AI summarySouth Kesteven District Council Cabinet awards a one year, £2 million contract to Global HSE Solutions for fire compartmentation works across its housing stock.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedOne year direct award, no extension provision
MoneyUp to £2 millionQuoted total £1,645,419 from 11 December 2025
What happens nextTender for longer-term contract underwayThis award covers the interim period only
Who it affectsAll wardsCouncil tenants in domestic and sheltered housing
What was decided
Cabinet approved a one year direct award to Global HSE Solutions for fire prevention and compartmentation works on council owned dwellings, with no extension provision. Report P2, 2.1
The contract is a direct award through the LHC Fire Safety framework, used because the previous contract with the same supplier expired in September 2025. Report 2.2, 2.3, 2.5
Works will cover fire doors, fire breaks, fire curtains and other compartmentation measures arising from Fire Risk Assessments. Report 2.4
Why
The council needed a competent contractor in place to deliver fire prevention and compartmentation works and keep its housing stock meeting required fire safety standards. Report 5.1, 5.3, 3.1
Fire compartmentation is a core part of the council's fire safety strategy, containing fire, smoke and heat for a set time to protect occupants and support safe evacuation. Report 1.5, 1.6
Doing the work in-house was ruled out because the work is specialist and needs specific materials to meet fire safety standards. Report 4.1
What happens next
The procurement team is preparing a tender for a new, longer-term contract at a greater value to replace this interim award. Report 1.3
Any additional unforeseen works found once the contract starts will be separately quoted and absorbed within the £2 million contract value. Report 2.7
All works must meet Approved Document B of the Building Regulations, the RRFSO, the Fire Safety Act 2021 and the Building Safety Act 2022. Report 1.6
The money
£2 million Maximum value of the one year contract Report P2
£1,645,419 Total quoted cost for the identified works Report 2.6
£232,509 Quotation: compartmentation works across 7 schemes Report 2.6
£292,587 Quotation: fire doors across 7 schemes Report 2.6
£351,608 Quotation: communal areas across 7 schemes Report 2.6
£768,715 Quotation: flat compartmentation across 13 schemes Report 2.6
Options considered
Chosen: Award one year contract to Global HSE Solutions. Supplier has 3-4 year track record; specialist work and urgent need for compliant contractor Report P2, 2.3, 4.1
Rejected: Carry out the works in-house. Specialist nature of work and material requirements to meet fire safety standards Report 4.1
Implications
Financial: Sufficient capital budget is allocated within the HRA to fund this contract. Report 1.1
Legal: A direct award under the LHC framework is compliant with the Procurement Act and carries no risk of challenge. Report 1.2
Legal: Cabinet is the decision maker because of the contract's value. Report 1.4
Risk: Council Contract Procedure rules would normally require competition at this value; direct award approved because of urgency and unforeseen additional work. Report 1.3
Staffing: Award means the council does not need to bring the specialist work in-house. Report 4.1
Other: Supports statutory housing compliance duties as a social landlord and the Healthy and Strong Communities corporate priority. Report 3.1, P4
Tenants in the council's domestic housing stock Report 2.4, 3.1
Residents in the council's sheltered housing stock Report 2.4
Visitors and others who use the premises Report 2.4
Timeline
September 2025: Previous contract with Global HSE Solutions expired Report 2.3
10th November 2025: LHC issued expression of interest to Global HSE Solutions Report 2.6
11th December 2025: Quotations received from Global HSE Solutions Report 2.6
2026-01-15: Cabinet decision to award the new contract
Plain English for the jargon
Fire compartmentation: Building design that contains fire, smoke and heat within an area for a set time to protect occupants and aid evacuation.
HRA: Housing Revenue Account, the ringfenced account that funds the council's landlord housing functions.
FRA: Fire Risk Assessment, a required review of fire safety in a building.
LHC framework: London Housing Consortium procurement framework, used here for Fire Safety works.
RRFSO: Regulatory Reform (Fire Safety) Order 2005, the main fire safety legislation for non-domestic premises.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item88
Resolved
Decision Cabinet approved the award of a contract to Global HSE Solutions for the provision of carrying out fire prevention and compartmentation works at South Kesteven District Council owned dwellings for a period of 1 year. The value of this contract is up to £2 million Other options considered Consideration had been given to the option of carrying out the works “in-house”, but due to the specialist nature of the work and material requirements to ensure the fire prevention and compartmentation works were completed to the required fire safety standards, this was not a viable option. Reasons for the decision To ensure the Council had a competent contractor in place to deliver the required fire prevention and compartmentation works. To ensure that the Council’s housing stock meets the required fire safety standard and residents have safe homes to live in. The Council had been using Global HSE for these types of works for a 3–4-year period. The current contract had ended; this was a 1-year contract to allow the completion of previously identified works. These works included fire doors, fire breaks, fire curtains and other general compartmentation work. A compliant contract will be in place to deliver the work.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
To seek approval to enter into a contract with Global HSE Solutions for the provision of carrying out fire prevention and compartmentation works to council owned dwellings for South Kesteven District Council.
Recommendations
Cabinet is asked to approve the award of a contract to Global HSE Solutions for the provision of carrying out fire prevention and compartmentation works at South Kesteven District Council owned dwellings for a period of 1 year. The value of this contract is up to £2 million.
Decision Information
Is this a Key Decision? Yes Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Housing that meets the needs of all residents. Healthy and strong communities
Which wards are impacted? All Wards 1. Implications
Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:
Finance and Procurement
1.1There is sufficient capital budget allocated within the HRA to fund this contract.
Completed by: David Scott – Assistant Director of Finance
Procurement
1.2Under the Procurement Act, a direct award under a framework is complaint and at no risk of challenge.
1.3Under the councils’ Contract Procedure rules, a contract of this value should be competed. However, due to the urgency and unforeseen additional work required, it is advised to allow for this 1-year contract to go ahead. Approval to direct award has also been signed. The team are currently working on a tender to get a new, longer-term contract in place for a greater value.
Completed by: Helen Baldwin (Procurement Lead)
Legal and Governance
1.4Due to value, Cabinet is the decision maker for the proposed contract award.
Completed by: James Welbourn, Democratic Services Manager
Health and Safety
1.5The completion of Fire compartmentation works form a key part of the Council's Fire safety strategy. Fire compartmentation is designed to contain fire, smoke, and heat within a specific area of a building for a set time, preventing its spread to protect occupants, provide safe evacuation routes, and allow emergency services time to respond, protecting lives and property.
1.6The awarding of this contract ensures the Council remains committed to increasing fire safety for tenants and compliant with the Regulatory Reform Fire Safety Order 2005 (RRFSO), as well as the Fire Safety Act 2021 and Building Safety Act 2022. 1.7 All works will be completed to the technical requirements set out in Approved Document B of the Building Regulations
Completed by: Philip Swinton, Head of Health, Safety, Compliance and Emergency Planning
2. Background to the Report
2.1This report seeks approval to enter into a contract with Global HSE Solutions for the provision of carrying out fire prevention and compartmentation works on South Kesteven District Council’s (SKDC’s) housing stock. The contract would be awarded for a fixed term of 1 year with no extension provision.
2.2This contract is a direct award and is being proposed for a 1-year term only; this is to allow for urgent outstanding fire prevention and compartmentation works to be completed following Fire Risk Assessments (FRA’s) and for the council to meet housing compliance requirements whilst a longer-term solution is procured.
2.3Global HSE Solutions were previously under contract to SKDC for the same works. The previous contract expired in September 2025. This 1-year contract is to allow for the completion of the previously identified works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.