Resolved

(1) Report number CEX264 and additional information circulated prior to the meeting by the Chief Executive explaining that formal market testing will be a key component of the Council’s procurement strategy; (2) I t is understood that an incremental approach toachieving efficiency savingscan be harmful to service delivery .
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Recommendation

That the Cabinet approve this element of the Council’s procurement strategy and endorse the schedule of services for formal market testing in 2005/6 that emerges from the assessment processes.

Introduction

The formal market testing of services will be a key component of the Council’s procurement strategy. It has been brought forward to allow it to be considered before the finalisation of the Council’s service plans for 2005/6. Make or Buy?

A key component of the Council’s policy and approach to procurement is the determination of where the authority wishes to position itself on the continuum that runs between the following “poles”

Pole Explanation “Make” Clear preference for in-house provision. Services only procured if in-house provision has consistently failed, or the Council cannot recruit/retain the skills. Council considers itself to be better than any other provider at everything it does. “Buy” Clear preference for commissioning services. Services only provided in-house where there is no interest from external providers. Council considers other providers are always better than the Council.

Traditionally Councils “made” the vast majority of their services. This culture was challenged by the advent of Compulsory Competitive Tendering (CCT), which forced Councils to seek external competition.

Since the repeal of this legislation Councils have been given the discretion to make their own decisions regarding whether to “make” or “buy” services.

Where is South Kesteven on this continuum?

Perhaps the most useful indicator of the Council’s location on this continuum would be to assess the total number of staff and compare this with other authorities. Unfortunately data for other comparable authorities is simply not available. However we can track the number of staff directly employed by the District Council over the past few years as these figures are reported in the Budget book. An analysis of the past few years reveals the following:

Change from Year Full Time Part Time Casual* Total 93/4 2004/2005 441 200 82 723 8.56% 2003/2004 421 196 99 716 7.51% 2002/2003 345 191 94 630 -5.41% 2001/2002 352 181 91 624 -6.31% 2000/2001 357 231 588 -11.71% 1999/2000 365 210 575 -13.66% 1998/1999 366 183 549 -17.57% 1997/1998 397 172 569 -14.56% 1996/1997 397 204 601 -9.76% 1995/1996 413 237 650 -2.40% 1994/1995 442 232 674 1.20% 1993/1994 448 218 666

*Casuals included as Part Time until 2001/2002 As can be seen, the number of employees declined consistently during the period when Compulsory Competitive Tendering was in force to a low of 549 in 1998/9. The current figure of 723 is over 30% higher than this total. The highest increase incurred in 2003/4 when waste management was brought back in-house.

Another useful way of indicating our position is to recognise that the quantity and value of work offered to competition since the repeal of the CCT legislation is less than that achieved when this legislation was in force.

The final piece of evidence is the Council’s CPA report which concluded:

”Although the Council has a mixed economy of provision, for example internal audit, there is a preference for using a traditional contract approach and of doing things itself. There are currently no modern partnering arrangements and a new procurement strategy has not been developed or implemented after a best value review” (Para 69).

Taking all of this evidence into account it would be hard to refute that, if judged by our actions, we are closer to “Make” than we are to “Buy”.

Where do we want to be?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
South Kesteven Procurement Strategy: Selection of In-house Services to be formally Market-tested for Quality and CostReport 22 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. South Kesteven Procurement Strategy: Selection of In-house Services to be formally Market-tested for Quality and CostThis decision
  2. South Kesteven Shopfront Design Guide ReviewNoted
  3. MHCLG Statutory Consultation on Proposals for Local Government Reorganisation in Greater Lincolnshire: Response by South Kesteven District CouncilApproved
  4. Climate Action Plan for South KestevenApproved
  5. Biodiversity Action Plan for South KestevenNoted
  6. South Kesteven Design Code Statutory ConsultationApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open