AGREED : DECISION: That Full Council: 1. Approves the allocation of funding of £1million to accelerate the replacement of the Council operated streetlights with LED energy efficiency lamps. The scheme to be funded as follows: · £500k Invest to Save Reserve · £250k Budget Stabilisation Reserve · £250k Local Priorities Reserve 2. Requests the Environment Overview & Scrutiny Committee review the current Street Lighting Policy with regard to further reducing energy costs at specific times and locations.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
This report provides an overview regarding South Kesteven District Council’s potential to upgrade District Council operated streetlights to energy efficient LED (Light Emitting Diode) units.
Recommendations
Council is asked: 1. To approve the allocation of funding of £1 million to accelerate the replacement of the Council operated streetlights with LED energy efficiency lamps. The scheme to be funded as follows: o £500k Invest to Save Reserve o £250k Budget Stabilisation Reserve o £250k Local Priorities Reserve 2. To request Environment Overview and Scrutiny Committee review the current Street Lighting Policy with regard to further reducing energy costs at specific times and locations. Decision Information Is this a Key Decision? Yes Does the report contain any No exempt or confidential information not for publication?
What are the relevant corporate Clean and sustainable environment priorities?
Which wards are impacted? All wards
1. Implications Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:
Finance and Procurement
1.1The financial implications, should there be a faster paced rollout of energy efficient units, will incur a significant financial outlay. However, the ongoing revenue savings will also be a significant contribution towards reducing the Council’s operating expenditure. The funding of any accelerated replacement programme will be required to be funded from reserves as no budget allocation in this financial year has been made. Following an analysis of the reserves and the anticipated use during the current financial year, the proposal is to provide the funding from the following: £500k Invest to Save reserve, £250k Budget Stabilisation Reserve and £250k Local Priorities Reserve.
Completed by: Richard Wyles, Chief Finance Officer (s151 Officer)
Legal and Governance
1.2Councils do not have a duty to provide streetlighting, however once provided, the local authority does have a duty to maintain the system in a safe condition.
1.3Regarding considerations to continue to upgrade lamps to LED any further changes to the project to allocate further funding would need to comply with the Council’s Financial Regulations and Contract Procedure Rules.
Completed by: Graham Watts, Assistant Director of Governance and Monitoring Officer Climate Change
1.4The energy reduction potential of upgrading the Council’s stock of lamps to LED is significant, with streetlighting being the single largest area of electricity consumption for the Council. Annual carbon savings are modelled within the report which will contribute towards the Council’s carbon reduction target.
Completed by: Serena Brown, Sustainability and Climate Change Officer
2. Background to the Report and Reasons for Recommendations
2.1South Kesteven District Council is responsible for 3893 streetlights within the district which are all funded from the Council’s General Fund.
2.2The majority of lights operated by the Council are 35W (or 36W) low pressure sodium lamps and are responsible for just over 4% of the Council’s total carbon emissions – a significant contribution.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Warm Homes Social Housing Fund GrantDECISION: That Council a) Recommend that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant whi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.