Cabinet, Thursday 15 January 2026 at 4.00pm

Contract Award - New Build Housing Scheme at Toller Court, Horbling

Approved Executive 2 papers

AI summarySouth Kesteven District Council Cabinet approved a £544k contract with Gusto Construction Limited to build three affordable bungalows at Toller Court, Horbling, with work starting Spring 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedGusto Construction to build three bungalows at Toller Court
Money£544kContract value, with 10% contingency delegated
What happens nextSpring 2026Work to start, with completion in December 2026
Who it affectsToller wardThree new affordable bungalows for rent

What was decided

Cabinet approved the contract award to Gusto Construction Limited for three housing units at Toller Court, Horbling at a cost of £544k. Report P3

Cabinet delegated authority to the Section 151 Officer, in consultation with the Leader of the Council, to allocate an additional 10% of further funding if required due to unforeseen costs. Report P3

The contract will convert a long unused community centre within a sheltered housing scheme into three terraced bungalows. Report 2.5

Why

There is a housing need for the Council to develop the site, so the contract was awarded to allow works to start in Spring 2026. Report 5.1, 4.1

The procurement process followed the Council's Contract and Procurement Procedure Rules, the Procurement Act 2023 and the Public Contract Regulations 2015. Report 1.2, 1.3

The scheme supports the Corporate Plan 2024-2027 priority of increasing supply of sustainable, high quality Council provided housing. Report 2.1, 2.2, 2.5

What happens next

Works are due to start in March 2026, with completion expected by December 2026. Report 5.1

A project risk register will be created in partnership with the contractor and reviewed as the project progresses. Report 1.4

Monthly meetings with the contractor will be held, with officers inspecting the site before each meeting.

The money

  • £544k Contract value for construction of three housing units at Toller Court, Horbling Report P3, 2.7
  • £550,000 Budget for the development, included in the 2025-2026 capital programme, funded from HRA Capital Receipts Reserve Report 1.1
  • 10% Additional funding delegated to the Section 151 Officer for unforeseen costs Report P3

Options considered

  • Rejected: Wait to commence the scheme or not build the development. Discounted due to high levels of housing need in the area Report 4.1
  • Chosen: Award contract to Gusto Construction Limited. Highest scored bid at 92.00% in the procurement evaluation Report 2.11, 2.13, 2.14

Implications

  • Financial: Budget of £550,000 from HRA Capital Receipts Reserve, with a rental income stream to the HRA Report 1.1
  • Legal: Decision is above the Key Decision threshold; procurement complied with Contract Procedure Rules, the Procurement Act 2023 and the Public Contract Regulations 2015 Report 1.3
  • Risk: A project risk register will be created and reviewed; the contractor will insure the building works until handover to the Council Report 1.4, 1.5
  • Climate: Bungalows will include high fabric performance, water efficiency, low carbon heating, EV charging and 2.4kW Solar PV per plot Report 1.8, 1.9
  • Staffing: Health and safety documentation and joint site meetings will be arranged with the contractor, with a full handover of compliance information on completion Report 1.6, 1.7

Who and where

  • Residents of Toller ward, including sheltered housing scheme residents Report P6
  • Future tenants of the three bungalows Report 2.3, 1.9
  • Housing Revenue Account Report 1.1

Timeline

  • 23 October 2025: Planning application approved under reference S25/1626 for demolition of community facility and construction of three terraced bungalows
  • 2025-2026: Budget included in capital programme Report 1.1
  • March 2026: Works due to commence
  • December 2026: Expected completion

Plain English for the jargon

  • HRA: Housing Revenue Account, the council's landlord account for social housing
  • EOI: Expression of Interest, an initial step to gauge supplier interest in procurement
  • S25/1626: Planning application reference for the demolition and new build at Toller Court
  • EV charging: Electric vehicle charging infrastructure
  • Solar PV: Solar photovoltaic panels that generate electricity
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item87

Resolved

Decision That Cabinet: 1. Approve the award of a contract to Gusto Construction Limited for the construction of the three housing units at Toller Court, Horbling at a cost of £544k. 2. Delegates authority to the Council’s Section 151 Officer, in consultation with the Leader of the Council, to allocate an additional 10% of further funding if required due to unforeseen costs during the project. Other options considered The Council could wait to commence the scheme or not build the development, but these options were discounted due to the high levels of housing needs in the area. Reasons for the decision There was a housing need for the Council to develop the site therefore the resolution was for the contract to be awarded so that works could commence in Spring 2026. The procurement process accorded with the Council’s Contract and Procurement Procedure Rules, the Procurement Act 2023 and the Public Contract Regulations 2015. The contract award sought to convert a long unused community centre within a sheltered housing scheme. The building had been in the process of being demolished. To rectify this the Council proposed to convert the property into three bungalows which would link into sheltered housing. A procurement exercise was undertaken, supported by Welland Procurement - four suppliers bid for the work. Works were due to commence in March 2026 with a view to completion in December 2026. The following points were highlighted: Monthly meetings with the contractor were normal practice for these types of schemes. Officers would generally inspect the site prior to the monthly meetings. Any complaints about noise from residents would be taken on board and dealt with. If necessary, meetings could be held more frequently. A contingency had been built into the budget. The building currently in situ was in the process of demolition. The three bungalows would a range of environmental features.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report sets out the proposals for a new build social housing development of three units at Toller Court, Horbling, and seeks approval to award the construction contract to Gusto Construction Limited.

Recommendations

That Cabinet:

1. Approve the award of a contract to Gusto Construction Limited for the construction of the three housing units at Toller Court, Horbling at a cost of £544k. 2. Delegates authority to the Council’s Section 151 Officer, in consultation with the Leader of the Council, to allocate an additional 10% further funding if required due to unforeseen costs during the project.

Decision Information

Is this a Key Decision? Yes Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Housing

Which wards are impacted? Toller 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance

1.1The delivery of this scheme is a key element of the new build programme for the Housing Revenue Account (HRA). The budget for this development of £550,000 was included in the 2025-2026 capital programme and is funded from the HRA Capital Receipts Reserve. The delivery of three units will provide a rental income stream to the HRA and will be built in the HRA financial business plan.

Completed by: David Scott – Assistant Director of Finance and Deputy Section 151 Officer

Procurement

1.2The necessary processes have been followed in accordance with the Council’s Contract Procedure Rules.

Completed by: Helen Baldwin, Procurement Lead

Legal and Governance

1.3The necessary processes have been followed in accordance with the Council’s Contract Procedure Rules – this decision is above the Key Decision threshold. There are no further significant legal, or governance implications not already highlighted within the body of the report.

Completed by: James Welbourn, Democratic Services Manager

Risk and Mitigation

1.4A project risk register will be created in partnership with the contractor and the Council which will be subject to robust review as the project progresses. As part of the process there will be a mutual agreement of the identified risks.

1.5The contractor will be responsible for insuring the building works until the properties are handed over to the Council.

Completed by: Tracey Elliott, Governance & Risk Officer Health and Safety

1.6Gusto Construction Ltd have a contract in place to provide inspections, support and guidance to ensure compliance across all sites and office locations. All documentation will be made available to the Council and joint meetings and visits will be arranged to ensure that there is a collaborative approach to health and safety. This will include provision and review of all risk assessments and safe systems of work, relevant to works on site and reporting of accidents to the Council representatives.

1.7On completion of the works, there will be a full handover of all compliance information, technical data and relevant safety information. This will ensure that safe management of the asset can be implemented and required works embedded into existing programmes of compliance inspections and surveys.

Completed by: Phil Swinton, Head of Health, Safety, Compliance and Emergency Planning

Climate Change

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Site PlanAppendix 1 908 KB Download
PDF
Contract Award: New Build Housing Scheme at Toller Court, HorblingReport 549 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Contract Award - New Build Housing Scheme at Toller Court, HorblingThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award for Fire Compartmentation WorksApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies