CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Kesteven District Council
Cabinet, Tuesday 8 July 2025 at 2.00pm

Contract award for Gas and Electrical Auditing

Approved Executive 2 papers

Cabinet approved this item on Tuesday 8 July 2025. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

Decision That Cabinet approves the award of a contract to Morgan Lambert for the provision of carrying out gas and electrical auditing in South Kesteven District Council owned dwellings, with an annual value of £50k for a period of 3 years with the option to extend annually for up to 2 years. Alternative options considered and rejected Consideration had been given to the option of carrying out the work in-house, but this was not a viable option due to the specialised nature of this work and third-party assurance required. Not carrying out the work was also not practicable as this would have led to further issues as noted above. Carrying out this service by means of a third party ensured impartiality was maintained ensuring a fair and transparent service. Reasons for the decision Audits were undertaken on a sample of the gas and electrical works completed each month which provide assurance regarding the quality of the works. The annual cost for this service was anticipated at £50,000 per annum and would be met from the Technical Services Gas and Electrical capital budgets. The procurement opportunity was tendered as a mini competition using a framework run by Efficiency East Midlands (EEM). Following publication of the opportunity five Expressions of Interest were received which resulted in two Tender Submissions. Morgan Lambert have given the best tender submission through the combination of price and quality to carry out gas and electrical auditing on the Council’s housing stock and to ensure the Council has a compliant contract in place which is compliant with procurement requirements. The contract award was for the auditing of gas and electrical works rather than for gas and electrical inspections. This award allowed a separate company to audit Council work.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To seek approval to enter into a contract with Morgan Lambert for the provision of carrying out gas and electrical auditing to Council owned dwellings for South Kesteven District Council.

The contract will be awarded for an initial period of 3 years with an option to extend annually for up to 2 years.

Recommendations

That Cabinet approves the award of a contract to Morgan Lambert for the provision of carrying out gas and electrical auditing in South Kesteven District Council owned dwellings with an annual value of £50k for a period of 3 years with the option to extend annually for up to 2 years. 1. Decision Information

Is this a Key Decision? Yes Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Housing that meets the needs of all residents

Which wards are impacted? (All Wards); 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The contract will be funded from the revenue compliance budget which has sufficient budget in place to cover this spend.

Completed by: David Scott – Assistant Director of Finance (Deputy s151 officer)

Procurement

1.2This contract was compliantly tendered via a Mini competition through the EEM framework DPS0010. Full details of the tender process can be found in Appendix 1.

Completed by: Helen Baldwin (Procurement Lead)

Legal and Governance

1.3Cabinet is the correct body to take this decision.

Completed by: Alison Hall-Wright, Deputy Monitoring Officer

2. Background to the Report

2.1The purpose of this report is to provide assurance to Cabinet that relevant procedures were followed in the selection of a provider to carry out gas and electrical auditing and to seek approval to enter into a contract with Morgan Lambert. The contract would be awarded for an initial period of 3 years with an option to extend annually for up to 2 years, giving a total duration of 5 years.

2.2Gas and electrical auditing is an essential quality assurance process to ensure the gas and electrical works undertaken in the Council’s housing stock are carried out in accordance with health and safety regulations and industry best practice.

2.3Audits are undertaken on a sample of the gas and electrical works that are completed each month which provides assurance regarding the quality of the works. The annual cost for this service is anticipated at £50,000 per annum and will be met from the Technical Services Gas and Electrical capital budgets. 2.4. The procurement opportunity was tendered as a mini competition using a framework run by Efficiency East Midlands (EEM). Following publication of the opportunity 5 Expressions of Interest were received which resulted in 2 Tender Submissions.

2.5The Tender was made up of two questionnaire sets: one for the selection criteria and one for the award criteria. The award criteria questions were evaluated as follows:

Evaluation Weighting Quality 60% Price 40%

2.6An evaluation panel was constructed to ensure that individuals assigned to evaluate questions were the most suitable and relevant to the criteria being examined, based upon qualifications and experience. Each question was evaluated by at least two evaluators and their scores, and comments recorded.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Contract award for Gas and Electrical AuditingAppendix 1 451 KB Download
PDF
Contract award for Gas and Electrical AuditingReport 228 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Contract award for Gas and Electrical AuditingThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open