Facilities Management Contract

Approved Executive 1 paper

AI summarySouth Kesteven District Council Cabinet awards a Facilities Management contract to Key Integrated Services (Maintenance) Ltd for up to £450,000 a year, with a total potential value of £3,150,000 over up to seven years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo Key Integrated Services (Maintenance) Ltd
MoneyUp to £450,000 per yearTotal up to £3,150,000 with extensions
What happens nextSign Parent Company GuaranteeDelegated to Deputy Chief Executive and s151 Officer
Who it affectsAll wardsCovers all SKDC corporate buildings

What was decided

Cabinet approved awarding the Facilities Management contract to Key Integrated Services (Maintenance) Ltd for up to £450,000 a year, initially for three years with an option to extend by up to two further two-year periods. Report P3

Cabinet delegated authority to the Deputy Chief Executive and Section 151 Officer to sign a Parent Company Guarantee with Key Integrated Services (Holdings) Ltd and to agree any extensions in consultation with the Cabinet Member for Property and Public Engagement. Report P4

Why

The previous external contract has reached the end of its maximum term and cannot be extended, so a new contract is needed to meet legal, health and safety compliance and maintain corporate assets. Report 2.1, 2.2

A new contract supports a structured approach to legal and safety obligations, keeps assets in safe working order, helps sustainability objectives, and gives budget certainty, using providers with specialist expertise. Report 5.1

Bringing the service in-house was ruled out because SKDC has no specialist maintenance operatives and setting up an in-house team would need significant resource and financial investment. Report 4.1, 4.2

What happens next

The Deputy Chief Executive and s151 Officer will sign a Parent Company Guarantee with Key Integrated Services (Holdings) Ltd to secure the supplier's financial resilience. Report 2.21

The contract can be extended by up to two further two-year periods, with the decision delegated to the Deputy Chief Executive and s151 Officer in consultation with the Cabinet Member for Property and Public Engagement. Report 1.1

The money

  • £450,000 Annual contract value, up to Report P1, P13
  • £3,150,000 Total contract value including extensions Report P13
  • £125,000 Annual spend on covered activities, in the region of, for planned maintenance Report 2.19

Options considered

  • Chosen: Award the contract to Key Integrated Services (Maintenance) Ltd. Highest scoring bid at 89.33%, provides specialist expertise and supports compliance and budget certainty. Report P38, 5.1
  • Rejected: Adopt an in-house maintenance model. Would require recruiting specialist personnel in HVAC, electrical and gas safety and significant financial investment; SKDC has no specialist maintenance operatives. Report 4.1, 4.2

Implications

  • Financial: Annual spend is in line with budgeted levels, but exact expenditure may vary due to the responsive nature of some works. Report 1.1
  • Legal: Cabinet is the correct body to consider the award given the contract value. Report 1.3
  • Risk: A Parent Company Guarantee is required to ensure the supplier has sufficient financial resilience to deliver the service. Report 2.21, 1.1

Who and where

  • Staff and users of SKDC corporate buildings, including The Picture House, South Kesteven House, leisure facilities and the two arts centres Report 2.3
  • All wards across South Kesteven Report P6
  • The Corporate Property Team at SKDC Report 3.1, 5.1

Timeline

  • 3 years (36 months): Initial contract term Report P13
  • 2 x 24 months (4 years): Optional extension periods Report P13
  • Up to 7 years in total: Maximum possible contract length if both extensions used Report P13

Plain English for the jargon

  • Facilities Management (FM): The service that maintains and manages a building, including planned, reactive and statutory maintenance.
  • Planned Preventive Maintenance (PPM): Maintenance scheduled in advance to keep equipment and buildings working safely and efficiently.
  • HVAC: Heating, ventilation and air conditioning systems.
  • PWTAG: Pool Water Treatment Advisory Group, which sets the code of practice for swimming pool water safety.
  • Parent Company Guarantee: A promise by the parent company to cover the obligations of its subsidiary if it fails to deliver.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item102

Resolved

Decision That Cabinet: 1. Approve the award of the Facilities Management contract to Key Integrated Services (Maintenance) Ltd for an annual sum of up to £450,000 for a period of 3 years with an option to extend for a further 2 periods of 2 years. 2. Delegate to the Deputy Chief Executive and Section 151 Officer to sign a Parent Company guarantee with Key Integrated Services (Holdings) Ltd in respect of the award of the Facilities Management Contract. 3. Delegate to the Deputy Chief Executive and Section 151 Officer, in consultation with the Cabinet Member for Property and Public Engagement to extend the contract by up to a further two periods of two years should this be required. Other options considered The Council could have adopted an in-house maintenance model. However, this approach would have required the recruitment of specialist personnel to deliver services in key technical areas such as heating, ventilation and air conditioning (HVAC), electrical systems and gas safety. The Council does not employ any specialist maintenance operatives within the Corporate Property Team, and it would have required significant resource and financial investment to have established a capable in-house maintenance approach. Reasons for the decision By entering a new contract, SKDC could now: a) Continue with a structured approach to managing legal and health & safety obligations, including gas, electrical, and building safety requirements, ensuring a reducing risk of regulatory breaches. b) Ensure all assets and equipment were maintained in a safe and operational condition, supporting the continued availability and functionality of facilities. c) (through the Corporate Property Team) maintain and enhance the existing planned maintenance programme, monitor asset performance, and implement new initiatives to contribute towards SKDC’s sustainability objectives. d) Operate within forecasted maintenance budgets, providing greater certainty and planning capability over the contract period. e) Continue to utilise providers with expert knowledge across a wide range of building maintenance disciplines, ensuring professional and effective service delivery.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To seek approval for the award of the Facilities Management Contract to Key Integrated Services (Maintenance) Ltd. for an annual sum of up to £450,000 for a period of 3 years with an option to extend for a further 2 periods of 2 years.

Recommendations

Cabinet is asked to:

1. Approve the award of the Facilities Management contract to Key Integrated Services (Maintenance) Ltd for an annual sum of up to £450,000 for a period of 3 years with an option to extend for a further 2 periods of 2 years.

2. Delegate to the Deputy Chief Executive and s151 Officer to sign a Parent Company guarantee with Key Integrated Services (Holdings) Ltd in respect of the award of the Facilities Management Contract.

Decision Information

Is this a Key Decision? Yes Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Sustainable South Kesteven Enabling economic opportunities Effective council Which wards are impacted? (All Wards); 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The procurement of the facilities management has been undertaken in accordance with the Council’s Contract Procedure Rules. The annual anticipated spend level is in accordance with budgeted levels however the exact expenditure level may vary due to the responsive nature of some of the necessary works. Given the value of the works, it is necessary to receive a Parent guarantee from the holding company.

Completed by: Richard Wyles, Deputy Chief Executive and s151 Officer

Procurement

1.2The tender has been carried out by Welland Procurement. The procurement is in accordance with the Council's Contract Procedure Rules. The summary of the contract is:

Annual Value £450,000 Initial Term Three Years (36 months) Option Extensions 2 x 24 months (4 Years) Total Contract Value £3,150,000 Including Extensions

Completed by: Helen Baldwin (Procurement Lead)

Legal and Governance

1.3Due to the value of the contract, Cabinet is the correct body to consider this report.

Completed by: James Welbourn, Democratic Services Manager

2. Background to the Report

2.1South Kesteven District Council (SKDC) is currently in contract with an external provider for the provision of Facilities Management (FM) and maintenance services across the Council’s corporate assets. This contract has now reached the end of its maximum term and cannot be extended further, necessitating the procurement of a new contract.

2.2The contract is essential to ensure that the Council meets all legal, health, and safety compliance requirements, while maintaining Council assets in a safe, efficient, and cost-effective condition for use by both staff and the public.

2.3The scope of the contract covers all SKDC (General Fund) corporate buildings and associated assets, including key operational sites such as The Picture House, South Kesteven House, the leisure facilities and both arts centres. The proposed new contract also provides SKDC with the flexibility to add or remove assets as required, ensuring the arrangement can adapt to changes within the Council’s property portfolio.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Facilities Management ContractReport 243 KB DownloadRead as text

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open