(1) Report number ENV209 by the Head of Environmental Health and Licensing detailing the Council’s performance against the 2003/04 Plan and presenting the Plan for 2004/05; (2) Statutory requirement to produce a Plan for 2004/05 and guidance from the Food Standards Agency; (3) Implementing charges for discretionary advice services could discourage the public from using this service but it could also be valuable to the Council to at least investigate its potential.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
FOOD FRAMEWORK AGREEMENT REPORT OF ACTIVITY FOR 2003/2004
Local authorities are required, by statutory Code of Practice made under the Food Safety Act 1990, to produce an Annual Framework Agreement in respect of their proposed food activities. The document must be approved by the elected Members and this has been done in respect of the period 2003/2004. This approved document sets out the proposals and plans for food safety activity for a 12-month period and detailed budget provision and other resources. It confirmed that a review comparing performance with the plan would be produced at the end of the period.
This review report confirms performance for the period 2003/2004 and compares this against the plan. Pertinent facts are that several Environmental Health Practitioners left our employment during the period, accordingly there were severe capacity issues, particularly towards the end of the period, work has therefore had to be prioritised and some activities reduced.
A contractor has been employed since January and officers have worked “overtime “ to partially address this capacity deficit. Various targets were specified in the plan, most of which were estimates based on previous years’ demand factors and were, therefore, subject to variation, the exception to this was the number of hazard generated food hygiene inspections. A total budget of £280,148 was allocated to food safety and associated activities.
Actual expenditure for the period 2003/04 was £218,487. The reduction against budget mainly arising from the resignation and non-replacement of several Environmental Health Practitioners, other expenditure was broadly in line with budget.
Food Hygiene Inspections
Inspections were divided into two categories of inspections, (1) those scheduled by hazard scores which could be confirmed, and (2) those likely to be generated, for example, at new premises:
• Those due by hazard category were confirmed to be 638 due • Those projected at new premises and other re-scheduled premises. 62 estimated
1 All inspections due by hazard category were carried out in the period, but not all other generated inspections were carried out within the period, with 20 outstanding due to staffing shortages. However, FLARE software records indicate a total of 764 food hygiene inspections were carried out in the period indicating that demand was greater than anticipated.
Other visits
Revisits to premises were projected to be 451 and 375 sampling, survey or advisory visits were also projected, giving a total projection of 826 other visits.
FLARE records indicate that 441 revisits and 442 sampling, survey or advisory visits were carried out, giving a total of 883 other visits. At the end of the period 30 revisits were outstanding due to staffing shortages but again demand exceeded projections.
Complaints
Food premises and foodstuff complaints were estimated to be 250. A total of 251 food premises and foodstuff complaints were received and resolved in accordance with section procedure.
Infectious Diseases
Infectious diseases necessitating an investigation were estimated to be 300.
A total of 283 cases were investigated in accordance with section procedures. In addition, a food poisoning outbreak associated with the consumption of egg fried rice, as well as viral outbreaks at residential and nursing homes, were investigated.
Sampling
A total of 130 food and 280 water samples, as well as 36 Biotrace/Ecolog surveys, were projected.
A total of 139 food and 229 water samples were taken, as well as 18 Biotrace/Ecolog surveys carried out. The variation in samples taken was as a result of a switch in emphasis from water to food samples, the reduction in Biotrace/Ecolog surveys, was as a result of staff shortages.
Home Authority Work
Total time allocated to ‘Home Authority’ work was estimated as 40 hours. Actual time spent was 10 hours, again as a result of staff shortages.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.