CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Somerset Council
Audit Committee, Thursday 28 May 2026 at 10.00am

Treasury Management Year End Report 2025-2026

Decided Finance 1 paper

AI summarySomerset Audit Committee notes the 2025/26 Treasury Management outturn and recommends it to the Executive, with debt reduced by £13.096m and borrowing costs under budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMembers happy with the recommendations
Money£13.096m debt reductionNet debt down; interest under budget by £13.849m
What happens nextFull Council meetingReport to go to next available Full Council
Who it affectsCouncil finances and external bodiesBorrowing, investments and managed cash

What was decided

The committee noted the year-end position as compliant with the approved Treasury Management Strategy and within the prudential indicators set in that strategy. Report P4

The committee noted the reduction in borrowing costs and that the General Fund proportion of financing costs to net revenue stream was 6.97%, against the CIPFA recommended maximum of 10%. Report P5, P59

The committee approved the report as compliant with the CIPFA Code of Practice for Treasury Management and recommended it to Full Council at the next available meeting. Report P6

Why

The Local Government Act 2003 and the CIPFA Code of Practice require an annual Treasury Management report after the close of the year. Report P7, P8

All borrowing and investment activity in 2025/26 remained within the agreed Prudential Limits and the approved strategy, so risks have been well managed. Report P2, P11, P221

What happens next

The report will go to Full Council at the next available meeting, as required by the Code. Report P6, P8

Borrowing requirements will be monitored closely and financing arranged in line with the borrowing strategy, with credit and market conditions kept under constant review. Report P71, P236

The money

  • £13.096m Net reduction in total debt during 2025/26 Report P55
  • £20.495m General Fund debt interest paid in year, £13.849m under the £34.344m revised budget Report P56
  • £8.90m Net investment income after external investor shares, £2.40m over the £6.50m budget Report P140
  • £33.308m Capital receipts from sale of investment properties in 2025/26, with a net gain on disposal of £4.715m Report P214
  • £9.25m Pooled fund investments liquidated during 2025/26, realising a small loss of £16,442 Report P132, P137
  • 4.07% Average rate on total borrowing at 31 March 2026, down from 4.17% a year earlier Report P51, P55
  • 6.97% General Fund financing costs as a proportion of net revenue stream, against the CIPFA 10% maximum Report P5, P59
  • 4.54% Combined investment return for 2025/26 on an average balance of £213.34m Report P139

Options considered

  • Chosen: Adopt the Treasury Management review for 2025/26. The review is a regulatory requirement under the CIPFA Code and Local Government Act 2003; no alternative was considered. Report P240
  • Rejected: Consider any other options. The report states that no other options were considered because adoption of the review is a regulatory requirement. Report P240

Implications

  • Legal: Treasury Management must operate within the legal and regulatory parameters set out in the summary and in the Treasury Management Practice documents. Report P249
  • Risk: There are no specific risk implications from this outturn report; ongoing treasury risks are managed through the strategy and TMPs and remained within agreed limits in 2025/26. Report P2, P221, P247
  • Financial: General Fund interest paid was £13.849m under the revised budget, and investment income was £2.40m over budget, easing in-year pressure on the revenue account. Report P56, P140
  • Staffing: There are no HR or workforce implications from this report. Report P252

Who and where

  • Somerset Council taxpayers and service users, through reduced financing costs as a share of net revenue stream Report P5, P59
  • The Council itself, as borrower and investor, with total debt of £706.282m at 31 March 2026 Report P55
  • External bodies whose cash the Council manages, including Exmoor National Park Authority, South-West Councils, the Society of County Treasurers, PACCTS and the Police and Crime Commissioner for Avon and Somerset Report P123, P158, P159
  • The Local Enterprise Partnership partners, as the residual LEP Growth Deal balances were returned to participating authorities at year-end Report P123, P160
  • Subsidiary company Aspen Housing and Development Limited, in which the Council is sole shareholder Report P202, P204
  • SSDC Opium Power Ltd and its subsidiaries, in which the Council has a joint venture interest through legacy South Somerset District Council Report P215, P216

Timeline

  • April 2025: US trade tariff 'Liberation Day' caused market disruption Report P16, P126
  • 1 April 2025: Start of 2025/26 financial year; Bank Rate 4.50%, 10-year gilt 4.65% Report P23, P272
  • May, August and December 2025: Three Bank Rate reductions from 4.50% to 3.75% Report P125
  • December 2025: Mid-year Treasury Management review presented to Full Council Report P14
  • End of February 2026: Start of the Middle East conflict, which pushed gilt yields and PWLB rates sharply higher Report P17, P23
  • 31 March 2026: End of financial year: Bank Rate 3.75%, 10-year gilt 4.86%, 20-year gilt 5.45% Report P23, P272
  • 28 May 2026: Audit Committee considered the year-end report and recommended it to the Executive Report P244
  • Next available meeting: Report to be presented to Full Council Report P6

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy, which issues the Code of Practice for Treasury Management.
  • PWLB: Public Works Loan Board, a UK government lender to local authorities.
  • MRP: Minimum Revenue Provision, the revenue charge to repay past capital debt.
  • CFR: Capital Financing Requirement, the Council's underlying need to borrow for capital purposes.
  • LOBO: Lender Option Borrower Option loan, where the lender can periodically change the rate.
  • MHCLG: Ministry for Housing, Communities and Local Government, which issues the investment guidance.
  • Prudential Indicators: Limits set by the Council to control borrowing, investment and treasury risk.
  • HRA: Housing Revenue Account, the ringfenced account for council housing.
  • SONIA: Sterling Overnight Index Average, the benchmark overnight interest rate for sterling.
  • EIP: Equal Instalment of Principal, a PWLB loan repaid in equal capital instalments.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item140

Resolved

RESOLVED Members were happy with the recommendations for the Executive.
Word for word from the decision Somerset published for this meeting. Source: democracy.somerset.gov.uk

Follow this further

Built from Somerset's papers

What the report saysPro

Report to Audit Committee, 35 pages

Executive summary

The report is a summary of the treasury management activity of Somerset Council for the financial year 2025/26, in compliance with the CIPFA Code of Practice and the Local Government Act 2003.

All borrowing and investment activities have been undertaken in accordance with the approved strategy and remain within the agreed Prudential Limits set. Accordingly, risks to the Council have been well managed.

Recommendations

Audit Committee is asked to note the recommendations for Executive which are:

1. Notes the year end position and that all activity during the year was compliant with the approved Treasury Management Strategy, and within the prudential indicators set in that Strategy.

2. Notes the reduction in borrowing costs and for the General Fund the 6.97% proportion of net revenue stream, which compares well with the CIPFA recommended maximum of 10%.

3. Approves the report as being compliant with the CIPFA Code of Practice for Treasury Management and recommends it to Full Council at the next available meeting. Reasons for Proposals

The Local Government Act 2003 requires the Council to operate the overall treasury function in accordance with the CIPFA Code of Practice for Treasury Management in the Public Services.

The Code requires Full Council to receive as a minimum, an annual strategy and plan in advance of the year, a mid-year review, and an annual report after its close. This is the full year review for the 2025/26 financial year.

Authors: Alan Sanford, Principal Investment Officer Paul McClean Senior Accountant Capital & Projects Contact Details: [email protected] or (01823) 359585 [email protected] or (01823) 219521 Background and purpose of the report

Purpose of the report

1. In compliance with the requirements of the Chartered Institute of Public Finance and Accountancy’s (CIPFA) Code of Practice this report provides Members with a summary of the treasury management activity during the 2025/26 financial year. It gives a summarised account of Treasury Management activity and outturn for the year and ensures Somerset Council (SC) is embracing Best Practice in accordance with the CIPFA recommendations.

2. During the year, all Council treasury management policies, practices, and activities remained compliant with all relevant statutes and guidance, namely Ministry for Housing, Communities and Local Government (MHCLG) investment guidance issued under the Local Government Act 2003, the CIPFA Code of Practice for Treasury Management, and the CIPFA Prudential Code.

3. The MHCLG’s Guidance on Investments reiterates security and liquidity as the primary objectives of a prudent investment policy. All investments were compliant with guidance issued by the MHCLG, with the investment strategy agreed, and activities conducted within the procedures contained in the Treasury Management Practices.

Treasury Management Strategy

4. The Treasury Management Strategy Statement for 2025/26 sets out the framework and boundaries for the treasury management activities during the year. This alongside the Prudential Indicators were considered by Audit Committee and approved by Full Council in February and March 2025. The mid- year review was presented to Full Council in December 2025.

Economic environment and background

5. The financial year was largely dominated by two periods of significant uncertainty and volatility. The first being the US trade tariff ‘Liberation Day’ in April 2025 and the second was the middle east conflict at the end of February 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management Year End Report 2025-2026Appendix 35 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Somerset

Search all
  1. Treasury Management Year End Report 2025-2026This decision
  2. Annual Treasury Management Year-End Report 2025/26Noted
  3. Treasury Management Year End Report (Outturn)Noted
  4. Medium Term Financial Reports: Treasury Management Strategy & Policy 2025/26; Flexible Use of Capital Receipts 2025/26 and MRP Policy 2024/25 and 2025/26Agreed
  5. Annual Treasury Management Mid-Year Report 2024-25Approved
  6. Treasury Management Mid Year Report 2024-25Noted

More from Somerset Audit Committee

All decisions
MeetingDecisionOutcome
27 Aug 2026 Progress against the Recommendations of the Auditor's Annual Report 2024-25RESOLVED That the report be noted. ... view the full minutes text for item 160. Noted Open
27 Aug 2026 External Audit Progress for Somerset Council's 2025-26 AccountsRESOLVED That the report be noted. Noted Open
27 Aug 2026 External Audit Regaining Assurance Strategy for Somerset CouncilRESOLVED That the report be noted. Noted Open
27 Aug 2026 Audit Committee WorkplanRESOLVED That the Workplan be noted, subject to the removal of the internal update report on progress against the Aud... Noted Open
25 Jun 2026 Strategic Risks and High Scoring Tactical and Operational Risks Q4 Update 2025-26RESOLVED To note the strategic risk profile, operational risks and mitigating actions. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies