Use of the ESPO Liquid Fuel Framework for the Procurement of Diesel Fuel

Approved Executive 1 paper

Cabinet approved this item on Thursday 22 September 2022. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

Decision That Cabinet approves the utilisation of the ESPO Liquid Fuel Framework for the procurement of diesel fuel from 1 October 2022 until the expiration of the Framework on 30 September 2026. Alternative options considered and rejected The Council could go directly out to the market, however, it was considered that this was unlikely to lead to a more competitive alternative, as the benefits of the economies of scale bought about by using the Framework would not be available. Reason for decision Except for two electric pool cars, the Council’s vehicle fleet was entirely comprised of diesel vehicles. Whilst opportunities to replace vehicles with alternative fuel equivalents were being explored, it was anticipated that diesel vehicles would continue to be part of the fleet until at least the expiration of the Framework. The new framework agreement operated in a different way to its previous iteration; previously there was one supplier per region, but now there were a number of suppliers, which allowed for a greater degree of flexibility and competition. As the Council’s volume usage was standard (approximately 2,500 litres per day) and requirements were not complex, the framework provider strongly recommended that a direct award be made to the most suitable supplier. This ensured the continuity of supply as committing to purchase fuel from one supplier would foster commitment from the supplier to the customer and ensure preferential deliveries in times of fuel supply disruption or driver shortages. This was essential for business continuity to enable the Council to continue to deliver essential services such as household waste collections and housing maintenance. The Council’s approved budget for diesel fuel for 2022/23 was £712,750. The following points were raised during discussion: The cost of diesel fuel could potentially rise by an additional £200,000 in year. However, being part of the ESPO framework enabled SKDC to make savings as diesel would be procured in bulk. The use of the new framework would help ease pricing pressures on fuel. Whilst electric vehicles would be used where possible, it was unlikely that vehicles using the most fuel, such as refuse lorries, would have this option in the short term.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

The Council currently utilises an ESPO Framework for the procurement of diesel fuel. ESPO is establishing a new framework agreement for the provision of liquid fuels from 1 October 2022. Agreement is sought to utilise this Framework.

Recommendations

That Cabinet: 1. Approves the utilisation of the ESPO Liquid Fuel Framework for the procurement of diesel fuel from 1 October 2022 until the expiration of the Framework on 30 September 2026. Decision Information

Is this a Key Decision? Yes

Does the report contain any No exempt or confidential information not for publication? What are the relevant corporate Clean and sustainable environment priorities? High performing Council Which wards are impacted? All

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The establishment of the ESPO framework is particularly welcome given the current volatility of the fuel market which has led to increasing costs in diesel placing pressures on current budgets. The average spend on the procurement of fuel has in the past been approximately £700k although this is rising by a minimum of a further £200k in the current year. It is therefore essential that the most cost effective procurement is in place to enable the Council to take advantage of the best price in the market.

1.2The new Framework will offer a number of suppliers and allows the Council to prove ‘best value’ in selecting a supplier.

1.3The ESPO Framework Agreement is fully compliant with UK Public Procurement Regulations. Call-off from the Framework must be undertaken in accordance with the Council’s own Procurement Regulations.

1.4Suppliers are assessed during the procurement process for their financial stability, track record, experience and contract management, before being awarded a place on the framework. Legal and Governance

1.5The total value of the contract over its lifetime exceeds £200,000 and therefore meets the criteria to be considered a Key Decision by Cabinet. 1.6 There are no additional legal implications associated with this report.

Risk and Mitigation

1.7Given the on-going situation regarding the worldwide fuel supply, entering into a call-off contract with a chosen supplier will ensure the Council receives delivery priority in times of fuel supply disruption or driver shortages and supports business continuity.

Climate Change

1.8The Council has declared a Climate Emergency and has committed to reducing greenhouse gas emissions by at least 30% by 2030 and achieving net zero as soon as viable before 2050.

1.9Carbon emissions from the operation of the Council’s vehicle fleet represent around a quarter of overall emissions, and options for decarbonisation of the fleet are currently being explored to reduce fuel consumption and support electrification of the fleet where possible. In the meantime, there continues to be a requirement for diesel fuelled vehicles.

2. Background to the Report

2.1The Council currently procures diesel fuel through the ESPO Liquid Fuels Framework Agreement. ESPO has decided not to take up the option of an extension to the existing framework agreement and has instead undertaken a tender process to replace it with a new framework agreement. The new framework agreement will expire in September 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Use of the ESPO Liquid Fuel Framework for the Procurement of Diesel FuelReport 149 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Use of the ESPO Liquid Fuel Framework for the Procurement of Diesel FuelThis decision
  2. Use of the ESPO Specialist Vehicles FrameworkApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open