Resolved

Decision That Cabinet approves the contract award for the supply, installation and maintenance of stairlifts, through floor lifts, step lifts and external modular ramps to EMS Lifts Ltd with an annual contract value of £120k for a period of 3 years with the option to extend by a further 1 year plus 1 year. Alternative options considered and rejected No other options were considered. This function cannot be delivered in house and the current arrangements are due to end, therefore this was the only option considered. Reasons for decision The current contractual arrangements were ending and following a robust procurement process the successful supplier. Due to the contract value and in accordance with the Constitution, the contract award requires Cabinet approval. Two teams had been involved in working on the contract award; the Disabled Facility Grants team were responsible for private households, and the Council Adaptation team were responsible for Council tenants. A joint procurement exercise had taken place to find a new contractor to take on both services. There was no means testing for private households. The discretionary financial limit was nominally £15,000, but there was discretion to go above this award. Items such as stairlifts tended to be lower in value and would not meet the discretionary threshold. Funding could not be awarded retrospectively.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To obtain approval to enter into a contract with EMS Lifts Ltd for the provision, installation and maintenance of stairlifts, through floor lifts, step lifts and ramps for the Disabled Facility Grants Team and Council Adaptations service covering both private and council owned properties for a period of 3 years with the option to extend by a further 1 year plus 1 year.

Recommendations

That Cabinet approves the contract award for the supply, installation and maintenance of stairlifts, through floor lifts, step lifts and external modular ramps to EMS Lifts Ltd with an annual contract value of £120k for a period of 3 years with the option to extend by a further 1 year plus 1 year

Decision Information

Is this a Key Decision? Yes – included on the forward plan

Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Housing Effective council Which wards are impacted? All wards 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance

1.1The financial implications are set out within the report. The contract costs can be met from the existing Disabled Facilities Grant capital budget.

Completed by: Paul Sutton Interim Head of Finance (Deputy 151)

Procurement

1.2This tender was a compliant process with no risk to challenge.

Completed by: Helen Baldwin – Procurement Lead

Legal and Governance

1.3There are no significant legal and governance implications arising from this report.

Completed by: Graham Watts, Monitoring Officer

2. Background to the Report

2.1The Council has a legal obligation under The Housing Grants, Construction and Regeneration Act 1996 to provide adaptations to disabled individuals’ properties where they meet the eligibility requirement. This obligation is undertaken via the Disabled Facility Grants Team for those living in the private sector and the Council Adaptations Service for those living in a Council owned property.

2.2The current contract for the Council Adaptations service expires on 30 June 2024 and the pilot for the Private Sector Housing adaptations is not delivering as expected and therefore will not be continuing so the Council there is a requirement to procure a new contractor.

2.3The purpose of this report is to seek approval to enter into a contract with EMS Lifts Ltd for the supply, installation and maintenance of stairlifts, through floor lifts, step lifts and external modular ramps. The contract value is £120,000 per year, with an initial term of 3 years and with the option to extend for two subsequent years. This totalling a possible contract length of 5 years and a full value of £600,000.

2.4Welland Procurement established that no frameworks were available which met the specification for the contract so an open tender process was followed. The tender opportunity was advertised on Contracts Finder which resulted in 5 tender submissions being received to be evaluated.

2.5The tender was made up of two questionnaire sets: one questionnaire for the selection criteria questions and one for award criteria questions. The award criteria questions were evaluated as follows:

Evaluation Criteria Weighting Quality 60% Price 40%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Contract award supply and install of Stairlifts, through floor lifts and external modular rampsAppendix 1 326 KB Download
PDF
Contract award supply and install of stairlifts, through floor-lifts and external modular rampsReport 151 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Contract award supply and install of stairlifts, through floor-lifts and external modular rampsThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies