Cabinet, Tuesday 12 March 2024 at 2.00pm

Contract Award Earlesfield Refurbishment Project

Approved Executive 1 paper

Cabinet approved this item on Tuesday 12 March 2024. Below is the council's own wording, with the papers it was decided on.

Item95

Resolved

Decision That Cabinet approves the award of a contract to United Living to complete the works associated with the Earlesfield Project for a period of 12 months with a contract value of £2.4m. Alternative options considered and rejected The Council could go out to formal tender for the contract, but this would have delayed the completion of the works on the properties. Reasons for decision The direct award to the contractor through the Fusion 21 Framework was a compliant procurement route and was the most expedient way to continue with the asbestos removal and refurbishment works that the contractor had already commenced with. This would minimise disruption to the tenants and ensure that the project is completed. The contractor had an existing network of contractors in the area, and they were familiar with the removal and refurbishment process. Asbestos was originally identified within the build of a particular style of houses that were built a number of years ago. The previous administration had started a project of removal and identified 119 houses that required this work. By the end of March 2024 45 of those houses would have had the asbestos removed but will also have been refurbished and modernised. By the end of March 2024 the existing contract with United Living would have expired; this contract would now be renewed with a target of completing the overall project by the end of the 2024/2025 financial year.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To seek approval to enter into a contract with United Living to complete the works associated with the Earlesfield Refurbishment Project. The contract will be awarded via the Fusion 21 Framework for a period of 12 months commencing 1 April 2024.

Recommendations

It is recommended that Cabinet:

1. Approve the award of a contract to United Living to complete the works associated with the Earlesfield Project for a period of 12 months with a contract value of £2.4m. Decision Information

Is this a Key Decision? Yes

Does the report contain any No exempt or confidential information not for publication? What are the relevant corporate Housing that meets the needs of all residents priorities? Healthy and strong communities

Which wards are impacted? Grantham only.

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance

1.1The cost of these works will be met from the approved budget for the HRA capital programme.

Reviewed/Completed by: Alison Hall-Wright, Deputy Director (Finance & ICT) and Deputy S151 Officer

Procurement

1.2It is confirmed that a fully compliant procurement process has been completed and the Council’s Procurement Lead has been consulted throughout the process.

Completed by: Helen Baldwin, Procurement Lead Legal and Governance

1.3There are no significant legal and governance risks arising from the report which are not already reflected elsewhere in the report, particularly in relation to procurement and compliance with the Council’s Contract Procedure Rules.

Completed by: Graham Watts, Assistant Director (Governance and Public Protection) and Monitoring Officer

Risk and Mitigation

1.4Any risks will be monitored as part of the contract management process.

Completed by: Tracey Elliott, Governance and Risk Officer

Health and Safety

1.5As part of the tender documentation, a comprehensive Pre-Construction Information document was provided for the contractor to consider the aspects of health & safety associated with the works.

1.6When the contract is awarded to the successful bidder, a Construction Phase Plan will be requested/provided by the Principal Contractor, and this will detail how all the health & safety risks associated with the construction phase will be implemented to minimise the risks where possible or eliminate them.

Completed by: Phil Swinton, Emergency Planning and Health and Safety Lead

2. Background to the Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award Earlesfield Refurbishment ProjectReport 148 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Contract Award Earlesfield Refurbishment ProjectThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies