Award of Contract for Space Heating, Installation and Servicing in respect of HRA Properties

Approved Executive 1 paper

Cabinet approved this item on Thursday 18 January 2024. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

Decision That Cabinet approves the award to Aaron Services Ltd for the contract for a 3 year period (with the option to extend by a further 1 + 1 years) of an annual value of up to £3m for the provision of asset services and the repair, maintenance and installation of domestic heating and mechanical services, including low carbon installations to the Council’s housing stock. Alternative options considered and rejected The ongoing maintenance of a number of existing systems, as opposed to replacing them had been considered, but this could be difficult due to the availability of parts. Additionally, consideration was being given to obtaining grant funding to check the integrity of cavities and lofts, as insulation in these key areas of property construction was unknown. A further report on this would follow in due course under Fabric First. Reasons for decision The proposed contract award had followed compliant procurement processes and would provide the Council with the appropriate contracts to aid the delivery of the Corporate Priority to provide “Housing that meets the needs of all residents”. The contract award was one of the largest that the Council granted, as it was for up to £15 million over 3 years with an option to extend by another two years. Collaboration was underway with Aaron Services Limited; they were willing to relocate some of their staff into Council premises, which added value to the contract. One other advantage was that Aaron Services Limited had for many years serviced a similar contract at North Kesteven District Council, who seemed to have received an efficient. Considerable work had been carried out to ensure that under the new contract there would be marked improvements to the Council’s housing tenants.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To seek approval to enter into a contract with Aaron Services for the provision of asset services and the repair, maintenance and installation of domestic heating and mechanical services, including low carbon installations to South Kesteven District Council’s housing stock.

Recommendations

That Cabinet: Approves the award to Aaron Services Ltd for the contract for a 3 year period (with the option to extend by a further 1 + 1 years) of an annual value of up to £3m for the provision of asset services and the repair, maintenance and installation of domestic heating and mechanical services, including low carbon installations to the Council’s housing stock. Decision Information

Is this a Key Decision? Yes, this is a key Decision included on the Forward Plan. Does the report contain any Yes – The appended Procurement Summary exempt or confidential Report (Due to the sensitive information it information not for publication? contains relating to the bidder’s tender submissions) What are the relevant corporate Housing that meets the needs of all residents priorities? Healthy and strong communities Clean and sustainable environment High performing Council Which wards are impacted? Grantham, Bourne, Stamford, Deepings and surrounding villages. 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance

1.1The 2024/25 – 2026/27 includes a combined budget proposal of £11.m for Space Heating, Installation and Servicing in respect of HRA Properties which will ensure that there is sufficient budget to fund the cost of this contract over the next 3 years.

Completed by: Alison Hall-Wright, Deputy Director (Finance & ICT) and Deputy S151 Officer

Procurement

1.2It is confirmed that a fully compliant procurement process has been completed and the Council’s Procurement Lead has been consulted throughout the process.

Completed by: Helen Baldwin, Procurement Lead, SKDC Legal and Governance

1.3There are no significant legal and governance implications arising from the report which are not already reflected elsewhere in the report, particularly in relation to procurement and compliance with the Council’s Contract Procedure Rules.

Completed by: Graham Watts, Assistant Director (Governance and Public Protection) and Monitoring Officer

Risk and Mitigation

1.4As part of the contract, any risk will be monitored as part of the contract management process. Completed by: Tracey Elliott, Governance and Risk Officer

Health and Safety

1.5As part of the tender documentation, a comprehensive Pre-Construction Information document was provided for all bidders to review and consider the aspects of health & safety associated within the proposed works. This is still to be completed.

1.6When the contract is awarded to the successful bidder, a Construction Phase will be requested/provided by the Principle Contractor and this will detail how all the health & safety risks associated with the construction phase will be implemented to minimise the risks where possible or eliminate them.

Completed by: Phil Swinton, Emergency Planning and Health and Safety Lead

2. Background to the Report

2.1The Council has a clear commitment in its Corporate Plan 2020-2023 to provide “Housing that meets the needs of all residents”. As a stock-retained local authority, the Council has statutory and regulatory obligations to maintain and repair circa 5,900 properties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Contract for Space Heating, Installation and Servicing in respect of HRA PropertiesReport 246 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Award of Contract for Space Heating, Installation and Servicing in respect of HRA PropertiesThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies