Cabinet, Thursday 22 September 2022 at 10.30am

Replacement of Gym Equipment at Bourne Leisure Centre

Approved Executive 1 paper

Cabinet approved this item on Thursday 22 September 2022. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

Decision That Cabinet: 1. Approves the addition of £137,000 to the capital budget for 2022/23 to provide a loan to LeisureSK Ltd to facilitate a refurbishment of the gym area and equipment at Bourne Leisure Centre. 2. Delegates to the Chief Finance Officer to agree the terms and conditions of the loan and sign the loan agreement on behalf of the Council. Alternative options considered and rejected The options for LeisureSK Ltd to either directly purchase the equipment or enter a lease arrangement had been fully considered. It had been established that it was financially beneficial for the Council to finance the cost of refurbishing the gym at Bourne Leisure Centre via a loan arrangement. The option not to invest in the gym area at Bourne Leisure Centre had been discounted by the Board of Directors for LeisureSK Ltd. Without this investment, it would become increasingly difficult to attract and retain customers to the centre. Reason for decision At their September 2022 meeting, the Board of Directors for LeisureSK Ltd. considered a report concerning the equipment provision at Bourne Leisure Centre. It was thought that the age of the equipment in place there was more than 8 years old, beyond the accepted lifespan as advised by the leisure industry. Work had taken place with suppliers to identify the costs of providing new equipment; these costings would include the removal of the old equipment as well as installation of the replacement items. All servicing and maintenance costs for five years would also be covered. The most cost-effective solution for Bourne Leisure Centre would be the refurbishment of the gym equipment. The Directors of LeisureSK Ltd. approved the proposal to undertake a replacement of the gym equipment at Bourne Leisure Centre. Work was carried out by SKDC’s finance team to assess the impact of SKDC providing a loan to help meet this proposal. The resolutions within the report provided the optimal financial outcome for SKDC and the planned refurbishment of the gym at Bourne Leisure Centre would have a significant impact on improving income and aiding the recruitment and retention of customers. The investment in new equipment for Bourne Leisure Centre demonstrated the Council’s ongoing commitment to ... view the full minutes text for item 36.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

For Cabinet to consider an amendment to the in-year budget framework and provide a loan to LeisureSK Ltd to finance the purchase of gym equipment at Bourne Leisure Centre.

Recommendations

That Cabinet: 1. Approves the addition of £137,000 to the capital budget for 2022/23 to provide a loan to LeisureSK Ltd to facilitate a refurbishment of the gym area and equipment at Bourne Leisure Centre. 2. Delegates to the Chief Finance Officer to agree the terms and conditions of the loan and sign the loan agreement on behalf of the Council. Decision Information

Is this a Key Decision? Yes

Does the report contain any No exempt or confidential information not for publication? What are the relevant corporate Healthy and strong communities priorities?

Which wards are impacted? Bourne

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The Board of Directors for LeisureSK Ltd has formally approached the Council and requested that a loan be provided in the sum of £137,000. The financing options have been modelled in order to identify the most cost-effective borrowing option for the company. The recommendation is for the Council to undertake a loan arrangement with LeisureSK Ltd over a 60-month period in order for them to procure the equipment.

1.2This will require an amendment to the Council’s capital programme of £137,000. The Council’s Financial Regulations include the provision that any changes to the in-year budget framework can be approved by Cabinet up to £150,000 per addition.

Completed by: Richard Wyles, Chief Finance and S151 Officer.

Legal and Governance

1.3The provision of funds and requested amendment to the Council’s budget framework is in accordance with the Council’s Financial Regulations.

Completed by: Alan Robinson, Deputy Chief Executive and Monitoring Officer. 2. Background to the Report

2.1The Council’s Corporate Plan 2020 – 2023 identifies the provision of high-quality leisure across the district as a key priority and a contributory factor to ensuring that South Kesteven continues to be the best district in which to live, work and visit. The adopted Sport and Physical Activity Strategy (2021 to 2026) also sets out the mission to provide opportunities that our residents need now and, in the future, to build healthy and strong communities and encourage residents to live healthy, active lifestyles.

2.2LeisureSK Ltd is a wholly owned Council company and has, under a contractual arrangement, been responsible for the management of the Council’s leisure facilities since 1 January 2020.

2.3The Board of Directors for LeisureSK Ltd are appointed by the Council and are responsible for the management and financial performance of the company. The Contract Manager for LeisureSK Ltd took up the role in April 2022 and is responsible for the operational performance of the company, reporting directly to the Board of Directors.

2.4At their 1 September 2022 meeting, the Board of Directors for LeisureSK Ltd considered an urgent report presented by the Contract Manager for LeisureSK Ltd, regarding the gym equipment at Bourne Leisure Centre and the issues arising from the age and condition of the equipment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Replacement of Gym Equipment at Bourne Leisure CentreReport 153 KB DownloadRead as text

At this meeting

Whole meeting

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies