South Holland District Council
Planning Committee, Wednesday 7 January 2026 at 6.30pm

H16-0854-25

Agreed Planning 1 paper

AI summarySouth Holland Planning Committee approved a Section 73 modification at Castle Sports Complex in Spalding, allowing changes to approved plans and wording of conditions 3, 7 and 25 for the leisure centre redevelopment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSection 73 modification to existing consent H16-0462-24
MoneyNot stated
What happens nextDevelopment must begin by 17 January 2028Per condition 1
Who it affectsCastle Sports Complex, Albion Street, SpaldingSite users, nearby residents and highway network

What was decided

The committee agreed to grant permission subject to the conditions set out in section 9.0 of the report, moved by Councillor Bingham and seconded by Councillor Beal. Report 8.1, 9.0

The modification varies condition 2 to allow amended plans and varies conditions 3, 7 and 25 to allow wording changes, while keeping the rest of the original permission H16-0462-24 intact. Report 9.0, P4

Work must start no later than 17 January 2028, with the development carried out strictly in line with the listed approved plans and supporting documents. Report P3, P4, P5

Why

The changes only amend the approved drawings list and the wording of three conditions, with the underlying scheme and its assessments already considered acceptable under the original consent. Report 9.0, P4

The conditions continue to manage construction impact, highway safety, drainage, noise, landscape and tree protection, and require an Employment, Skills and Local Procurement Strategy. Report P6, P7, P8, P9, P10, P12, P13, P15, P16, P17

The committee accepted the officer recommendation to approve with conditions, applying South East Lincolnshire Local Plan 2019 policies and the National Planning Policy Framework December 2024. Report 8.1, P7, P9, P10, P11, P12, P13, P14, P15, P16, P17

What happens next

Before first use of each phase, the access, parking and turning areas shown on the approved site plan must be completed and kept available. Report P6, P7

No occupation is allowed until the local planning authority certifies that the public highway works at the Albion Street access and The Green junction are complete. Report P11

Before any plant is installed, details of fixed machinery noise must be submitted and approved, and the noise level must not exceed background by more than 5dB(A) on residential boundaries. Report P12

Options considered

  • Chosen: Approve subject to conditions as recommended by the Development Manager. Recommended in the officer report and the application only amends plans list and wording of conditions 3, 7 and 25 Report 8.1, 9.0

Implications

  • Legal: Permission is granted under Section 73 of the Town and Country Planning Act, varying conditions on the existing H16-0462-24 consent while leaving the original permission otherwise in force. Report P3, P4, 9.0
  • Risk: Construction noise, traffic and hours are controlled through the construction method statement, construction management plan and restricted working hours already approved under H16-0462-24. Report P8, P9
  • Risk: Surface water drainage must follow the scheme approved under H16-0742-25 and foul water drainage must follow H16-0462-24 to manage flood and pollution risk. Report P10, P13
  • Risk: Plant and machinery noise must be limited to 5dB(A) above background at residential boundaries not in the applicant's ownership. Report P12
  • Other: Retained trees must be protected during construction with chestnut pale fencing at the spread of the crown, with restrictions on storage, burning and services. Report P17
  • Other: An Employment, Skills and Local Procurement Strategy must be implemented to secure local employment and training opportunities. Report P17

Who and where

  • Users and operators of Castle Sports Complex, Albion Street, Spalding Report 9.0, P4
  • Residents living near the Castle Sports Complex site Report P7, P9, P12, P14
  • People using the surrounding highway network, including Albion Street and The Green junction Report P11
  • Local job seekers and training providers covered by the employment and skills strategy Report P17

Timeline

  • 2026-01-07: Planning Committee resolved to grant permission subject to conditions.
  • Not later than 17th January 2028: The development must be begun, otherwise the permission expires. Report P3
  • Monday to Friday 08.00 to 18.00 and Saturday 08.00 to 13.00 only: Demolition, ground works, construction, deliveries and collections are permitted; no work on Sundays or public holidays. Report P9
  • Before first use of Phase 1: Access, parking and turning facilities for Phase 1 must be completed and retained. Report P6
  • Before first use of any later phase (2, 3 or 4): Access, parking and turning facilities for that phase must be completed and retained. Report P7
  • Before occupation of any building: Public highway works at the Albion Street access and The Green junction must be certified complete by the local planning authority. Report P11

Plain English for the jargon

  • Section 73 modification: An application to vary or remove conditions attached to an existing planning permission, while keeping the original consent otherwise in force.
  • 3G ATP: Third generation artificial turf pitch, a full size floodlit sports pitch surface.
  • IOGA: Informal Outdoor Games Area, an outdoor space for casual sport and play.
  • H&WH building: The Health and Wellbeing Hub building shown in the approved plans.
  • CEMP / Construction Phase Plan: Documents setting out how construction work will be managed to control noise, dust, traffic, drainage and site safety.
  • Biodiversity Net Gain: A requirement for development to leave the natural environment in a measurably better state than before, assessed in a BNG report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item37

Resolved

AGREED: That permission be granted subject to the conditions outlined at section 9.0 of the report. (Moved by Councillor Bingham, Seconded by Councillor Beal)
Word for word from the decision South Holland published for this meeting. Source: democracy.sholland.gov.uk

Follow this further

Built from South Holland's papers

What the report saysPro

Report to Planning Committee, 23 pages

SOUTH HOLLAND DISTRICT COUNCIL

Report of: Lead Development Management Planner (Interim) - BBC & SHDC

To: Planning Committee - 07 January 2026

(Author: Mark Niland - Planning Officer)

Purpose: To consider Planning Application H16-0854-25

Application Number: H16-0854-25 Date Received: 10 September 2025

Application Type: SEC 73 MODIFICATION

Description: Demolition of existing swimming pool building following the construction of a two storey extension including basement area to existing Castle Sports Complex building to provide new and upgrade indoor leisure and health related facilities including two new swimming pools, plant area and changing rooms. Reconfiguration of existing building to provide new and upgraded sports facilities and physical activity facilities and related supporting services. Provision of a new 3G artificial turf pitch (ATP), an Informal Outdoor Games Area (IOGA), other outdoor play areas, an informal running trail/track, a health and well being garden and an outdoor splash pad relating to the new swimming pool. The provision of supporting infrastructure including additional car parking and landscaped areas - Approved under H16-0462-24. Modification to Condition 2 to allow amendments to previously approved plans & modification to Conditions 3, 7 & 25 to allow amendment to wording

Location: Castle Sports Complex Albion Street Spalding

Applicant: South Holland District Council Agent: JEH Planning Ltd

Ward: Spalding Castle Ward Councillors: Cllr G J Taylor

You can view this application on the Council's web site at http://planning.sholland.gov.uk/OcellaWeb/planningDetails?reference=H16-0854-25

1.0REASON FOR COMMITTEE CONSIDERATION

1.1The proposal which is presented before committee is a Section 73 application. It requires consideration by committee because the application site is a major development and on council owned land.

2.0PROPOSAL

2.1This is an application made under Section 73 of the Town & Country Planning Act 1990 (as amended). Planning permission was achieved under planning application H16-0462-24, for:

Demolition of existing swimming pool building following the construction of a two storey extension including basement area to existing Castle Sports Complex building to provide new and upgrade indoor leisure and health related facilities including two new swimming pools, plant area and changing rooms. Reconfiguration of existing building to provide new and upgraded sports facilities and physical activity facilities and related supporting services. Provision of a new 3G artificial turf pitch (ATP), an Informal Outdoor Games Area (IOGA), other outdoor play areas, an informal running trail/track, a health and well being garden and an outdoor splash pad relating to the new swimming pool. The provision of supporting infrastructure including additional car parking and landscaped areas. 2.2 Background

2.3Planning permission was granted in January 2025 for the redevelopment and expansion of Castle Sports Centre, including demolition of the existing swimming pool and construction of a new leisure hub comprising two new pools, reconfigured indoor sports and fitness facilities, outdoor play and recreation areas, and a new 3G pitch, together with associated access, parking and landscaping. The approved scheme forms part of a wider masterplan, including a future extra-care development on the site of the demolished pool, and was developed with Levelling Up funding to deliver enhanced health, wellbeing and community leisure provision for Spalding and the wider district.

2.4This application seeks to make amendments to that approval, which include Modification to Condition 2 to allow amendments to previously approved plans & modification to Conditions 3, 7 & 25 to allow amendment to wording.

2.5Key Proposed Changes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
H16-0854-25Report 23 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 17 attended
BA
Councillor Bryan AlcockCommittee Member, present
JA
Councillor James AveryChairman, present
AC
Councillor Allan C BealVice-Chairman, present
HJ
Councillor Henry J W BinghamCommittee Member, present
CJ
Councillor Christopher J T H BrewisCommittee Member, present
AC
Councillor Anthony CassonCommittee Member, present
SH
Councillor Sophie HutchinsonCommittee Member, present
TS
Councillor Thomas SneathCommittee Member, present
AC
Councillor Andrew Charles TennantCommittee Member, apologies, sent representative
JT
Councillor Jack TyrrellCommittee Member, absent
AR
Councillor Andrew Robert WoolfCommittee Member, present
PN
Phil NormanOfficer, expected

All 17 on the meeting page

More from South Holland Planning Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 H16-0515-25AGREED: That the application be approved subject to the conditions outlined at section 9.0 of the report, with streng... Agreed Open
21 Oct 2026 H16-0683-26AGREED: That the application be approved subject to the conditions outlined at section 9.0 of the report. (Moved by C... Agreed Open
21 Oct 2026 H14-0731-26AGREED: That the application be refused for the reasons stated at section 9.0 of the report. (Moved by Councillor Hut... Agreed Open
21 Oct 2026 Planning AppealsAGREED: That the report be noted. Agreed Open