Resolved

Decision That Cabinet approves the award of a contract for Fire Risk assessments and Fire Compartmentation surveys with Penningtons following compliant procurement. Contract period was for a maximum of 4 years (2+1+1), with a contract value up to £400,000. Alternative options considered and rejected There were no other options available. Reason for decisions The proposed contract award had followed compliant procurement processes and should provide the Council with the appropriate contracts to aid the Council to deliver on its Corporate Priority to provide “Housing that meets the needs of all residents”. The decision helped support the delivery of improvements to the whole housing structure.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report is for the contract award for the completion of fire risk assessments and fire compartmentation surveys within our Housing Revenue Account property portfolio. This has been through a compliant procurement process, with the contract to be awarded through the Fusion21 framework.

Recommendations

That Cabinet: 1. Approves the award of a contract for Fire Risk assessments and Fire Compartmentation surveys with Penningtons following compliant procurement. Contract period maximum 4 years (2+1+1) contract value up to £400,000. Decision Information

Is this a Key Decision? Yes

Does the report contain any No exempt or confidential information not for publication? What are the relevant corporate Housing that meets the needs of all residents priorities?

Which wards are impacted? All

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The cost of this contract is included in the approved budget for the Housing Revenue Account.

Completed by: Alison Hall-Wright, Assistant Director of Finance

Legal and Governance

1.2Sufficient notice has been provided on the Cabinet Forward Plan for this Key Decision, however, the item was not included on the agenda for this meeting of Cabinet.

1.3The item is submitted to Cabinet in accordance with Paragraph 18 of the Council’s Access to Information Procedure Rules due to the necessary five clear days’ notice not having been provided of the business to be transacted. It is considered impracticable to defer consideration of this report to a future meeting of Cabinet, as set out in the below decision notice (within the modern.gov library on the South Kesteven website, copies can be made available at the Council’s offices):

https://moderngov.southkesteven.gov.uk/ecSDDisplay.aspx?NAME=Specia l%20Urgency%20Notice%20- %20Contract%20Awards%20in%20relati&ID=394&RPID=11587471 1.4 The proposal would safeguard the Council in terms of its key housing compliance obligations, as outlined in the report.

Completed by: Graham Watts, Assistant Director of Governance and Monitoring Officer

2. Background to the Report

2.1The Council has a clear commitment in its Corporate Plan 2020-2023 to provide “Housing that meets the needs of all residents”. As a stock-retained local authority, the Council has statutory and regulatory obligations to maintain and repair circa 5,900 properties.

2.2Fire safety is a key housing compliance obligation and the requirement for regular Fire Risk Assessments is key to ensuring the ongoing health and safety of our tenants.

2.3We have ensured compliance with the procurement process by engaging our in- house procurement officer. The contract would be awarded via Lot 5 of the Fusion21 procurement framework which ensures deliverability, minimal risk and procurement guidelines compliance.

2.4The identified supplier is currently ranked as number one on the Fusion21 procurement framework, which can be seen on page 4 of Appendix 1 - Fusion21 Direct Award Report.

2.5The proposed contract would be for an initial two-year period with the option of two further one-year extensions, the maximum contract length would be four years.

3. Key Considerations

3.1A fully compliant procurement process has been undertaken resulting in the identification of a supplier to undertake this important aspect of work.

3.2There are no existing contracts in place to complete these works.

4. Other Options Considered

4.1There are no other options available.

Reasons for the recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fusion21 Direct Award ReportAppendix 1 553 KB Download
PDF
Contract Awards in relation to Social Landlord ResponsibilitiesReport 145 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Contract Awards in relation to Social Landlord ResponsibilitiesThis decision
  2. Contract Awards in relation to social landlord responsibilitiesApproved
  3. Contract Awards in relation to social landlord responsibilitiesApproved
  4. Contract Awards in relation to social landlord responsibilitiesApproved
  5. Contract Awards in relation to social landlord responsibilitiesApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies