Award of Contract for the Construction of the Waste Depot, Turnpike Close Grantham

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 April 2024. Below is the council's own wording, with the papers it was decided on.

Item108

Resolved

Decision That Cabinet: 1. Approves the outcome of the tender process and appoints Lindum Group Ltd as the preferred contractor for the construction of the Turnpike Close construction contract. 2. Delegates to the Deputy Chief Executive in consultation with the Cabinet Member for Property and Public Engagement to enter into a NEC4 Professional Services Contract with Lindum Group Ltd in order to develop the submitted design to Stage 4 supported by a Value Engineering process in order to align the overall contract price with the approved budget. 3. Following the conclusion of the Value Engineering, delegation be granted to the Deputy Chief Executive in consultation with the Cabinet Member for Property and Public Engagement to enter into the construction contract to enable the commencement of the works. Alternative options considered and rejected No other options were available as the decision to award the contract was essential to enable the project to continue to the construction stage. Reasons for decision This report set out the background behind the project. The procurement process that had been undertaken since the decision was taken by Council to allocate funding for this project. The awarding of the contract would enable the project to continue in accordance with the timeline. The business case for the Waste Depot was approved by Cabinet in September 2023, and the funding for the project was approved by Full Council in September 2023 and February 2024. An ‘expression of interest’ notice was published and presented to a list of approved contractors; from this, five contractors confirmed their interest in the project and were invited to tender for the work. This list of five contractors reduced to 2 for a number of reasons; the two remaining contractors formally submitted tenders and these were scored by a panel of experts using agreed criteria. The contractors were interviewed on 19 March 2024 and the bids were scrutinised; Lindum Group emerged from this process with the successful tender. The design of the Waste Depot would be reviewed in order to reduce the projected costs of the tender – a process known as ‘value engineering’. Once this process was complete, the construction contract could be entered into. It was hoped that works would commence no later than September 2024, with a completion by July 2025. The following points were highlighted during debate: · Officers were working with Lindum Group on bringing the costs of the tender down whilst not compromising the delivery or the quality of the project. · The ‘fit out’ of the depot could not be costed at the moment because investigations were still ongoing regarding the potential transfer of equipment from the existing site. · Whilst officers were confident of a start date of September 2024, the date was not definite because a value engineering exercise needed to be undertaken. · The ... view the full minutes text for item 108.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report sets out the procurement that has been undertaken in order to award the contract to the successful contractor for the construction of the new Waste Depot, Turnpike Close Grantham.

Recommendations

That Cabinet: 1. Approves the outcome of the tender process and appoints Lindum Group Ltd as the preferred contractor for the construction of the Turnpike Close construction contract. 2. Delegates to the Deputy Chief Executive in consultation with the Cabinet Member for Property and Public Engagement to enter into a NEC4 Professional Services Contract with Lindum Group Ltd in order to develop the submitted design to Stage 4 supported by a Value Engineering process in order to align the overall contract price with the approved budget. 3. Following the conclusion of the Value Engineering, delegation be granted to the Deputy Chief Executive in consultation with the Cabinet Member for Property and Public Engagement to enter into the construction contract to enable the commencement of the works.

Decision Information

Is this a Key Decision? Key Decision

Does the report contain any N/a exempt or confidential information not for publication? What are the relevant corporate Effective Council priorities? Which wards are impacted? Earlesfield Ward

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance

1.1Council has approved the necessary funding allocation in order to provide the resources to fund the construction works and the necessary project management support to deliver the contract. To ensure best price for the project and to bring the construction costs in line with the approved budget, it is recommended that value engineering is undertaken with the successful bidder. The current financial strategy is to fund the costs of the project from internal borrowing for the short term and there will be a requirement for the Council to provide an annual Minimum Revenue Provision (MRP) whilst the borrowing is undertaken (estimated over the asset life of 50 years). The MRP will be a requirement for each financial year following the asset becoming operational.

Completed by: Richard Wyles, Deputy Chief Executive and s151 Officer

Procurement

1.2This requirement has been compliantly tendered via further competition under the Pagabo framework. The tender opened on the 19th December 2023 and closed on 26th February 2024. 1.3 Two bids were received and the details of which are contained within this report. This procurement process has been managed by Gleeds Property Consultants and SKDC Procurement Lead has been kept informed throughout.

Completed by: Helen Baldwin, Procurement Lead

Legal and Governance

1.4There are no significant legal and governance implications associated with this proposal, which represents the award of a contract through a compliant procurement process, that are not already referenced elsewhere in the report.

Completed by: Graham Watts, Monitoring Officer

2. Background to the Report

2.1At its meeting on 11 September 2023, Cabinet considered the business case for the transfer of the depot from the current location at Mowbeck Way Grantham to a new location at Turnpike Close Grantham. In summary the key elements of the business case are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Contract for the Construction of the Waste Depot, Turnpike Close GranthamReport 353 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Award of Contract for the Construction of the Waste Depot, Turnpike Close GranthamThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies