DECISION: (1) That the Council Formally adopts the Capital Programme 2004/5 as set out in report FIN195 to Cabinet dated 9 th August 2004 as a policy framework document; and (2) That the Capital Programme continue to be developed in accordance with the Council’s agreed category A and B priorities. The Leader of the Council, Councillor Linda Neal, introduced the report on behalf of the Cabinet. The current programme was necessarily limited since capital expenditure may be required to facilitate the delivery of the Council’s priorities and the need to restructure the programme. The report encompassed:- · Outturn position 2003/4 · Commitment 2004/5 · Development of the Programme in the light of priority setting · The next steps During the course of the debate a Member took photographs of the meeting, it was confirmed that photographs should not be taken without permission. A number of points were raised on the programme, some members were concerned at the low level of spending on some items. In particular more detail was requested on the flood prevention programme. It was explained that smaller flood prevention works were often treated as revenue and not capital expenditure. The motion was moved and seconded.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
REPORT OF: Director of Finance and Strategic Resources
REPORT NO. FIN195
DATE: 9TH August 2004
TITLE: Capital Programme and Individual Project Update KEY DECISION OR POLICY Policy Framework Proposal FRAMEWORK PROPOSAL:
COUNCIL AIMS/PORTFOLIO Corporate Budget Setting HOLDER NAME AND DESIGNATION: CORPORATE PRIORITY: Corporate Health: Achievement of Priorities
1. Introduction
The purpose of this report is to update the Cabinet on the Capital Programme. It covers
(i) Outturn Position 2003/04 (ii) Commitment 2004/05 (iii) Development of the Programme in the light of Priority Setting. (iv) Next Steps
2. Background - 2003/04
The Council has been going through a major period of consultation on its future priorities. It is possible that capital expenditure will be required to facilitate the delivery of the priorities and therefore it is not surprising that the current programme has been limited. 3. During 2003/04, the capital programme was revised (FIN162) to ensure it reflected the position outlined in paragraph (2) and brought together all commitments for 2003/04. The outturn position for 2003/04 and revised position 2004/05 is shown at Appendix 1.
4. The authority's position for 2003/04 reflects the changes made during the year. Below is a short commentary on the main areas.
5. All work has now been completed in this area. The payments incurred during 2003/04 related to the final accounts. A small element of final payment may take place in 2004/05. Overall this area of activity will be within budget.
Flood Prevention
6. A provision of £100,000 was included within the revised budget for 2003/04. In the event £25,000 was required in 2003/04 from capital; smaller schemes have been charged to revenue accounts. Two projects need to be assessed for 2004/05, Rippingale and the Grantham Canal (Phase 2).
Public Conveniences
7. The project included within the programme was Red Lion Square, Stamford. The project will be completed in 2004/05; £15,000 was expended during 2003/04.
Other Schemes
Thurlby Youth Hostel
8. The budget allowed £125,000 for this commitment to the purchase of Thurlby Youth Hostel which is being led by the Lincolnshire County Council. At time of writing no purchase has yet taken place. The Property PMG has sent a letter to those officers leading at the County on this project to firm up the timescales and commitment of the District.
Alexandra Road Depot
9. The works to the depot for the Waste Management division have been completed.
Social and Recreation PDC (Lines 13 - 21 Appendix 1 - page 3)
Cycleways
10. The budget provision in the capital programme relates to the net expenditure on cycling initiatives. Contributions have been received over the past three years from various external partners eg Sustran; and thus the net figure of District Council expenditure is relatively small in comparison to the level in resources from the other sources. The outturn figure for 2003/04 shows £86,000 of capital expenditure incurred against the £50,000 provision. Grants from the partner agencies will be received in 2004/05, reducing the overall impact on the Council.
Leisure Equipment and Leisure Centres
11. The revised budget included the contractual commitment of £200,000 for the replacement of leisure equipment at the Meres Leisure Centre. Leisure Connections have 'called down' upon this budget during 2004/05. An assessment needs to be made as to whether the full amount will be required.
12. The capital works (provision of a lift) at the Bourne Leisure Centre to comply with the DDA legislation have been completed.
Grants and Loans
13. The capital grant to the Harrowby Community Centre was completed during 2003/04, whilst the loan to Mirlees Blackstone Social Club has been advanced in the first quarter of 2004/05.
Warm Homes Social Housing Fund GrantDECISION: That Council a) Recommend that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant whi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.