CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Kesteven District Council
Planning Committee, Tuesday 16 March 2010 at 2.00pm

ENFORCEMENT ACTION

Noted Planning 1 paper

Planning Committee noted this item on Tuesday 16 March 2010. Below is the council's own wording, with the papers it was decided on.

Item132

Resolved

- 1) That authority be given for the issue of a formal caution with regard to non-compliance with some of the steps required in the enforcement notice issued in respect of the unauthorised access track at Marston Hall, Marston; 2) That authority be given for prosecution proceedings to be commenced, if the top soiling / grass seeding as required by the enforcement notice is not completed by the end of April 2010. Members considered report PLA809 from the Planning Enforcement Officer in relation to the failure to comply with the enforcement notice issued in respect of the unauthorised access track at Marston Hall, Marston. The report set out the history to the site, and detailed the current situation with regard to the breach, from which it was noted that the enforcement notice had been partly complied with, and included the planning policy position and appropriate legal advice which had been sought. The Acting Lead Professional referred to an email which had been received from the owner’s planning agent. It was suggested that Members might consider a change in the recommendation to the issue of a caution for the offence, but that if the top soiling / grass seeding was not completed by the end of April 2010, then authority be given for prosecution proceedings to be commenced. It was then accordingly proposed, seconded and agreed as recommended above.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Planning Committee

Recommendations

That the Development Control Committee authorise the Corporate Head of Sustainable Communities to commence prosecution proceedings for failure to comply with the terms of the enforcement notice dated 3 September 2007 in respect of an unauthorised access track at Marston Hall.

Purpose of the report

This report seeks to gain authorisation to prosecute for non-compliance with the terms of the enforcement notice, issued on 3 September 2007, and upheld on appeal by the Planning Inspectorate on 25 March 2008.

Page 1 3. DETAILS OF REPORT – THE PLANNING ENFORCEMENT ROLE

Applications for full planning permission to retain and construct an access track have been submitted on a number of occasions, S04/1700/57, S05/0554/57, S07/1245/57 and S09/0696/57 refer.

An enforcement notice took effect on 11 October 2007 and required:

1. Remove all imported waste material in the form of rubble and hardcore and also plastic liners from the access track, level and reseed with grass.

2. Remove from the land all materials, rubble, hardcore and plastic liners arising from compliance with the first requirement.

The time for compliance was 3 calendar months after the notice takes effect.

An enforcement appeal was submitted in respect to the enforcement notice served. This was dismissed. The Inspector noted that the works undertaken to create part of the track falls within the definition of ‘development’. Further he stated, “the case, A.1(c) is not met because the appellant has failed to provide factual evidence to demonstrate that he was undertaking any agricultural activities on the land for the purposes of trade or business before the track was constructed”. The Inspector indicated that the appellant stated, “when constructed the track was intended to have a dual use that included serving “The Lodge”, a dwellinghouse”. The Inspector concluded that as a matter of fact and degree the track was not reasonably necessary for agricultural purposes and that it did not enjoy permitted development rights.

Since the enforcement appeal dismissal the appellant has subsequently submitted 2 further planning applications to accommodate and re-locate the access track, and took into consideration the Inspectors comments. One of the planning applications was refused and the other withdrawn.

This matter has become rather protracted without a resolution. The owner has been requested to remove the track and re-instate back to agricultural land. He has been advised that failure to comply with the terms of the enforcement notice can result in prosecution proceedings being instigated. The removal of the track and re- instatement of the land back to agricultural land has currently not been undertaken.

PLANNING POLICY POSITION

The information and recommendation contained in this report are consistent with the Authority’s statutory purposes.

The following is relevant with the Saved Policies of South Kesteven District Council:

• Policy EN1 – Seeks to protect and enhance the built environment, through the reflection of appropriate designs and materials.

HUMAN RIGHTS ACT IMPLICATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ENFORCEMENT ACTIONReport 66 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. ENFORCEMENT ACTIONThis decision
  2. Enforcement action – beverley house, new cross road, stamfordAgreed
  3. Enforcement action – provision of amenity decking, great gonerby social club, 8 high street, great gonerbyAgreed
  4. Enforcement action – unauthorised demolition of listed buildings on land to the rear of four seasons, braceboroughAgreed
  5. Enforcement action – unauthorised painting of building frontage, 77-78 westgate, granthamAgreed
  6. Enforcement action – use of building as independent dwelling, 72 eastgate, deeping st jamesDecided

More from South Kesteven Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Application S26/0096Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S26/0354Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S25/1082Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning to GRANT planning permis... Agreed Open
16 Apr 2026 Application S26/0363It was agreed that Officers would consult with Grantham Civic Society were the application approved and a note would ... Agreed Open
16 Apr 2026 Application S25/2342It was AGREED to extend the meeting until 18.00 The meeting adjourned at 16.52 and resumed at 17.01. Proposal: Outlin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies