TREASURY MANAGEMENT QUARTER 3 PERFORMANCE

Noted Finance 1 paper

Governance and Audit Committee noted this item on Thursday 17 March 2011. Below is the council's own wording, with the papers it was decided on.

Item74

Resolved

The Committee noted Report Number HOF149 – Treasury Management Quarter 3 Performance.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Governance and Audit Committee

Recommendation

Members are asked to note the treasury management activity for the period up to and including Quarter 3 of 2010-11 (October to December 2010)

2. PURPOSE OF THE REPORT/DECISION REQUIRED

Treasury Management is the term used to cover the Council's borrowing and investment strategies. The Council has formally adopted the key recommendations of the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice for Treasury Management in the Public Services. In line with the Code the Council has adopted a treasury management policy statement that requires regular reports on treasury and debt management operations during the financial year.

Page 1 Additionally, under Part 1 of the Local Government Act 2003, the Council is required to have regard to the Prudential Code for Capital Finance including the setting of Prudential Indicators. Relevant treasury management indicators were incorporated into the Treasury Management Strategy 2010/11 and an updated Strategy was approved on 9th September 2010.

This report is submitted in accordance with these requirements and provides a review of treasury management for the period ended 31 Dec 2010 and reviews current developments.

The CIPFA Treasury Management Panel Bulletin published March 2009 following the collapsed Icelandic banks promotes the view that Council’s monitor performance at least half yearly and ideally quarterly. In addition to this, a report by the Audit Commission entitled ‘Risk and Return’ identifies the need for Local Authorities to report regular to members in addition to the annual review.

3. DETAILS OF REPORT

This report sets out the following for the 9 month period from 1 April to 31 December 2010:

a. A review of debt management operations;

b. A review of investment operations;

c. A summary of interest rate movement and investment performance; and

d. An update on the treasury management Prudential Code Indictors.

DEBT MANAGEMENT OPERATIONS

Long Term Borrowing

No additional long term borrowing was required during Quarter 3. £1 million was paid off in November 2010. The remaining £2.5 million PWLB loans are long term debt, repayable after 12 months. All Council borrowing is with the Public Works Loans Board (PWLB). The average rate of interest paid on the debt portfolio was 9.975%. Appendix A is a schedule of loans outstanding at 31 December 2010. At the point in time of these PWLB loans being taken and in the context of today’s interest rates the coupon rates appear high. Subsequently interest rates have reduced significantly. Regular reviews are undertaken to review redemption costs of natural maturity against new borrowing to settle the outstanding debt early. Currently, it is not cost effective to settle early but the position continues to be reviewed in conjunction with our Treasury Management advisors.

Short-Term/Temporary Borrowing

This can be defined as borrowing which is due to be repaid within 364 days. We do not have any short term borrowing as at 31 December 2010.

Page 2 INVESTMENT OPERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TREASURY MANAGEMENT QUARTER 3 PERFORMANCEReport 80 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. TREASURY MANAGEMENT QUARTER 3 PERFORMANCEThis decision
  2. Treasury Management Annual Report 2024/25Agreed
  3. Review of Treasury Management Activities - Environmental, Social and Governance ReviewNoted
  4. Treasury Management Strategy Statement 2024-2025Approved
  5. 2020 - 2021 Treasury Management Annual ReportApproved
  6. Treasury Management Strategy 2021-22Agreed

More from South Kesteven Governance and Audit Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 Risk Management Annual Report 2025/26Agreed’; 1% ‘Not Agreed’ and 2% ‘Don’t Know’. Themes for improvement were identified for Governance, Health and Safet... Agreed Open
25 Jun 2026 Draft Annual Governance Statement 2025/26Decision on LGR structure expected in July 2026 · Lincolnshire Chief Executives and Leaders to develop a constituted ... Noted Open
18 Mar 2026 2025-26 Action Plan for Draft Statement of AccountsIt was agreed at the previous meeting of the committee that the Section 151 Officer would present proposed actions be... Agreed Open
18 Feb 2026 Statement of Accounts 2024-25It was agreed with audit that this would remain unadjusted as it was below our materiality threshold of £1.7m. During... Agreed Open
24 Sep 2025 Risk Management Annual Report 2024/25Agreed’ with 83% of the statements on assurance with the remainder being 14% ‘Partially Agreed’; 1% ‘Not Agreed’ and ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies