Cabinet, Thursday 17 September 2026 at 6.00pm

Budget monitoring April 2026 - June 2026

Noted Executive 4 papers

AI summarySouth Oxfordshire District Council Cabinet noted the quarter one 2026/27 budget monitoring report, which shows a forecast net revenue underspend of £184,000 against a service overspend of £714,000 offset by higher investment income.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new decision, recommendation was to note contents
MoneyNet forecast underspend £184,000Service overspend £714,000, investment income £899,000 above budget
What happens nextContinued budget monitoring through the yearOfficers actively managing budgets, no further Cabinet action
Who it affectsAll wards in South OxfordshireCouncil-wide revenue and capital budgets

What was decided

Cabinet noted the contents of the budget monitoring report covering April to June 2026. Report P4

No further decisions were taken; the report was for information and review of forecast revenue and capital positions. Report P4, P102, P106

Why

The report sets out directors' forecasts of revenue and capital spend at the end of month three, so councillors can see how the budget is tracking against agreed corporate objectives. Report P7, P8, P9

A service level overspend of £714,000 is more than offset by £899,000 of extra investment income, producing a net underspend of £184,000. Report P16, P107

What happens next

Officers will continue to monitor revenue and capital budgets and review profiling of capital projects throughout the year. Report P48, P106

The housing team will work with partner agencies to reduce the forecast £1.1 million disabled facilities grant underspend, with the Department for Health and Social Care reviewing DFG underspends nationally. Report P61

The money

  • £25.087 million Net revenue budget for 2026/27 agreed by Council on 12 February 2026 Report P11
  • £25.228 million Working revenue budget after additional grant income Report P11
  • £714,000 Forecast full year service level revenue overspend Report P16, P107
  • £720,000 Forecast overspend on employee costs Report P18
  • £250,000 Contingency held for the vacancy factor Report P25
  • £899,000 Forecast investment income above budget Report P16, P107
  • £184,000 Net forecast revenue underspend at year end Report P16, P107
  • £28.252 million Approved capital programme 2026/27 Report P42
  • £22.347 million Provisional capital programme including Cabinet growth proposals Report P43
  • £43.632 million Approved capital programme at end of June 2026 Report P44, P50
  • £3.638 million Capital spend to end of June 2026, 8% of approved programme Report P44, P50
  • £1.1 million Predicted disabled facilities grant underspend against budget Report P61
  • £6.205 million Annual investment income budget Report P69, P72
  • £7.2 million Forecast full year investment interest against £6.2 million budget Report P73
  • 4.56 per cent Average return on internally managed treasury deposits in the quarter Report P78

Options considered

  • Chosen: Note the budget monitoring report. Recommendation from the Director of Finance for review of quarter one position Report P4

Implications

  • Financial: Forecast net revenue underspend of £184,000 at year end, with service overspends on employee costs and external audit fees partly offset by higher investment income. Report P16, P18, P34, P107
  • Financial: Capital programme shows £3.638 million spent (8%) against £43.632 million approved, with £40.0 million variance as many projects are profiled across the year. Report P44, P50
  • Financial: Treasury investments remain within prudential indicators and Treasury Management Strategy, with no borrowing during the quarter. Report P96, P97, P99
  • Legal: No direct legal implications identified for this report. Report P103
  • Equalities: No equality impact assessment required; report is information only and outside the scope of the assessment tool. Report P105
  • Climate: No direct climate or ecological implications; the Climate Impact Assessment Tool was not required for this report. Report P104
  • Risk: No risk implications; budgets are being actively managed by officers. Report P106

Who and where

  • All wards in South Oxfordshire (council-wide budget) Report P3
  • Corporate Management Team, Communities, Corporate Services, Development and Corporate Landlord, Finance, Housing and Environment, Legal and Democratic, Planning, Policy and Programmes services Report P15
  • Residents receiving disabled facilities grant adaptations Report P61
  • Treasury management counterparties and the council's investment portfolio holders Report P68, P80

Timeline

  • 12 February 2026: Council agreed net revenue budget of £25.087 million and capital programme for 2026/27 Report P11, P41
  • End of June 2026: Quarter one revenue and capital position reported, with £3.638 million capital spent and £1.869 million investment income earned Report P44, P50, P69
  • 17 September 2026: Next Monetary Policy Committee meeting on UK Bank Base Rate Report P63

Plain English for the jargon

  • Revenue budget: Day to day spending on council services such as staff and running costs
  • Capital programme: Spending on larger projects and asset purchases that last more than one year
  • Carry forwards: Unspent budget moved from one financial year to the next
  • s106: Section 106 legal agreements requiring developers to contribute to local infrastructure
  • Prudential Code: Framework setting limits on council borrowing and investment to manage risk
  • SONIA: Sterling Overnight Index Average, a benchmark interest rate used to compare treasury returns
  • CIL: Community Infrastructure Levy, a charge on new development to fund local infrastructure
  • DFG: Disabled Facilities Grant, funding to help adapt homes for disabled residents
  • TMS: Treasury Management Strategy, the council's approved plan for borrowing and investing
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item300

Resolved

that Cabinet noted the contents of the report.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Agenda Item 7

Cabinet Report

Report of Director of Finance Author: Anna Winship Telephone: [phone removed] E-mail: [email protected] Wards affected: All Cabinet member responsible: Pieter-Paul Barker Tel: Email: [email protected] To: CABINET Date: 8 October 2026

Budget monitoring April 2026 – June 2026 Recommendation(s) a) Cabinet is recommended to note the contents of the report

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes No No No

Signing off officer Anna Winship Nick Bennett Kim Hall Ruth Lewin- Leigh

Purpose of Report 1. To report the revenue and capital expenditure forecast for June 2026 as forecasted by directors.

Corporate Objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the council. The budget monitoring report shows how these resources have been allocated during the first three months of the financial year.

Background 3. This report reviews the council’s revenue and capital expenditure performance to the end of month three (June). Year-end outturn forecasts were worked on during July and are based on directors’ best knowledge at that time.

1 Page 12 Agenda Item 7

Revenue budget monitoring 4. On 12 February 2026, Council agreed a net revenue budget for 2026/27 of £25.087 million. This has subsequently increased to £25.228 million to reflect additional grant income being received. The carry forwards from 2025/26 have not yet been approved and are therefore not included in the working budget.

5. Table 1 below shows, summarised at service level, the current forecast position at year end.

Table 1: Breakdown of forecast variance as at June 2026

Working Forecast Variance Employee Other budget full spend for costs Service year year

£000 £000 £000 £000 £000 Corporate Management Team 1,278 1,126 (153) (45) (108) Communities 2,601 2,664 63 (37) 100 Corporate Services 3,916 4,069 153 151 2 Development & Corporate Landlord 921 1,250 329 296 33 Finance 870 1,101 231 134 97 Housing & Environment 8,218 8,269 51 51 0 Legal & Democratic 1,546 1,659 113 173 (60) Planning 973 1,175 202 52 150 Policy & Programmes 4,856 4,631 (225) (305) 80 Contingency 50 0 (50) 250 (300) Service Expenditure 25,228 25,943 714 720 (6) Investment Income (6,296) (7,195) (899) 0 (899) Capital Financing 320 320 0 0 0 Net Expenditure 19,252 19,068 (184) 720 (905)

6. The projected full year overspend at service level is forecast to be £714,000, and treasury income to be achieved in year is anticipated to be above budget by £899,000 leading to an overall net underspend of £184,000 at year end.

Employee costs

7. The full year position being reported as at the end of June 2026 for employee costs are forecasting to be overspent by £720,000. Key employee cost variances are as follows:

• Corporate services are forecasting an overspend due to additional resources in HR to support the work need for local government reorganisation.

• Development and corporate landlord are projecting an overspend which relates to additional surveyors who are working on some of our major projects, such as property purchases.

• Finance is forecasting an overspend due to additional resources required to cover long term absence and an increase in workload.

• The projected overspend in Legal services is due to the use of more expensive locum staff covering additional workload.

2 Page 13 Agenda Item 7

• Policy and Programmes is projecting an underspend as a result of vacancies in the planning policy team.

8. The Council continues to hold a contingency of £250,000 for its vacancy factor, this was reduced to this level for the current year budget. This budget contributes to the net overspend on employee costs.

Service department variances

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 320 KB Download
PDF
Appendix AAppendix A 320 KB Download
PDF
Budget monitoring April 2026: June 2026Report 380 KB DownloadRead as text
PDF
Budget monitoring April 2026: June 2026Report 380 KB Download

At this meeting

Whole meeting

Who was there

16 of 32 attended
JJ
Jeni JacksonCouncil Staff, expected
JO
Julian OsgathorpeCouncil Staff, in attendance
MF
Maggie Filipova-RiversChair, present
TW
Tony WorganVice-Chair, present
PB
Pieter-Paul BarkerCommittee Member, present
SC
Sue CooperCommittee Member, present
MG
Mike GilesCommittee Member, apologies
GH
Georgina HeritageCommittee Member, present, as expected, virtual
BH
Ben HigginsCommittee Member, present
LR
Leigh RawlinsCommittee Member, present
AS
Anne-Marie SimpsonCommittee Member, present
NB
Nick BennettCouncil Staff, in attendance

All 32 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Budget monitoring April 2026 - June 2026This decision
  2. Budget monitoring April 2025 - December 2025Noted
  3. Budget monitoring April 2025 – September 2025Noted
  4. Budget monitoring April 2025 - June 2025Noted
  5. Q3 Budget Monitoring reportNoted
  6. Q2 budget monitoring reportNoted

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open
2 Jul 2026 Business Rates - Local Discretionary Pub 'top up' Relief scheme for 2026/2027RESOLVED : That Cabinet: a) Approve the introduction of a local discretionary pub ‘top up’ relief scheme, providing a... Approved Open