CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Kesteven District Council
Cabinet, Tuesday 7 October 2025 at 4.00pm

Corporate Asset Management Strategy Review

Approved Executive 2 papers

Cabinet approved this item on Tuesday 7 October 2025. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

Decision Cabinet approve the adoption of the updated Corporate Asset Management Strategy 2025-2030. Alternative options considered and rejected Consideration had been given to not updating the existing strategy and relying on the existing outdated Asset Management Strategy 2022-2027. This option was considered inappropriate, as the existing Strategy outlined need for a mid-term review and there had been significant change since the Strategy’s initial implementation. This may also have resulted in a missed opportunity to support the delivery of the Council’s Corporate Plan. Manage the portfolio on a purely responsive basis – this was not pursued as this tended to be more costly than a strategic approach to management of the portfolio and could have impacted on the delivery of services. Reasons for the decision This was a medium-term strategy to manage corporate property within the GF set within the context of the Corporate Plan. There were 11 key actions within the Strategy: 1. Service Planning and Asset Appraisal 2. Asset Information 3. Compliance 4. Maintenance and Investment 5. Current Major Projects 6. Regeneration 7. Equalities 8. Investment Portfolio 9. Working with Partners 10. Energy Efficiency 11. Value for Money The Strategy had been submitted to Finance and Economic Overview and Scrutiny Committee who had recommended no edits to the Strategy. Much importance was attached to properly maintaining assets. The Council invested in a new Asset Management System approximately two years ago. The Strategy was clear that the Council was trying to plan rather than reactively spend. This was difficult due to many years of backlog, but it was slowly being turned around. Condition surveys drove investment plans. Officers were focussing on desirable and long-term repairs [JW1] Officers looked at reactive repairs in terms of planned maintenance. If repairs were failing at a car park then investigations would take place to find out whether there was any planned maintenance. If the repair was urgent it would be dealt with there and then; the central database was updated alongside this. A ratio of 70:30 in favour of planned maintenance was aimed for; currently it was the other way around. There was an asset disposal strategy. Criteria were followed before investing in assets. There was a delegation in place for senior officers in consultation with the Cabinet Members for Property and Public Engagement and Finance to dispose of GF assets up to a value of £2 million. [JW1] Richard is this what was meant by Cat C and D repairs?
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To review and adopt the Corporate Asset Management Strategy 2025-2030, ensuring the strategy is in accordance with SKDC current priorities and objectives.

Recommendations

Cabinet is asked to approve the adoption of the updated Corporate Asset Management Strategy 2025-2030

Decision Information

Is this a Key Decision? No Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Connecting communities Sustainable South Kesteven Enabling economic opportunities Effective council Which wards are impacted? (All Wards); 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The Council’s asset base is the largest value on the Council’s balance sheet and is a significant annual cost both in terms of operational cost but also planned and responsive maintenance. It is important the Council has a clear and robust strategy in respect of the asset portfolio to ensure the assets are well maintained and managed in order to provide value for money and to minimise cost exposure. This is particularly important in a climate or rising costs and operational demands.

Completed by: Richard Wyles, Deputy Chief Executive and s151 Officer

Legal and Governance

1.2It is good governance practice for a Local Authority to have an up to date Corporate Asset Management Strategy. No legal implications are identified in this report.

Completed by: James Welbourn, Democratic Services Manager

2. Background to the Report

2.1The draft Corporate Asset Management Strategy 2025-2030 (AMS) was considered by the Finance and Economic Overview and Scrutiny Committee on 23rd September 2025. The Committee recommended the Strategy to Cabinet without amendments. The AMS will provide update and replace the existing Asset Management Strategy 2022-2027, which previously included HRA assets, which no longer sit within the same directorate.

2.2The AMS is a medium-term plan for optimising the value, performance, and utility of the Council’s corporate property assets — whether owned, leased, or managed. It goes beyond day-to-day property management by aligning property decisions with broader corporate strategic aims, financial returns and sustainability targets.

2.3The AMS sets the framework for managing the Councils property portfolio effectively over the next 5 years (2025 to 2030) and will guide future strategic property decisions to make sure the property portfolio is managed sustainably and efficiently and so it can adapt to remain fit for the future and support frontline delivery.

2.4The strategy is designed to align with the Council’s Corporate Plan and strategies, policies, and services to support the residents of South Kesteven. It provides a framework for managing owned, tenanted and leased assets, ensuring they are fit for purpose despite financial constraints. The strategy focuses on optimal and flexible use, sustainable maintenance, and futureproofing to meet short, medium, and long-term needs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Asset Management StrategyAppendix A 7.6 MB Download
PDF
Corporate Asset Management Strategy ReviewReport 233 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Corporate Asset Management Strategy ReviewThis decision
  2. Maintenance Strategy (Corporate Property Assets)Approved
  3. Corporate Asset Management StrategyApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open