AI summarySomerset Council's Scrutiny Committee noted Inspiring Innovation Q1 progress and asked the Executive for clarity on savings tracking, alignment with Building Better Finance and the Best Value Notice, and a future update on Modern Data and AI.
Who it affectsCouncil staff, residents, third-party suppliersWhole-council programme covering adults, children, place, finance
What was decided
The Committee noted the progress made in delivering the Council's Transformation Programme for Quarter 1. Report P1, P7
The Committee requested further information on how Inspiring Innovation, Building Better Finance and the Council's response to the Best Value Notice align, with clearer reporting between programme governance boards and Scrutiny. Report P19, P68
The Committee supported live dashboard reporting and verbal updates at meetings, and asked for a written response on progress against original transformation savings assumptions and targets, plus a future update on the Modern Data and AI Programme. Report P22, P38, P58
Why
Quarter 1 marks a shift from mobilisation to delivery, with six Wave 1 programmes improving, twelve stable and one showing emerging concern. Report P2, P20
Three programmes continue to need management attention: Homes and Horizons, Room to Grow and Fleet, all currently rated Red or Red/Amber. Report P3, P24
Evidence of impact is emerging, including reduced temporary accommodation costs, completed Phase 1 of SAP SuccessFactors, a 55.3% reduction in EHCP drafting time and identified third party expenditure reductions. Report P4, P21, P22, P31, P39
What happens next
In Quarter 2 (July to September 2026) the programme will focus on strengthening governance, embedding RACI accountability, automating dashboards and improving benefits tracking. Report P50, P51
Recruitment of additional transformation business partners and an integrated resource plan are planned to address the increased organisational capacity and capability risk. Report P52, P79
Building Better Finance was approved as a Lead Member Key Decision on 23 June 2026; the My World, My Tomorrow Executive Key Decision is scheduled for 5 August 2026. Report P19
The money
£52.118m Total transformation investment programme 2025/26 to 2029/30 Report P58
£20.803m Committed transformation spend, up by £0.288m for additional Business Partner resource Report P58
£2.02 Current return for every £1 invested across committed transformation projects, below the £3:£1 target Report P58
£3.86 Return for every £1 invested on other projects, above target Report P58
£0.550m-£0.750m Third Party Spend potential expenditure reductions identified, against a £0.500m target Report P22, P31, P58
£0.100m Cashable financial benefits from Third Party Spend for inclusion in the MTFP 2027/28 Report P22
£0.200m Forecast additional income from improved housing benefit claim processes Report P38
£0.150m Estimated benefit from reduced housing voids via data-sharing tools Report P38
£45.734m Investment funds allocated across the five-year programme, mainly via Flexible Use of Capital Receipts Report P69
£6.384m Additional investment funds allocated to March 2027 through capitalisation direction Report P69
£135m Minimum financial benefit needed to achieve the 3:1 ROI by 31st March 2030 Report P70
£25.000m Cumulative Medium Term Financial Plan gap in 2026/27 Report P84
£95.806m Cumulative MTFP gap by 2031/32 Report P84
Options considered
Chosen: Note the Q1 progress report and consider whether to make recommendations to Executive. Committee resolved to note progress and forwarded five areas of comment to Executive for consideration Report P7
Implications
Financial: Programme is a key mitigating action for strategic risk ORG009 on medium-term financial sustainability, with a 3:1 ROI target requiring £135m of benefit by 31 March 2030. Report P70, P75
Risk: Four programme risks are being managed (IIPROG001, 006, 007, 008); the organisational capacity risk (IIPROG007) increased during Quarter 1 due to scale, pace and competing priorities. Report P78, P79
Staffing: Culture Discovery engaged more than 1,800 colleagues and the Elevate Leadership and Management Development Programme will support over 820 managers. Report P41, P42
Other: The Council continues to rely on Exceptional Financial Support and faces a growing MTFP gap, increasing the importance of recurring savings and large-scale transformation. Report P67, P84
Legal: Officers confirm the update report has no direct legal, procurement, HR, equalities, community safety, climate, health and safety, health and wellbeing or social value implications. Report P85, P87, P89, P90, P92, P94, P96, P98, P100
Who and where
Children and families, including those in or at risk of entering care Report P23, P33, P34
Council staff, including over 820 managers on the Elevate programme Report P42
Residents in or at risk of homelessness, with reduced temporary accommodation costs reported Report P21, P31
SEND families benefiting from the EHCP Digital Drafting Assistant Report P31, P39
Housing benefit claimants and tenants in social housing voids Report P38
Third party suppliers, with the Council managing approximately £700m of annual third-party expenditure Report P49
Adults receiving prevention, working age adult and demand management services Report P25
Timeline
July 2025: Inspiring Innovation Programme established Report P9
4 March 2026: Revenue and Capital Budget 2026/27, Council Tax 2026/27 and MTFS 2026/27 to 2030/31 approved by Full Council Report P83
3 June 2026: Medium Term Financial Strategy update 2027-28 to 2031-32 approved by Executive Report P83
23 June 2026: Building Better Finance approved as a Lead Member Key Decision Report P19
8 July 2026: Informal transformation workshop held with Scrutiny Members on Wave 2 business cases Report P72
5 August 2026: My World, My Tomorrow Executive Key Decision scheduled Report P19
12 August 2026: Scrutiny Committee Corporate and Strategic reviewed and noted the Q1 update
July to September 2026: Quarter 2 priorities focused on governance, capacity, benefits tracking and engagement Report P50
31st March 2030: Target date for delivering the 3:1 transformation return on investment Report P70
Plain English for the jargon
Direction of Travel (DoT): Quarterly assessment of whether a programme's delivery confidence is improving, stable or showing emerging concern
RAG status: Red, Amber, Green delivery rating, with Blue used for closed programmes or phases
Best Value Notice: Statutory notice issued by government requiring the Council to improve value for money in its services
MTFP / MTFS: Medium Term Financial Plan or Strategy covering several years of council budgets
KPI: Key Performance Indicator used to measure service improvement and outcomes
EHCP: Education, Health and Care Plan for children and young people with special educational needs and disabilities
FUoCR: Flexible Use of Capital Receipts, allowing revenue transformation costs to be funded from asset sales
ROI: Return on Investment, here measured as pounds of financial benefit per pound invested
SAP SuccessFactors: HR and payroll software system; Phase 1 was completed in Quarter 1
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30
Resolved
The Scrutiny Committee Corporate and Strategic reviewed the and RESOLVED to note the progress made in delivering the Council's Transformation Programme. In addition, the Committee requested that the following comments be considered by the Executive as part of the ongoing delivery of the programme: · The Committee requested further information regarding how the Inspiring Innovation Programme, the Building Better Finance Programme and the Council's response to the Best Value Notice will align and avoid duplication of activity, governance and reporting and greater clarity regarding the reporting relationship between programme governance boards and Scrutiny. · The Committee strongly supported the use of live dashboard reporting, where appropriate, to provide Members with the most up-to-date programme information and the provision of verbal updates at meetings where there have been significant developments since the publication of reports. · The Committee requested a written response setting out progress against the original transformation savings assumptions and targets approved as part of the programme, including whether the programme remains on track to deliver the anticipated savings and how these compare with the original projections. · The Committee sought greater clarity regarding how transformation savings are calculated, monitored and evidenced, including assurance that reported savings are deliverable and sustainable. · The Committee requested a future update on the Modern Data and Artificial Intelligence Programme, including progress, outcomes achieved, benefits realised and future opportunities.
Word for word from the decision Somerset published for this meeting.Source: democracy.somerset.gov.uk
Report to Scrutiny Committee - Corporate and Strategic, 17 pages
Executive summary
This report provides the Quarter 1 update on Inspiring Innovation, Somerset Council's whole-council transformation programme, established to deliver large- scale, sustainable improvement across services: improving outcomes for residents, strengthening organisational capability and supporting the Council’s long-term financial sustainability.
Quarter 1 marks an important shift from programme mobilisation, discovery and business case development into delivery, benefits realisation and measurable impact. Across Wave 1, the direction of travel assessment shows that six programmes improved their delivery confidence, twelve remained stable and one programme showed emerging concern.
Three programmes continue to require management attention due to their current delivery status: 1. Homes and Horizons 2. Room to Grow 3. Fleet.
Evidence of impact is emerging across the portfolio: reduced temporary accommodation costs through the Reducing Homelessness programme; completed reunifications and increased fostering capacity within Children's Services; successful delivery of SAP Success Factors Phase 1; productivity improvements through the Education, Health and Care Plan Digital Drafting Assistant; and expenditure reduction opportunities identified through Third Party Spend.
The programme is also providing greater transparency around areas requiring intervention, including Homes and Horizons, Room to Grow and Fleet.
Quarter 1 also saw continued development of the Wave 2 pipeline, including progression of Building Better Finance, My World, My Tomorrow and Third Party Spend towards formal approval and implementation. These opportunities are central to the Council's wider improvement journey, financial sustainability and response to the Best Value Notice and previous statutory recommendations. The overall position is one of increasing delivery confidence, stronger evidence of impact and a growing focus on implementation, benefits realisation and long-term sustainability. Scrutiny is invited to review progress and consider whether any recommendations should be made to Executive.
Recommendations
Scrutiny Committee is asked to review and comment on the Inspiring Innovation Programme progress report and consider whether there is a need for any recommendation to Executive.
Reasons for Proposals
The report provides an update to the Corporate and Strategic Committee on the progress of the Inspiring Innovation Programme. Established in July 2025, the Programme aims to fundamentally change how we work, deliver services, and lead change. It brings together people, technology and new ways of working to unlock potential and deliver better outcomes at lower costs. The Programmes objectives are to improve services, enhance workforce experience, and support long-term financial sustainability.
Report Author: Sara Cretney, Service Director, Strategy Performance and Communications / Inspiring Innovation Programme Director Contact Details: 01823 357780, [email protected] Main report and supporting information
Background and purpose of report
1. This report provides the Quarter 1 update on Inspiring Innovation, Somerset Council’s whole-council transformation programme. It marks an important shift: Inspiring Innovation is moving from set-up, discovery and business case development into delivery, benefits realisation and measurable impact.
2. Inspiring Innovation exists to improve outcomes for residents, strengthen organisational capability, reduce avoidable cost pressures and support the Council's long-term financial sustainability.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Scrutiny Committee - Corporate and Strategic at Somerset and we tell you when its next papers are published, before the meeting rather than after it.
Reserves Review 2026/2027 UpdateThe Scrutiny Committee Corporate and Strategic considered the report and RESOLVED to note the outcome of the initial ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.