To report to Cabinet concerns over the current situation with respect to the Grantham Growth Point Agreement and request an update on the issue at the next meeting of the Committee. Members discussed the risk recommendations related to markets. The Committee asked internal audit to look into these issues and report back to the next meeting. The implementation deadline for those recommendations was 31 March 2011, after that follow-up work on progress would begin. This had been built into the audit strategy covering 2011/12. To review progress against internal audit’s recommendations on the market service at the earliest possible opportunity and update the Committee at its next meeting.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
th SOUTH KESTEVEN DISTRICT COUNCIL Internal Audit Progress Report – 17 March 2011
SOUTH KESTEVEN DISTRICT COUNCIL
Internal Audit Progress Report
Governance and Audit Committee Meeting – 17th March 2011 th SOUTH KESTEVEN DISTRICT COUNCIL Internal Audit Progress Report – 17 March 2011
CONTENTS SECTION Page 1 Introduction 1 2 Final reports issued 1 3 Work in Progress or Planned 1 4 Key Findings From Internal Audit Work 2 5 Liaison with Management 2 6 Changes to our Plan 2 Appendix A Operational Plan Performance 2010/11 3 Appendix B Reports Finalised – Summary of Key Findings 10
The matters raised in this report are only those which came to our attention during our internal audit work and are not necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required. Whilst every care has been taken to ensure that the information provided in this report is as accurate as possible, based on the information provided and documentation reviewed, no complete guarantee or warranty can be given with regard to the advice and information contained herein. Our work does not provide absolute assurance that material errors, loss or fraud do not exist.
This report is prepared solely for the use of Council and senior management of South Kesteven District Council. Details may be made available to specified external agencies, including external auditors, but otherwise the report should not be quoted or referred to in whole or in part without prior consent. No responsibility to any third party is accepted as the report has not been prepared, and is not intended for any other purpose.
RSM Tenon Limited is a member of RSM Tenon Group RSM Tenon Limited is an independent member firm of RSM International an affiliation of independent accounting and consulting firms. RSM International is the name given to a network of independent accounting and consulting firms each of which practices in its own right. RSM International does not exist in any jurisdiction as a separate legal entity.
RSM Tenon Limited (No 4066924) is registered in England and Wales. Registered Office 66 Chiltern Street, London W1U 4GB. England th SOUTH KESTEVEN DISTRICT COUNCIL 1 Internal Audit Progress Report – 17 March 2011
1. INTRODUCTION th 1.1 The periodic internal audit plan for 2010/11 was approved by the Governance and Audit Committee on the 18 March 2010. This report summarises the outcome of work completed to date against that plan, and Appendix A provides cumulative data in support of internal audit performance.
2. FINAL REPORTS ISSUED 2.1 We have finalised ten reports since the last Committee meeting; these are in the areas of:
Follow Up (2); Partnerships; General Ledger; Cash & Banking (Area Offices & Public Conveniences); Council Tax; Licensing Income; Markets; Democracy; Planning & Building Control Fees; Data Protection. At the request of management, a VAT Data collection exercise was undertaken and information was passed to the Finance department and therefore there is no audit report for this piece of work.
3. WORK IN PROGRESS OR PLANNED 3.1 IT Review audits are being undertaken by our IT specialist and these have been confirmed with the auditees separately.
3.2There are seven draft reports that have been issued for which we are awaiting management responses (see Appendix A).
3.3For all the remaining audits, audit commencement dates have been agreed with the auditees and all assignment planning sheets have been issued. th SOUTH KESTEVEN DISTRICT COUNCIL 2 Internal Audit Progress Report – 17 March 2011
4. KEY FINDINGS FROM INTERNAL AUDIT WORK 4.1 We have raised 53 recommendations across the ten reviews that are being presented to this committee; two recommendations have been classified as High Risk and the remaining 51 have been classified as Medium or Low risk. Details of the key findings are shown in Appendix B.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Risk Management Annual Report 2025/26Agreed’; 1% ‘Not Agreed’ and 2% ‘Don’t Know’. Themes for improvement were identified for Governance, Health and Safet...
Risk Management Annual Report 2024/25Agreed’ with 83% of the statements on assurance with the remainder being 14% ‘Partially Agreed’; 1% ‘Not Agreed’ and ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.