What was decided
Approved the Full Business Case and the establishment of the Academy as a contractual joint venture between Somerset Council, Somerset NHS Foundation Trust and NHS Somerset Integrated Care Board. Report P2, 1.6
Approved property arrangements under which the Council retains freehold of the former Bridgwater Hospital site and Somerset NHS Foundation Trust acts as Host Organisation and anchor tenant for the operational Academy. Report 2.1, 2.3
Approved a £2.5 million increase in the Academy capital budget funded by reallocating Local Regeneration Fund resources from Tonedale, up to £609,400 for SCAPE pre-construction services, and up to £80,000 from earmarked reserves for mobilisation, all subject to MHCLG agreement. Report 9.1
Why
The Academy is a flagship workforce, skills, innovation and regeneration programme that addresses shared recruitment, retention and training challenges across Somerset's health and social care system. Report P1, P4
It supports delivery of the original Levelling Up Fund programme secured in 2022, while refurbishing and bringing the vacant Grade II listed former Bridgwater Hospital back into productive use. Report 1.1, 1.8, P30
A contractual joint venture was assessed as the preferred delivery model, providing the strongest strategic fit and long-term sustainability while letting partners retain their statutory responsibilities. Report 1.6, 1.7, P30, P33
What happens next
Finalise and complete the Collaboration Agreement, with delegated authority to the Head of Legal Services in consultation with the Section 151 Officer and Executive Director Adult Social Care and Housing. Report P2, 1.9
Continue design development, surveys, value engineering and planning work, with planning committee consideration anticipated in November 2026 and construction contract award programmed for March 2027. Report P50, P60
Procure the main construction contract and any enabling or early works through the SCAPE framework, with delegated authority to the Executive Director Community, Place and Economy subject to MHCLG agreement and the approved funding envelope. Report P60
The money
- £2.5 million Increase in Academy capital budget, reallocated from Tonedale Local Regeneration Fund allocation
- £609,400 Design development and pre-construction services through SCAPE Construction Framework
- £80,000 Mobilisation and implementation activity from earmarked reserves
- £21.216 million Current approved Academy capital budget before the £2.5m increase Report 9.1
- £19.716 million Levelling Up Fund grant within the approved budget Report 9.1
- £1.5 million Section 106 funding within the approved budget Report 9.1
- £5.649 million Expenditure to 31 March 2026 Report 9.1
- £15.567 million Available budget balance from 2026/27 onwards before the £2.5m increase Report 9.1
- £19.7 million Levelling Up Fund grant secured through the 2022 bid Report 1.1
- in excess of £10,000 per month Ongoing security and insurance costs for the vacant former hospital site Report P24
Options considered
- Chosen: Reallocate £2.5m of Local Regeneration Fund resources from Tonedale Mill and progress the revised Academy scheme (capital funding). Allows delivery of the revised scheme, protects the Levelling Up Fund investment and removes the vacant heritage liability, with Tonedale confirmed as not needing the full original allocation. Report P30
- Rejected: Do nothing (capital funding). Would jeopardise the Levelling Up Fund programme, leave a deteriorating Grade II listed building on the Council's hands and continue holding costs in excess of £10,000 per month. Report P24
- Rejected: Progress the project without additional funding (capital funding). Heritage requirements identified through engagement with Historic England could not be met, risking planning refusal and missing the March 2027 Local Regeneration Fund commitment deadline. Report P26
- Rejected: Further scope reduction and value engineering (capital funding). Most savings already identified, and further reductions would undermine Academy functionality and leave parts of the listed building undeveloped, generating ongoing costs. Report P28
- Chosen: Contractual joint venture between the Council, SFT and ICB (delivery model). Provides the strongest strategic fit, operational flexibility and long-term sustainability while allowing each partner to retain its statutory responsibilities. Report P33
- Rejected: Do nothing (delivery model). Would fail to address the workforce, skills, innovation and regeneration objectives underpinning the Levelling Up Fund programme. Report P32
- Rejected: Enhancement of existing training arrangements without a dedicated Academy (delivery model). Would not provide a coordinated Somerset-wide approach or deliver the regeneration benefits tied to the former hospital site. Report P32
- Rejected: Outsourced third-party delivery model or a separate corporate joint venture entity (delivery model). Less partner control, additional procurement or legal complexity, and the benefits did not outweigh the additional governance burden. Report P33
Implications
- Financial: Council capital budget for the Academy rises by £2.5 million, funded through Local Regeneration Fund reallocation from Tonedale; additional earmarked reserve spend of £80,000 for mobilisation; lease income and sinking fund arrangements to be established.
- Legal: A Collaboration Agreement between the Council, Somerset NHS Foundation Trust and NHS Somerset Integrated Care Board will be finalised, with the Council retaining freehold of the site and entering into lease arrangements with the Trust as Host Organisation and anchor tenant. Report 2.1, 2.3
- Risk: Major risks include construction cost overruns, heritage and planning delays, programme slippage beyond the Local Regeneration Fund milestones, resource capacity for mobilisation, partnership governance, and long-term financial sustainability of the Academy. Report 8.2, 8.3, P55, P73
- Staffing: Mobilisation activity covers recruitment of key Academy positions, training prospectus development, Learning Management Systems and partnerships with education providers, supported by a Joint Academy Board, Programme Delivery Group and workstream groups. Report 1.9, 2.6, P66
- Other: Subject to MHCLG agreeing a compliant funding and expenditure strategy for managing project expenditure under the revised programme; wider estate regeneration opportunities at the former hospital are being kept separate from the Academy business case. Report P18, P60
Who and where
- Somerset Council (as freeholder, accountable body for the Levelling Up Fund and Local Regeneration Fund, and joint venture partner) Report 2.1, 9.1
- Somerset NHS Foundation Trust (as Academy Host Organisation, anchor tenant and joint venture partner) Report 2.1
- NHS Somerset Integrated Care Board (as joint venture partner) Report P2, 1.6
- Health and social care workforce, learners, apprentices and employers across Somerset Report P9, P10
- Residents of Bridgwater and the wider Somerset area, including those with special educational needs and disabilities
- Tonedale Mill project, whose Local Regeneration Fund allocation is being reduced by £2.5 million Report 1.8, P30
Timeline
- 2022: Somerset Council submitted its Levelling Up Fund bid, securing £19.7 million for the former Bridgwater Hospital site Report 1.1
- 31 March 2026: Cumulative Academy expenditure of £5.649 million reported Report 9.1
- May 2026: Executive approved the Statement of Intent and Heads of Terms for the Academy partnership Report P4
- 2 September 2026: Executive approved the Full Business Case, joint venture, property arrangements, budget increase and delegations
- November 2026: Planning committee consideration and planning approval anticipated Report P50
- 2026 and early 2027: Completion of design development, planning and procurement activities
- March 2027: Main construction contract award currently programmed Report P60
- late 2028: Practical completion of the redeveloped Academy currently anticipated
Plain English for the jargon
- MHCLG: Ministry of Housing, Communities and Local Government, the Government department responsible for the Levelling Up Fund and Local Regeneration Fund programmes.
- Levelling Up Fund (LUF): Government capital funding programme; the 2022 Somerset bid secured £19.7 million for the former Bridgwater Hospital site.
- Local Regeneration Fund (LRF): Somerset Council fund that provides flexibility to reallocate resources between regeneration projects; the source of the £2.5 million reallocation from Tonedale Mill.
- SFT: Somerset NHS Foundation Trust, the Academy's proposed Host Organisation and anchor tenant.
- ICB: NHS Somerset Integrated Care Board, the third joint venture partner.
- SCAPE Construction Framework: A public sector procurement framework through which Morgan Sindall has been appointed for pre-construction services on the Academy.
- Section 106 funding: Developer contributions secured through planning obligations, providing £1.5 million of the current Academy capital budget.
- Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of the Council's financial affairs.
- RIBA Stage 2: Concept Design stage of the Royal Institute of British Architects' work stages, used here to describe the cost planning and value engineering work that identified the additional capital requirement.