Wellington Way, Market Deeping - Approval of Contract Sum Increase
ApprovedExecutive2 papers
AI summarySKDC Cabinet approved a £190,000 increase to the £1.926m construction contract for the 11-unit Wellington Way housing scheme in Market Deeping. The increase covers additional works after previously unknown ground contamination was found on site.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedExtra £190,000 for Wellington Way housing scheme
Money£190,000Increase funded from HRA Capital Receipts Reserve
What happens nextConstruction to continueScheme to proceed without delay following funding approval
Who it affectsMarket & West Deeping ward11-unit council housing development on Wellington Way
What was decided
Cabinet approved a £190,000 increase to the £1.926m construction contract sum for the 11-unit Wellington Way, Market Deeping new build housing scheme.
The increase was needed because site investigations after contract award found previously unknown areas of ground with historic contamination that could not reasonably have been identified at the tender stage.
The additional works will be funded from HRA capital receipts.
Why
Approval avoids delays to the project and protects delivery of the scheme, addressing ongoing local housing need and maintaining programme certainty.
The funding enables delivery of high quality, sustainable council housing while protecting the Council's investment.
The scheme supports the Corporate Plan housing priority, with strong local demand in Market Deeping for one and two bedroom homes. Report 2.2, 2.10
What happens next
The Wellington Way scheme will proceed without delay, with a project risk register to be created jointly between the contractor and the Council and subject to ongoing review. Report 1.4
The contractor will insure the building works until the properties are handed over to the Council. Report 1.4
Procurement processes were followed under the Council's Contract Procedure Rules, the Procurement Act 2023 and the Public Contract Regulations 2015. Report 1.2
The money
£190,000 Increase to construction contract sum for Wellington Way housing scheme
£1.926m Original approved construction contract sum for Wellington Way housing scheme Report P4
£2m Budget for Wellington Way development included in 2025-2026 capital programme, funded from HRA Capital Receipts Reserve Report 1.1
£7,260 S106 agreement cost to the HRA, includes an NHS Health Contribution Report 2.7
Options considered
Chosen: Approve the £190,000 increase. Avoids delays, protects delivery, and addresses ongoing local housing need
Rejected: Not approve the additional funding. Would delay the project and could compromise delivery of the scheme
Rejected: Wait to commence the scheme or not build the development. Discounted due to the high levels of housing need in the area Report 4.1
Implications
Financial: Increase funded from HRA Capital Receipts Reserve; original £2m budget was included in the 2025-2026 capital programme. Report 1.1
Risk: A project risk register will be created jointly between the contractor and the Council, with mutual agreement on identified risks. Report 1.4
Climate: Homes will be built to current Building Regulations and Secured by Design Bronze Award standard, with air source heat pumps, solar PV and EV infrastructure in line with SKDC Policy SB1. Report 1.8, 2.8
Legal: Contract Procedure Rules require an award of this value to be made by Cabinet. Report 1.3
Other: A separate S106 agreement costs £7,260 to the HRA, including an NHS Health Contribution. Report 2.7
Households on the housing waiting list seeking one and two bedroom homes in Market Deeping Report 2.10
Neighbouring Scout Group and local residents consulted during pre-application and planning Report 2.5, 6.1
Timeline
July 2024: Public consultation held by SKDC on an initial 14-unit proposal Report 6.1
Reference S24/2110: Planning application approved for 11 dwellings, subject to S106 agreement Report 2.6, 7.1
Autumn 2025: Works intended to commence following contract award to Lindum Group Limited Report 5.1, 2.13
2026-02-10: Cabinet approved £190,000 increase to the construction contract sum
Plain English for the jargon
HRA: Housing Revenue Account, the council's ringfenced account for income and spending on council housing.
S106 Agreement: A planning obligation under Section 106 of the Town and Country Planning Act used to secure contributions from a development.
Secured by Design: A police-led security accreditation scheme for buildings, with Bronze Award as a baseline standard.
s151 Officer: The council officer with statutory responsibility for the proper administration of its financial affairs.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item105
Resolved
Decision That Cabinet approve an increase of £190,000 to the approved construction contract sum of £1.926m for the Wellington Way, Market Deeping new build housing scheme. This was due to additional works arising from recent survey findings. Other options considered Not approving the additional funding would have resulted in delays to the project and could have compromised delivery of the scheme. This option was discounted due to the ongoing housing need and the importance of maintaining the certainty of the programme. Reasons for the decision Approval of the additional funding enabled the Wellington Way scheme to proceed without delay, ensuring delivery of high-quality, sustainable council housing whilst protecting the Council’s investment. Following the initial contract award, site investigations were undertaken which looked at ground conditions. Previously unknown areas of ground with historic contamination were discovered; this could not have reasonably been identified at the tender stage. The works would be funded from HRA capital receipts.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
This report sets out the proposals for a new build social housing development of 11 units at Wellington Way, Market Deeping and recommends that the construction contract be awarded to Lindum Group Limited.
Recommendations
That Cabinet:
1. Approve the outcome of the tender process and appoint Lindum Group Limited as the preferred contractor for the construction of the housing development at Wellington Way, Market Deeping.
2. Delegates to the Deputy Chief Executive and Section 151 Officer, in consultation with the Cabinet Member for Housing, to enter a contract with Lindum Group Limited to build 11 units at a cost of £1,926,000. Decision Information
Is this a Key Decision? Yes Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Housing
Which wards are impacted? Market & West Deeping;
1. Implications
Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:
Finance and Procurement
1.1The delivery of this scheme is a key element of the new build programme for the Housing Revenue Account (HRA). The budget for this development of £2m was included in the 2025-2026 capital programme and is funded from the HRA Capital Receipts Reserve. The delivery of 11 units will provide a rental income stream to the HRA and will be built in the HRA financial business plan.
Completed by: Richard Wyles, Deputy Chief Executive and s151 Officer
Procurement
1.2The necessary processes have been followed in accordance with the Council’s Contract Procedure Rules.
Completed by: Helen Baldwin, Procurement Lead
Legal and Governance
1.3There are no further significant legal, or governance implications not already highlighted within the body of the report. Contract Procedure Rules state that an award of this value must be made by Cabinet.
Completed by: Alison Hall-Wright, Director – Housing & Projects Risk and Mitigation
1.4A project risk register will be created in partnership between the contractor and the Council, which will be subject to robust review as the project progresses. As part of the process there will be a mutual agreement of the identified risks and enable confirmation of ownership to be confirmed by the contractor of the Council. 1.5 The contractor will be responsible for insuring the building works until the properties are handed over to the Council.
Completed by: Tracey Elliott, Governance and Risk Officer
Health and Safety
1.6Lindum Group Ltd have a contract in place to provide inspections, support and guidance to ensure compliance across all sites (and office) locations. All documentation will be made available to the Council and joint meetings and visits will be arranged to ensure that there is a collaborative approach to health and safety. 1.7 On completion of the works there will be a full handover of all compliance information, technical data and relevant safety information to ensure that safe management of the asset can be implemented and required works embedded into existing programs of compliance inspections and surveys
Completed by: Phil Swinton, Head of Health, Safety, Compliance and Emergency Planning
Climate Change
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.