Item92

Resolved

Decision That Cabinet: 1. Approves the contract award to Lindum Group Ltd to undertake works to facilitate and deliver the development of a 20-unit new build housing scheme at Swinegate Grantham for the sum of £3,519,690. 2. Agrees to delegate price variations to the contract of no greater than 10% to the Chief Finance Officer, in consultation with the Cabinet Member for Housing and Property, due to the complexity of the new build and the associated price volatility. Alternative options considered and rejected Option 1 – to appoint Lindum via the Scape Framework on the works to facilitate and complete the development of a scheme of 20 new build housing units at Swinegate, Grantham for the sum of £3,519.690. Option 2 – to allow Lindum to manage remaining pre-construction phase through to Royal Institute of British Architects (RIBA) Stage 4, in order to bring the scheme forward for construction phase works to be procured separately via an open tender process. This was not considered necessary as the Council’s Contract Procedure Rules allowed for the use of Frameworks, and utilising the Framework ensured all due diligence had been undertaken on the named contractors and would ensure the scheme could progress without unnecessary delays. Option 3 – not to progress the scheme following the viability and pre-construction phase works undertaken by Lindum. New Build delivery was a key element of the Council’s Corporate Plan and adding new units to social housing stock was necessary to sustain the viability of the HRA financial Business Plan. Reason for decisions Following the completion of the open tender procurement process, it was recommended that Lindum be awarded the works contract. This process was in accordance with the Council’s Contract and Procurement Procedure Rules and the Public Contract Regulations 2015. The acquisition of the land was driven by several objectives including enabling the Council to achieve land in a strategic location with the potential to acquire other adjacent sites identified as regeneration opportunities; this was to be undertaken whilst improving the street scene. The acquisition of the land would demonstrate the pursuance of a development opportunity in the centre of Grantham. Construction was now ready to commence. The appointment of Lindum, and the progression of the scheme to RIBA Stage 4 would provide the Council with a high degree of financial certainty. The costs of bringing the scheme through construction to completion was £3,519,690. Detailed costings would be established to enable accurate budgeting of the construction stage. The Council would be advised of anticipated cash flow to facilitate stage payments over the contract period along with any other consultants’ appointments. The existing viability report from Lindum would produce a build cost of £175,985 per unit. To facilitate the Swinegate development and deliver the optimum scheme there was a requirement to undertake alterations to ... view the full minutes text for item 92.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report sets out the proposals for a 20-unit new build social housing development at Swinegate, Grantham and to recommend that the new build contract be awarded to Lindum Group Ltd.

Recommendations

That Cabinet: 1. Approves the contract award to Lindum Group Ltd to undertake works to facilitate and deliver the development of a 20-unit new build housing scheme at Swinegate Grantham for the sum of £3,519,690.00 Decision Information

Does the report contain any No exempt or confidential information not for publication?

What are the relevant corporate Supported Housing for all priorities? Which wards are impacted? Grantham St Wulframs

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The delivery of this scheme is a key element of the new build programme or the Housing Revenue Account (HRA). The budget for this proposal is included in the 2022-2023 and 2023-2024 capital programme and is funded from the Capital Receipts Reserve. The delivery of 20 units will provide a rental income stream to the HRA and will be built in the HRA financial business plan.

Completed by: Richard Wyles, Chief Finance Officer

Legal and Governance

1.2The necessary processes have been followed in accordance with the Council’s Contract Procedure Rules. There are no further significant legal, or governance implications not already highlighted within the body of the report.

Completed by: Graham Watts, Assistant Director of Governance and Monitoring Officer

Risk and Mitigation

1.3A project risk register will be created in partnership between the contractor and the Council, which will be subject to robust review as the project progresses. As part of the process there will be a mutual agreement of the identified risks and enable confirmation of ownership to be confirmed by the contractor of the Council.

Completed by: Tracey Elliott, Governance and Risk Officer 2. Background to the Report

2.1The land at 20B Swinegate Grantham (Appendix 1 - edged red) was purchased by the Council and added to the Housing Revenue Account (HRA) in 2018 for £205,000 with full planning permission for the build of 9 apartments. The land is situated adjacent to the Council owned pay and display car park between Watergate and Swinegate, Grantham.

2.2The acquisition of the land was driven by several objectives including enabling the Council to ensure land in a strategic location with the potential to acquire other adjacent sites that were identified as a regeneration opportunity (for a brownfield site) whilst improving he street scene and pursue a development opportunity in the centre of Grantham.

2.3In 2019 the Council purchased 2 buildings adjacent to the land at 20B Swinegate, 20 Swinegate (Appendix 1 – edged green) and a listed building to the rear of 44 Watergate (Appendix 1 – edged blue), with the aim of extending the 20B Swinegate site and taking ownership of the dilapidated buildings within the site’s curtilage, which could otherwise hinder the project. The total cost of purchasing the 3 sites was £337,000. A site plan is shown as Appendix 1 - Plan of the combined site.

2.4An initial architect plans showed the potential for 20 flats whilst incorporating an archway to enhance the car park entrance, utilising the site plus a proportion of the car park. This design requires an approximate 15% reduction of existing car parking provision to facilitate the design.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Plan of combined siteAppendix 1 233 KB Download
PDF
New Build Housing Scheme for 20 units at Swinegate, GranthamReport 291 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. New Build Housing Scheme for 20 units at Swinegate, GranthamThis decision
  2. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved
  3. Contract Award for Wellington Way New Build Scheme (11 units)Approved
  4. Contract Award for New Build Housing Scheme for 19 units at Larch Close, GranthamApproved
  5. New Build Housing Scheme for 4 units at Elizabeth Rd, StamfordApproved
  6. Distribution of Monies Received by the Council Under a s106 Agreement and Grant of New Lease and Building Licence at Empingham Road Playing Fields, Stamford - Key DecisionAgreed

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies