Sewage treatment works in Moulsford

Noted Executive 3 papers

Cabinet noted this item on Thursday 15 June 2017. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

(a) To begin a procurement process to identify a suitable supplier for a new replacement sewage treatment works at Moulsford; (b) Subject to the winning tender being within capital allocation, to delegate the award of the contract to supply and install a new sewage treatment works to the head of HR, IT and technical services in consultation with the cabinet member for technical services. Decision to award to be recorded and fully documented using ‘record of officer decision’ documentation; (c) To note that the transfer of budget for the project from the provisional to the approved capital programme will be undertaken using an individual cabinet member decision once actual costs are known; and (d) To request officers to draft a letter, to be signed jointly by the council leader and the leader of the opposition, expressing the council’s concern and disappointment that there is no mechanism to require water companies to adopt community sewage treatment works and requesting that this situation is reviewed.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Cabinet Report

Report of Head of HR, IT and Technical Services Author: Ben Coleman Telephone: 01235 422158 Textphone: 1800 01235 422158 E-mail: [email protected] Wards affected: Cholsey Cabinet member responsible: Tony Harbour Tel: [phone removed] E-mail: [email protected] To: CABINET Date: Thursday 15 June 2017

Replacement of Moulsford sewage treatment works Recommendations (a) To begin a procurement process to identify a suitable supplier for a new replacement sewage treatment works (STW) at Moulsford.

(b) Subject to the winning tender being within capital allocation, to delegate the award of the contract to supply and install a new STW to the head of service in consultation with the cabinet member. Decision to award to be recorded and fully documented using ‘record of officer decision’ documentation.

(c) To note that the transfer of budget from the provisional to the approved capital programme for the project will be undertaken using an individual cabinet member decision once actual costs are known.

Purpose of Report 1. To set out the case for procuring a new STW for Moulsford and to obtain authorisation to begin a procurement process to supply and install a new works and to delegate authority (subject to financial limits) to award the contract to the Head of Service in consultation with the cabinet member.

Corporate objectives 2. This project falls under a number of corporate objectives including investing in the district’s future and services that meet residents’ needs. Page 51 Background 3. Moulsford is not on mains waste water drainage and a small council owned STW serves 57 properties in the village. Properties not connected to the works have other separate arrangements for dealing with their waste water such as septic tanks. The location of the works is shown in appendix one.

4. The current STW is composed of two connected sections, as shown on the plan in appendix one. Waste water flows from the houses through a private sewer into a three stage solids collection tank located to the rear of 42 Underhill. The waste water is then pumped up hill to two filter beds located behind 25 Underhill where the water is treated and discharged to the ground via land drains and ditches. There is no roadway to the filter bed site so vehicle access to maintain the filter beds is difficult.

5. The District Council owns and is responsible for the running and maintenance of the existing system.

6. To try to reduce future council liabilities a significant amount of officer time has been invested in negotiating with Thames Water to try to persuade them to adopt a new STW once we have upgraded the works. Unfortunately, because the site access is too narrow to accommodate Thames Water’s standard sized vacuum tankers they are not willing to do this. The council plans to empty the new system using a smaller tanker (as we do now), but Thames Water only want to use large tankers which can access any of their works.

7. The possibility of discharging the sewage to public sewers on the east side of the river Thames in South Stoke was also explored with Thames Water in 2013/14. This option would mean that a STW in Moulsford was not necessary. Unfortunately this was discounted due to the very high construction costs.

8. Officers have serious concerns about the environmental performance of the current STW which does not have a discharge consent from the Environment Agency. The works urgently need to be replaced.

9. The council has allocated £300,000 in the provisional capital programme to pay for a replacement STW at Moulsford. This amount is considered sufficient to replace the works with the proposed system.

10. The council obtained planning permission for a new package works on 10 March 2016, reference P15/S4368/FUL. The proposed location and layout of the new system is shown in appendix two. The design is similar to that shown in appendix three.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
existing works: indicative location planAppendix one 354 KB Download
PDF
and three: new works location and design plansAppendix two 557 KB Download
PDF
Sewage treatment works in MoulsfordReport 141 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 18 attended
JC
John CottonChairman, present
FB
Felix BloomfieldCommittee Member, present
EG
Elizabeth GillespieCommittee Member, present
TH
Tony HarbourCommittee Member, present
LL
Lynn LloydCommittee Member, present
JM
Jane MurphyCommittee Member, present
DN
David Nimmo-SmithCommittee Member, present
RS
Robert SimisterCommittee Member, present
SC
Steve CullifordOfficer, present
WJ
William JacobsOfficer, present
AL
Alice LynchOfficer, present
MR
Margaret ReedOfficer, present

All 18 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Sewage treatment works in MoulsfordThis decision
  2. Replacement of sewage treatment works in MoulsfordApproved

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. Noted Open
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies