Executive, Wednesday 2 September 2026 at 10.00am

A38 Major Road Network (MRN) - Funding Allocation, DfT funding Acceptance and Contract Award

Approved Executive 2 papers

AI summarySomerset Council Executive approves £7,347,994 of local funding and delegates acceptance of £8,639,034 of DfT funding for the A38 Major Road Network scheme covering four junctions on the A38 corridor.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedExecutive approved virement and delegated contract award
Money£18,784,786 total funding packageIncluding £7,347,994 Somerset Council and £8,639,034 DfT
What happens nextAccept DfT award and award contractsSubject to DfT approval of Full Business Case
Who it affectsA38 corridor users and communitiesEdithmead, Cross, Rooksbridge, Strawberry Line

What was decided

The Executive approved the virement of £7,347,994 of Somerset Council funding to the A38 MRN scheme, comprising £5,580,000 from the Local Transport Grant and £1,767,994 from the Previous Majors Underspend. Report P5

The Executive agreed that the scheme will be delivered through the existing M5 Junction 23 (Dunball) NEC contract and the Highways New Assets Framework. Report P6, P67

The Executive delegated authority to the Section 151 Officer and Service Director for Infrastructure and Transport to accept £8,639,034 of further DfT funding through North Somerset and to award contracts for the Somerset elements. Report P7, P8

Why

Approval enables formal allocation of Somerset Council funding, readiness to proceed to delivery following DfT approval, and timely contract award. Report P11

The Full Business Case demonstrates the scheme offers high value for money with an adjusted Benefit Cost Ratio of 2.78, and the scheme supports planned housing and employment growth along the A38 corridor. Report P1, P41

Not proceeding would risk losing significant external investment while Somerset Council would still need to deliver an alternative intervention at Edithmead to meet National Highways requirements. Report P23, P24

What happens next

The Section 151 Officer will accept the DfT funding award through North Somerset once the Full Business Case is approved and enter into associated funding agreements. Report P7, P12

The Service Director for Infrastructure and Transport will award contracts, issue task orders, and enter into any ancillary agreements necessary to deliver the Somerset elements. Report P8

Construction will follow the existing M5 Junction 23 (Dunball) NEC contract for Cross Junction and Edithmead, with Rooksbridge and Strawberry Line delivered through the Highways New Assets Framework via Task Order call-offs. Report P27, P67

The money

  • £7,347,994 Somerset Council virement to A38 MRN scheme Report P5, P49
  • £5,580,000 From the Local Transport Grant Report P5, P46
  • £1,767,994 From the Previous Majors Underspend Report P5, P48
  • £8,639,034 DfT MRN funding to be accepted through North Somerset (construction) Report P7, P45, P51
  • £521,158 DfT MRN funding already received Report P45
  • £9,160,192 Wider DfT funding profile including FBC development costs Report P45, P51
  • £1,658,600 Previously allocated Somerset Council funding from 2020/21 Report P45, P54
  • £618,000 Section 106 developer contribution Report P47, P55
  • £18,784,786 Total identified funding provision for the scheme Report P49, P50
  • £17,836,058 Full Business Case project cost estimate including scheme development and construction Report P50
  • £16,828,685 Construction-only estimate for Somerset elements Report P51
  • £8,189,651 Local contribution to construction estimate Report P51
  • £948,728 Surplus of identified funding over current FBC project cost estimate (approx 5.3%) Report P50

Options considered

  • Rejected: Option 1: Do nothing. Would lose significant external DfT investment, fail to deliver planned improvements, and Somerset Council would still need an alternative intervention at Edithmead to meet National Highways requirements. Report P21, P23, P24
  • Chosen: Option 2: Commit to local contributions, accept DfT funding, and proceed with delivery. Secures external investment, delivers road safety and active travel improvements, uses established procurement arrangements, and represents best overall value for money. Report P25, P26, P27, P28

Implications

  • Financial: Total funding package of £18,784,786 exceeds FBC project cost estimate by £948,728, providing contingency against inflation and timing risks; no new borrowing requirement beyond existing capital programme. Report P50, P56
  • Risk: Failure to approve could result in loss of DfT funding, increased future liabilities for National Highways growth mitigation, and loss of existing delivery mechanisms under the Dunball contract. Report P39, P40
  • Legal: The Council has statutory powers to deliver the highway improvements and enter into funding arrangements; necessary land interests for Somerset elements have been secured. Report P62, P65
  • Equalities: Improved crossing facilities and active travel infrastructure expected to benefit older, younger, and disabled users; construction-phase disruption to be mitigated through traffic management. Report P73, P119, P120
  • Climate: Somerset Council has embedded NEC climate change obligations and a Carbon Management Plan; construction will generate unavoidable carbon emissions to be monitored and reduced throughout delivery. Report P83, P84, P85, P87
  • Staffing: No direct HR implications; scheme to be managed through existing officer resources with capacity to be kept under review. Report P70, P71

Who and where

  • Users of the A38 corridor between M5 Junction 22 and Bristol Airport Report P15, P16
  • Residents and businesses in the Brent and Cheddar divisions Report P35, P102
  • Pedestrians, cyclists, and disabled users along the A38 Report P73, P119, P120
  • National Highways (M5 Junction 22 and Strategic Road Network) Report P22, P23
  • Bristol Airport and local businesses Report P33, P98
  • Axbridge, Cheddar, and surrounding parish communities Report P34, P36

Timeline

  • 2023: DfT approved the Outline Business Case Report P16
  • 2024 to 2026: Somerset Council and North Somerset Council jointly completed the Full Business Case Report P16
  • July 2025: Officer Non-Key Decision approved exercise of option within M5 Junction 23 (Dunball) NEC contract to deliver A38 MRN elements Report P67
  • May 2026 MRN funding profile: Funding profile reflects the May 2026 MRN funding profile for the Somerset elements Report P43, P44
  • June 2026: Full Business Case submitted to DfT Report P16
  • July 2026: DfT approval of Full Business Case pending at time of report Report P12, P45
  • 2 September 2026: Executive considered and approved the funding allocation and delegations

Plain English for the jargon

  • MRN: Major Road Network, a DfT classification of strategically important local authority roads
  • BCR: Benefit Cost Ratio, a measure used in business cases to compare scheme benefits to costs
  • NEC: New Engineering and Construction contract, a standard form of contract used in construction
  • FBC: Full Business Case, the final stage of DfT business case approval
  • virement: The reallocation of approved budget from one purpose to another within the capital programme
  • Section 151 Officer: The council officer with statutory responsibility for financial administration
  • Section 106: Planning obligation contributions from developers towards infrastructure
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Having been duly proposed and seconded, the Executive Resolved to:- · Approve the virement and therefore allocation of £7,347,994 of Somerset Council funding to the A38 MRN Scheme within the existing approved Capital Programme as per below: - £5,580,000 from the Local Transport Grant - £1,767,994 from the Previous Majors Underspend · Agree that the schemes (generally in accordance with the plans shown in appendices) would be delivered through the existing M5 Junction 23 ( Dunball ) NEC contract and the Highways New Assets Framework which had been competitively tendered with a scope that enabled the works to be included. · Delegate authority to the Section 151 officer, in consultation with the Service Director for Infrastructure and Transport to accept a further DfT funding award through North Somerset of £8,639,034 and enter into any associated funding agreements required to facilitate delivery of the scheme. · Delegate authority to the Service Director Infrastructure and Transport to award contracts, issue task orders and enter into any ancillary agreements, deeds, variations and contractual documentation necessary to deliver the Somerset elements of the scheme. · Note that the Local Authority contribution to the scheme had already been identified within the Council's approved Capital Programme.
Word for word from the decision Somerset published for this meeting. Source: democracy.somerset.gov.uk

Follow this further

Built from Somerset's papers

What the report saysPro

Report to Executive, 24 pages

Executive summary

The A38 Major Road Network (MRN) scheme is a jointly promoted transport infrastructure project between Somerset Council and North Somerset Council that will deliver improvements at Edithmead Roundabout, Cross Junction, Rooksbridge and the Strawberry Line crossing area. The scheme is designed to improve road safety, journey time reliability, active travel connectivity and network resilience along the A38 corridor, whilst supporting planned housing and employment growth and addressing impacts on the Strategic Road Network. The Full Business Case submitted to the Department for Transport demonstrates that the scheme offers High Value for Money, achieving an adjusted Benefit Cost Ratio (BCR) of 2.78.

The total Somerset Council project cost submitted through the Full Business Case is £17.836m, including both construction and pre-construction costs. The scheme is supported by a funding package comprising Department for Transport MRN funding, previously approved local authority capital funding, Local Transport Grant funding, Section 106 contributions and previous Major Schemes programme underspend. Approval of this decision will enable Somerset Council to accept external funding, commit the funding required to deliver the Somerset elements of the scheme and utilise established procurement and delivery arrangements, including the existing M5 Junction 23 (Dunball) contract, to progress construction.

This report seeks approval from the Executive to approve the acceptance of funding from the Department for Transport, and subsequent allocation of this together with existing capital funding to the delivery of Somerset elements of the A38 MRN scheme, at a total funding package of £18.785m. It also seeks the delegation of acceptance and award of contract to the Section S151 Officer and Service Director Infrastructure and Transport.

Recommendations

The Executive is recommended to:

• Approve the virement and therefore allocation of £7,347,994 of Somerset Council funding to the A38 MRN Scheme within the existing approved Capital Programme as per below: o £5,580,000 from the Local Transport Grant o £1,767,994 from the Previous Majors Underspend

• Agree that the schemes (generally in accordance with the plans shown in appendices) will be delivered through the existing M5 Junction 23 (Dunball) NEC contract and the Highways New Assets Framework which have been competitively tendered with a scope that enables these works to be included.

• Delegate authority to the Section 151 officer, in consultation with the Service Director for Infrastructure and Transport to accept a further DfT funding award through North Somerset of £8,639,034 and enter into any associated funding agreements required to facilitate delivery of the scheme.

• Delegate authority to the Service Director Infrastructure and Transport to award contracts, issue task orders and enter into any ancillary agreements, deeds, variations and contractual documentation necessary to deliver the Somerset elements of the scheme.

• Note that the Local Authority contribution to the scheme has already been identified within the Council's approved Capital Programme.

Reasons for Proposals

Approval of this decision will enable formal allocation of Somerset Council’s funding, ensure readiness to proceed to delivery following DfT approval and allow timely contract award and scheme delivery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A38 Major Road Network (MRN): Funding Allocation, DfT funding Acceptance and Contract AwardReport 24 pages DownloadRead as text
PDF
Appendices: SC Construction Programme and Schemes designsReport 11 pages Download

At this meeting

Whole meeting

On this subject at Somerset

Search all
  1. A38 Major Road Network (MRN) - Funding Allocation, DfT funding Acceptance and Contract AwardThis decision
  2. Major Planning Application 36.22.00024 Inwood Farm, Cannington Road, Nether Stowey, Bridgwater, TA5 1HYDeferred
  3. Major Planning Application 09/21/00030 - Land Off A38, Bristol Road And A39, Bath Road And Bounded By M5 Motorway And Railway Line, Bristol Road, Bridgwater, SomersetApproved
  4. Major Planning Application 34/23/00007 Land To The North Of, Olivers Road, Middlezoy, BridgwaterApproved

More from Somerset Executive

All decisions
MeetingDecisionOutcome
7 Oct 2026 Scrutiny Recommendations to ExecutiveThe Executive Resolved to:- 1) Consider the comments and recommendations made by the four Scrutiny Committees during ... Decided Open
7 Oct 2026 Somerset Parking Review and Charging Principles – October UpdateHaving been duly proposed and seconded, the Executive Resolved to:- a) Approve a 10% increase in all existing car par... Approved Open
7 Oct 2026 Somerset’s Local Transport Delivery Plan 2026-27 to 2029-30Having been duly proposed and seconded, the Executive Resolved to:- · agree the final Local Transport Delivery Plan, ... Agreed Open
7 Oct 2026 Adoption of reviewed Street Naming and Numbering Policy for Somerset CouncilHaving been duly proposed and seconded, the Executive Resolved to approve and adopt the Street Naming and Numbering P... Approved Open
7 Oct 2026 Medium Term Financial Plan Update 2027-28 to 2031-32Having been duly proposed and seconded, the Executive Resolved to:- a) Note the updated budget gap. b) Note the revis... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies