- 1) That authority be given for the issue of a formal caution with regard to non-compliance with some of the steps required in the enforcement notice issued in respect of the unauthorised access track at Marston Hall, Marston; 2) That authority be given for prosecution proceedings to be commenced, if the top soiling / grass seeding as required by the enforcement notice is not completed by the end of April 2010. Members considered report PLA809 from the Planning Enforcement Officer in relation to the failure to comply with the enforcement notice issued in respect of the unauthorised access track at Marston Hall, Marston. The report set out the history to the site, and detailed the current situation with regard to the breach, from which it was noted that the enforcement notice had been partly complied with, and included the planning policy position and appropriate legal advice which had been sought. The Acting Lead Professional referred to an email which had been received from the owner’s planning agent. It was suggested that Members might consider a change in the recommendation to the issue of a caution for the offence, but that if the top soiling / grass seeding was not completed by the end of April 2010, then authority be given for prosecution proceedings to be commenced. It was then accordingly proposed, seconded and agreed as recommended above.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
That the Development Control Committee authorise the Corporate Head of Sustainable Communities to commence prosecution proceedings for failure to comply with the terms of the enforcement notice dated 3 September 2007 in respect of an unauthorised access track at Marston Hall.
Purpose of the report
This report seeks to gain authorisation to prosecute for non-compliance with the terms of the enforcement notice, issued on 3 September 2007, and upheld on appeal by the Planning Inspectorate on 25 March 2008.
Page 1 3. DETAILS OF REPORT – THE PLANNING ENFORCEMENT ROLE
Applications for full planning permission to retain and construct an access track have been submitted on a number of occasions, S04/1700/57, S05/0554/57, S07/1245/57 and S09/0696/57 refer.
An enforcement notice took effect on 11 October 2007 and required:
1. Remove all imported waste material in the form of rubble and hardcore and also plastic liners from the access track, level and reseed with grass.
2. Remove from the land all materials, rubble, hardcore and plastic liners arising from compliance with the first requirement.
The time for compliance was 3 calendar months after the notice takes effect.
An enforcement appeal was submitted in respect to the enforcement notice served. This was dismissed. The Inspector noted that the works undertaken to create part of the track falls within the definition of ‘development’. Further he stated, “the case, A.1(c) is not met because the appellant has failed to provide factual evidence to demonstrate that he was undertaking any agricultural activities on the land for the purposes of trade or business before the track was constructed”. The Inspector indicated that the appellant stated, “when constructed the track was intended to have a dual use that included serving “The Lodge”, a dwellinghouse”. The Inspector concluded that as a matter of fact and degree the track was not reasonably necessary for agricultural purposes and that it did not enjoy permitted development rights.
Since the enforcement appeal dismissal the appellant has subsequently submitted 2 further planning applications to accommodate and re-locate the access track, and took into consideration the Inspectors comments. One of the planning applications was refused and the other withdrawn.
This matter has become rather protracted without a resolution. The owner has been requested to remove the track and re-instate back to agricultural land. He has been advised that failure to comply with the terms of the enforcement notice can result in prosecution proceedings being instigated. The removal of the track and re- instatement of the land back to agricultural land has currently not been undertaken.
PLANNING POLICY POSITION
The information and recommendation contained in this report are consistent with the Authority’s statutory purposes.
The following is relevant with the Saved Policies of South Kesteven District Council:
• Policy EN1 – Seeks to protect and enhance the built environment, through the reflection of appropriate designs and materials.
HUMAN RIGHTS ACT IMPLICATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.