SECTION 106 PROTOCOL

Approved Planning 1 paper

Planning Committee approved this item on Tuesday 16 March 2010. Below is the council's own wording, with the papers it was decided on.

Item133

Resolved

- a) That the protocol set out at 3.2 of report PLA 808, and as amended by the comments of the Legal Executive, be adopted with immediate effect. (For clarification this would apply to all new applications and requests for pre-application advice – not to applications or requests for pre-application advice already with the authority). b) That the Council’s Local List be amended to reflect these changes and that other publicity such as on the Council’s web site be given to these changes c) That an early meeting of the Planning Agent’s Forum be convened where amongst other matters this protocol can be explained. Members considered report PLA 808 from the Acting Lead Professional, in relation to a suggested protocol for the handling of Section 106 agreements. The Acting Lead Professional reminded Members that he had been requested to produce this report two or three meetings ago, following concern expressed by Members at the delays experienced when applications required such an agreement. It was noted that the practice elsewhere was for authorities to take an increasingly tougher stance against delays by applicants / developers in the completion of section 106 agreements. The suggested protocol set out in simple terms a series of steps and good practice guidance which was recommended should be followed to achieve an efficient processing of the agreements. It would be necessary for applicants’ agents and the development industry generally to be given notice of this change to the Council’s working practices and arrangements were in hand for appropriate publicity to be given, including an explanation at an early meeting of the agents’ forum. The full protocol was set out in the report and was recommended for adoption. The Legal Executive told the Committee that there was a need to be consistent in ensuring that deadlines were adhered to. At the moment a section 106 agreement could not be signed or sealed until the Committee had authorised the process, which generated a minute number for the purposes of the authority given to enter the agreement. The best way to resolve this would be for delegated powers to be given to Council officers to enter into agreements but, to allow Members to retain control and effective scrutiny, it was suggested that any application requiring a section 106 agreement would still need to be determined by the Committee. It was possible that changes would be required to the Council’s Constitution. After consideration, it was proposed, seconded and agreed that the protocol be adopted subject to the comments of the Legal Executive, and the other mechanisms for publicity be agreed.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Planning Committee

Recommendations

a) That the protocol set out at 3.2 below be adopted with immediate effect. (For clarification this would apply to all new applications and requests for pre-application advice – not to applications or requests for pre- application advice already with the authority).

b) That the Council’s Local List be amended to reflect these changes and that other publicity such as on the Council’s web site be given to these changes

c) That an early meeting of the Planning Agent’s Forum be convened where amongst other matters this protocol can be explained.

2. PURPOSE OF THE REPORT/DECISION REQUIRED

To consider a protocol for the handling of Section 106 agreements (Town and Country Planning Act 1990, as amended) and to formally endorse it

Page 1 for use with immediate effect.

3. DETAILS OF REPORT

1.1At the meeting of this Committee on 12th January 2010 concern was expressed generally by Members at the delays being experienced in bringing S.106 agreements to an early conclusion following the resolution by this Committee to grant a planning permission. In some cases many months elapse before agreements were finally concluded and the planning permission issued. This has a detrimental impact upon the authority’s performance targets which in turn can influence the amount of grant support it receives. One particular and unfortunate practice that has begun to be noticed was an increasing tendency amongst some applicants and developers to attempt to re-negotiate some of the principal terms e.g. the level of financial contributions or the “trigger” points following the Committee resolution. These would often then require to be reported back to Committee introducing more delays.

1.2The Acting Lead Professional advised Members that the practice elsewhere in other local authorities is for them to take an increasingly tougher stance against such practices. In particular many authorities had now introduced a policy that sets a deadline by which S.106 agreements are to be concluded. In addition the Committee resolution also includes a second authority for a refusal notice to be issued if the agreement is not concluded within a set timescale.

1.3This report sets out in simple terms a set of steps and good practice guidance which it is recommended should be followed to achieve an efficient processing of S.106 agreements. If these are approved it will be important to ensure that applicants, agents and the development industry generally are given early notice of this change to the Council’s working practices. Details need to be included on the Council’s web site and generally in the guidance we issue. It is also felt that this should be raised at an early meeting of the Agent’s Forum. The Council’s approved “Local List” (which sets out the minimum requirements for the various types of planning application to be accepted as valid) already includes a requirement for the Heads of Terms of S.106 agreements to be included with certain proposals. It will be necessary to revisit this to ensure that submissions are more detailed and specific requirements are included.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SECTION 106 PROTOCOLReport 92 KB DownloadRead as text

At this meeting

Whole meeting

More from South Kesteven Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Application S26/0096Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S26/0354Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S25/1082Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning to GRANT planning permis... Agreed Open
16 Apr 2026 Application S26/0363It was agreed that Officers would consult with Grantham Civic Society were the application approved and a note would ... Agreed Open
16 Apr 2026 Application S25/2342It was AGREED to extend the meeting until 18.00 The meeting adjourned at 16.52 and resumed at 17.01. Proposal: Outlin... Agreed Open