Outcome from Gateway review of Priorities: Monday 18th July 2005 - report number CEX294 by the Chief Executive on behalf of the Chairman, Councillor John Kirkman.
ApprovedCommittee1 paper
Council approved this item on Thursday 8 September 2005. Below is the council's own wording, with the papers it was decided on.
DECISION: That the Council approve the outcome of the gateway review of priorities and the consequential actions as set out in report CEX294. The Chief Executive introduced report CEX294 on behalf of the Chairman of the Council. A meeting to assess Council priorities and evaluate their progress had been held on 18 th July 2005. The meeting had included the Chairman and Vice-Chairman of the Council, the Chairmen and Vice-Chairmen of the DSPs and the Leaders of each political group. One member was concerned about the methods used for consultation with vulnerable people. They were assured that a variety of consultation methods had been employed to increase accessibility. One member was concerned over the lack of robustness in the scoping procedure. It was later explained that as a Category B Priority, it had not been scoped fully. There was member concern over housing management. A member questioned why there was a lack of objective data and who was responsible for data collection. The Chief Executive stated that a number of ways of measuring satisfaction had been employed, however quantifiable data to show progress was limited. Debate ensued over the current status of the attended public toilets for Grantham. The Economic Portfolio holder assured members that toilet provision for both Grantham and Bourne was in hand and provision had been made within the 2005/06 Budget for provision of this facility in Grantham. Members were also assured that the status of toilets District-wide would be reviewed in six-months. The recommendation in report CEX294 having been moved and seconded. It was carried following a vote.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
1. A panel comprising the Cabinet along with the Chairman and Vice-Chairman of the five DSPs met to undertake a full review of the Council’s progress in achieving the Category A and B priorities approved by Council last year and in realising the savings targets set from category Z services. The meeting was chaired by the Clr John Kirkman who asked me to prepare this report to Council on his behalf.
This work was undertaken by posing three key questions for each major priority:
1. Do we have a good understanding of the problem? 2. Is there a robust and resourced action plan? 3. Is there early evidence that the outcomes in the plan are being achieved?
2. Consideration of the response to each of these questions led the review team to make an overall assessment for that priority. The results of these assessments are detailed below:
Green light Priorities which passed the Gateway review
Priority Service A Access* A Recycling A Street Scene B Affordable housing B Business Development B Diversity B Housing Management* B Planning and Development Control* B Vulnerable Persons*
Amber light priorities, which passed the gateway, review but with a warning being issued.
Priority Service Reason for Warning and Actions A Crime and ASB Action plan has been drafted but not yet approved. Plan to be approved by October. A Town-centre Action plan is currently a consultative draft, final development plan to be approved by November B Communications* Majority view that this priority may be more important and complex than originally envisaged. To refer to Engagement DSP to re- assess importance of communications and how resources allocated in the communications strategy should be deployed.
Red light priorities which failed the review
Priority Service Reason Action B LSP + Insufficient evidence To review in six months Community that the required time Strategy* outcomes have been achieved. B Public Toilets Lack of progress in To review in six months Grantham time
Realisation of savings in non-priority areas
3. The review team considered the progress of the Council in securing the targeted savings from category Z services. Although some concern was raised in regard to the first quarter results for pest control and the implications of reducing eligibility for discretionary rate relief, it was determined that there was sufficient progress to give a green light. 2 Minority Views
4. Although the majority of the assessments were unanimous there were some assessments on a majority basis. These are marked * and the additional actions reflecting these minority concerns are detailed below:
Priority and Issue Proposed Action Outcome Access (A) Some members not on the It was recognised that Green appropriate DSP do not feel the member training and that the problem or the actions development being taken have been fully programme will help, explained to them. however the Access team will also consider better ways of communicating with these members. Communications Several members felt this (B) Amber should receive a green rather than an amber light. Housing A minority view was for an To review the Management (B) amber light based on the lack of appropriateness of the Green objective data regarding targets set. progress. LSP and A minority view was for an Community amber light reflecting recent Strategy (B) Red progress Vulnerable A minority view was for an To review the scoping of Persons amber light reflecting concern this priority. over whether the scoping was robust.
Budgetary Implications arising from the Gateway Review
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Outcome from Gateway review of Priorities: Monday 18th July 2005: report number CEX294 by the Chief Executive on behalf of the Chairman, Councillor John Kirkman.Report
62Outcome from Gateway review of Priorities: Monday 18th July 2005 - report number CEX294 by the Chief Executive on behalf of the Chairman, Councillor John Kirkman.This decision
Warm Homes Social Housing Fund GrantDECISION: That Council a) Recommend that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant whi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.