboarding of Newton Consulting as our Strategic Transformation Partner, the launch of the whole Council diagnostic, and the commitment to developing and approving additional transformation business cases as part of the 2026/27 budget setting process.

2. At Full Council on 4 March 2026, five additional transformation business cases were approved as part of the 2026/27 budget. These are described below and are now in delivery as part of the wave 1 transformation activity.

3. The immediate priorities for Inspiring Innovation are centred on three main areas:

1) delivering approved transformation activity (wave 1) 2) developing the next pipeline of business cases for 2027/28 (wave 2) 3) progressing the longer‑term vision for the future council (wave 3)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Inspiring Innovation Governance DiagramAppendix A 1 pages Download
PDF
Inspiring Innovation: Quarterly UpdateReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Somerset

Search all
  1. Inspiring Innovation - Quarterly UpdateThis decision
  2. Inspiring Innovation Quarterly UpdateDecided
  3. Inspiring Innovation Quarterly UpdateNoted
  4. Inspiring Innovation - My World My TomorrowApproved
  5. Inspiring Innovation including Modern Data and AI Council - Quarterly UpdateDecided
  6. Inspiring Innovation - Quarterly UpdateDecided

More from Somerset Executive

All decisions
MeetingDecisionOutcome
7 Oct 2026 Scrutiny Recommendations to ExecutiveThe Executive Resolved to:- 1) Consider the comments and recommendations made by the four Scrutiny Committees during ... Decided Open
7 Oct 2026 Somerset Parking Review and Charging Principles – October UpdateHaving been duly proposed and seconded, the Executive Resolved to:- a) Approve a 10% increase in all existing car par... Approved Open
7 Oct 2026 Somerset’s Local Transport Delivery Plan 2026-27 to 2029-30Having been duly proposed and seconded, the Executive Resolved to:- · agree the final Local Transport Delivery Plan, ... Agreed Open
7 Oct 2026 Adoption of reviewed Street Naming and Numbering Policy for Somerset CouncilHaving been duly proposed and seconded, the Executive Resolved to approve and adopt the Street Naming and Numbering P... Approved Open
7 Oct 2026 Medium Term Financial Plan Update 2027-28 to 2031-32Having been duly proposed and seconded, the Executive Resolved to:- a) Note the updated budget gap. b) Note the revis... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies