St Peters Hill Development - Budget Allocation & Project update

Agreed Committee 1 paper

Council agreed this item on Thursday 11 September 2014. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

That the Council notes the progress made on developing the St Peter’s Hill scheme and agrees to amend the allocation in the General Fund Capital Programme for this scheme to £4.95m from the £6.1m currently allocated to ‘Town Centre Projects – St Peter’s Hill Development’ for the period 2014/15-2016/17. The Portfolio Holder for Strategic Resources – Well Run Council proposed the recommendation in report number PD021 (which was seconded), requesting a revision to the General Fund Capital Programme. The Budget approved by Council on 3 March 2014 included an allocation of £6.1m for ‘Town Centre Projects – St Peter’s Hill Development’ for 2014/15 to 2016/17. Changes to proposed onsite provision and further work on costings identified a reduced budget requirement for the project of £4.95m. Members spoke in support of the proposed cinema development however some expressed disappointment that more information had not been made available to Councillors and that there had not been more public input in developing proposals for the site. Detailed costings , anticipated commercial yield and lease terms could not be shared as they were subject to ongoing negotiations and consequently commercially sensitive information. Members were assured that officers were undertaking detailed work with a potential contractor to better understand costs and the delivery timeframe and that work developing the business case and financial modelling was ongoing. The proposition was put to the vote and carried unanimously.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Council

Purpose of the report

2.1The report provides an update on the makeup of the components of the proposed scheme, the procurement route being progressed and allocation of capital towards the scheme. Cabinet has supported this project at it’s meeting on 4 August 2014 and is seeking approval from Council for the investment in line with the revised costings obtained as part of the project development.

3. DETAILS OF REPORT

3.1The General Fund capital programme is focussed on the delivery of priority projects particularly in relation to Grow the Economy – economic regeneration.

3.2This ambitious proposal involves the redevelopment of land and premises at St Catherine’s Road which will create a 6 screen multiplex cinema with adjacent restaurants thereby bringing significant improvements to the leisure and cultural offer in the vicinity. This level of investment in the town centre will provide an economic boost to the local economy and ensure the Council continues its track record of delivering its priorities.

3.3In order to compliment the enhanced Cinema offer and existing Guildhall Arts Centre a soft marketing exercise has been carried out to ascertain the likely level of interest from A3 (Restaurant) operators in locating new offers to Grantham in the space adjacent to the cinema.

3.4The level of confirmed interest in the scheme has been strong. Taking only those operators that confirmed definite interest in having space in the scheme, there is currently more demand than available space on the ground floor. We have therefore looked to include approximately 4000 sq ft of A3 space on the first floor.

3.5Typically first floor space for A3 use is less attractive to operators; however the concept of a food court with multi cuisine and live cooking areas sits well with a quality fast food offer for those seeking a quicker dining experience before or after a film. A reconfiguration of the space at first floor level will suit this use. Placing the entrance immediately adjacent to the Cinema entrance ensures footfall passes the entrance to the first floor A3 outlet.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St Peters Hill Development: Budget Allocation & Project updateReport 87 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. St Peters Hill Development - Budget Allocation & Project updateThis decision
  2. *Redevelopment of St Peters Hill, Grantham - Procurement and Budget allocation updateAgreed

More from South Kesteven Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Warm Homes Social Housing Fund GrantDECISION: That Council a) Recommend that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant whi... Approved Open
16 Jul 2026 Annual Review of Overview and Scrutiny 2025/2026DECISION: That Full Council: Notes the Overview and Scrutiny Annual Report. Note: The meeting adjourned for a short b... Decided Open
21 May 2026 Election of ChairmanAGREED: To elect Councillor Anna Kelly as the Chairman of the Council for the 2026/2027 municipal year. The Chairman ... Agreed Open
21 May 2026 Election of Vice-ChairmanAGREED: To elect Councillor Pam Byrd as the Vice-Chairman of the Council for the 2026/2027 municipal year. The Vice-C... Agreed Open
21 May 2026 Programme of Meetings of Full Council, Cabinet and Committees for 2026/2027DECISION That Full Council approve the programme of Meetings of Full Council, Cabinet and Committees for 2026/2027 as... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies