Contract Award for Mixed Vehicle Procurement

Approved Executive 1 paper

Cabinet approved this item on Tuesday 7 October 2025. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

Decision Cabinet approved the award of the following 14 contracts for the direct purchase of vehicles at a combined cost of £2.6m: • Volvo – 1 x 26t Hook Lift • Harris Maxus –3 x 3.5t Caged Tippers, 6 x 3.5t Caged Tippers with Tail Lifts and 1 x 3.5t Arb Tipper • Motus (Isuzu) – 2 x 3.5t Caged Tippers • Motus (Fiat) – 16 x Medium Panel Vans • Toyota – 7 x Small Panel Vans and 7 x Large Panel Vans • Lookers Ford – 2 x 4x4 Pickups • Thompson – 2 x 7.5t Tippers with Tail Lift and Removable Mesh Infilled Side Panels and 3 x 7.5t Caged Tippers • Aebi Schmidt – 1 x 6t Compact Road Sweeper • Karcher – 1 x 6t electric Compact Road Sweeper • Bucher – 2 x 12t Truck Mounted Road Sweepers 4 Alternative options considered and rejected Other options considered were: · Do not procure new vehicles – this would have resulted in an increased risk of service failure, reputational damage and a breach of statutory duties. · Run current vehicles beyond the recommended usage period – this risked service failure due to maintenance requirements, alongside increased repair costs. Reasons for the decision The Council required vehicles for the delivery of statutory services. The recommended vehicle purchases would support service delivery and ensure reliability and efficiency. All 14 contracts had been through a compliant procurement process with a fair and robust tender. All vehicles would be purchased outright. 54 vehicles would be purchased over 3 years, with 27 purchased through the Housing Revenue Account and used for Housing services. £812414 of the total amount was funded from the HRA, with the remaining funds coming from the General Fund (GF). These purchases increased electric vehicle usage whilst maintaining existing services. The variety of vehicles demonstrated the diversity of the service offering. The following points were highlighted during debate: · Old vehicles would be responsibly disposed of, most likely through auction. There were strict rules about age of vehicles. Old vehicles were not routinely retained for parts as there wasn’t adequate space to store them. Contingency had been built into the procurement for spare vehicles, for maintenance and emergency use. Spares were sourced through contracted suppliers. All vehicles would be supplied with warranties. · The design of the new fleet would be uniform. However, there was the potential for having special livery on vehicles as and when desired. · The procurement process had aimed to ensure the fleet was future proofed as far as possible.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report seeks approval to purchase vehicles including road sweepers, caged tippers, pickup vehicles, a hook lift, and panel vans. The procurement of these vehicles has been completed through a compliant process and as the vehicles will be purchased outright there is no contract length to consider. The procurement is for 54 vehicles at a combined cost of £2.6m.

Recommendations

Cabinet is recommended to:

1. Approve the award of the following 14 contracts for the direct purchase of vehicles at a combined cost of £2.6m: • Volvo – 1 x 26t Hook Lift • Harris Maxus –3 x 3.5t Caged Tippers, 6 x 3.5t Caged Tippers with Tail Lifts and 1 x 3.5t Arb Tipper • Motus (Isuzu) – 2 x 3.5t Caged Tippers • Motus (Fiat) – 16 x Medium Panel Vans • Toyota – 7 x Small Panel Vans and 7 x Large Panel Vans • Lookers Ford – 2 x 4x4 Pickups • Thompson – 2 x 7.5t Tippers with Tail Lift and Removable Mesh Infilled Side Panels and 3 x 7.5t Caged Tippers • Aebi Schmidt – 1 x 6t Compact Road Sweeper • Karcher – 1 x 6t electric Compact Road Sweeper • Bucher – 2 x 12t Truck Mounted Road Sweepers Decision Information

Is this a Key Decision? Yes Does the report contain any exempt or Yes – Appendices 1 and 2 are exempt confidential information not for publication? under paragraph 3 of Schedule 12A of the Local Government Act 1972 – commercially sensitive information related to the Council and 3rd parties. What are the relevant corporate priorities? Sustainable South Kesteven Effective council Which wards are impacted? All Wards

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1Replacement vehicles are required to ensure the Council can meet its statutory duties. The Vehicle Replacement Programme Budget is set annually, and the budget includes provision for the vehicles included within this procurement exercise.

1.2The costs associated with this procurement exercise initially exceeded the budget, however, the option to replace the proposed electric sweeper with a different electric vehicle will ensure the budget is not exceeded and the fleet still increases the use of electric vehicles.

1.3This procurement covers 54 vehicles, which will be purchased over three years in- line the agreed Vehicle Replacement Programme. The total estimated cost of all vehicles within this procurement exercise is £2.6m. Of the 54 vehicles, 27 are funded from the HRA for the Council's Housing Services and these vehicles are estimated to cost £812,414. The remaining cost is to be funded from the Council’s General Fund.

Completed by: Richard Wyles, Deputy Chief Executive and s151 Officer

Procurement

1.4This requirement had been procured compliantly and in line with the Councils Contract Procedure Rules. 1.5 Vehicles were procured via further competition under The Procurement Partnerships Fleet Framework

Completed by: Helen Baldwin, Procurement Lead

Legal and Governance

1.6The necessary processes have been followed in accordance with the Council’s Contract Procedure Rules – this decision is above the Key Decision threshold. There are no further significant legal, or governance implications not already highlighted within the body of the report.

Completed by: James Welbourn, Democratic Services Manager

2. Background to the Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award for Mixed Vehicle ProcurementReport 290 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Contract Award for Mixed Vehicle ProcurementThis decision
  2. Award of Arboricultural Services ContractApproved
  3. Award of Contract for Play Equipment Repairs and Operational InspectionsApproved
  4. Contract Award for Microsoft Subscription AgreementApproved
  5. Award of Contract for Christmas LightsApproved
  6. Contract Award - New Build Housing Scheme at Toller Court, HorblingApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies