Resolved
RESOLVED To note the report.
AI summarySomerset Council's Audit Committee notes progress on contract management, including 71% of contract managers trained and responses to five SWAP audit findings.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED To note the report.
Good contract management within the public sector is well recognised as being essential in ensuring value for money for taxpayers and high-quality public services. Effective contracting is crucial to the council’s performance. Contracts play a critical role in the delivery of Somerset Council services in all Directorates.
Grant Thorntons report stated, "The Council should ensure that robust contract management and procurement processes are in place end embedded across the organisation to ensure that value for money is achieved from procurement exercises and that the expected benefits are realised from contracts with third parties.”
Procurement has implemented measures to ensure that the Council’s contract managers receive training, with the dual objectives of strengthening their commercial capability and improvement of contract management practice in line with the enhanced requirements introduced by the Procurement Act 2023 and the Council’s Contract Management Framework.
Improving contract management offers savings and ensures the timely and complete delivery of the Council’s procured requirements. World Commerce and Contracting identified that 9% of revenue is lost due to poor contract management. Research from Weshare found that organisations save 2% of their annual costs through good contract management. This underscores the value of investing time and effort to improve contract management.
Members of the Audit Committee are asked to:
1. Note the status of Contract Management at Somerset Council and the progress made including against SWAP recommended actions. 2. Continue to support the development of Contract Management within Somerset Council. Reasons for Proposals
This report provides an update to Audit Committee on the progress made in the development of contract management within the Council and the results of the recent SWAP Audit of contract management.
Report Author: Gary Coleman Contact Details: [email protected] Main report and supporting information
Background and purpose of report
Introduction
1. The Procurement Act 2023 requires the Council to comply with contract management requirements including, transparency notices covering change control, contract performance and contract termination.
2. Since 30th May 2024 officers are mandated to complete the Contract Management Foundation level accreditation online training provided by the Government Commercial College (GCC) or equivalent training delivered by Procurement.
3. In preparation for the Procurement Act a new procurement system, Proactis was implemented by Procurement. The Proactis system extended functionality to include contract management. This system enables the recording of key contract information such as the applicable terms, contract duration, who manages the contract, contract changes and performance.
4. A new Contract Management Framework was adopted by the Executive 7th April 2025.
5. Procurement has introduced a new handover process to ensure all procurements have a formal handover to a named contract manager who must have completed the required training.
6. Procurement has implemented the Credit Industry Fraud Avoidance System (CIFAS) system, procurement are trained in the use of the systems and documents are updated to enable the necessary checks as part of due diligence.
7. The Procurement team continues to engage with the Contract Management Pioneer Programme rolled out by Local Partnerships in conjunction with the Local Government Association.
Context
8. The Procurement team has made significant changes to contract management within the Council since the last report to Audit Committee. Policy, Process, System, Templates, Guidance and Training are all updated and rolled out.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Recommendations and Actions TrackerAppendix 2 | 6 pages | Download |
PDF |
Contract Management Update and Appendix 1Appendix | 18 pages | DownloadRead as text |
Follow Audit Committee at Somerset and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Aug 2026 | Progress against the Recommendations of the Auditor's Annual Report 2024-25RESOLVED That the report be noted. ... view the full minutes text for item 160. | Noted | Open |
| 27 Aug 2026 | External Audit Progress for Somerset Council's 2025-26 AccountsRESOLVED That the report be noted. | Noted | Open |
| 27 Aug 2026 | External Audit Regaining Assurance Strategy for Somerset CouncilRESOLVED That the report be noted. | Noted | Open |
| 27 Aug 2026 | Audit Committee WorkplanRESOLVED That the Workplan be noted, subject to the removal of the internal update report on progress against the Aud... | Noted | Open |
| 25 Jun 2026 | Strategic Risks and High Scoring Tactical and Operational Risks Q4 Update 2025-26RESOLVED To note the strategic risk profile, operational risks and mitigating actions. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.