Resolved
RESOLVED : to approve the corporate delivery plan, as set out in the report of the head of HR, IT and technical services.
Cabinet approved this item on Thursday 3 August 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : to approve the corporate delivery plan, as set out in the report of the head of HR, IT and technical services.
Agenda Item 7
Cabinet Report
Report of Head of HR, IT and Technical Services Author: Debbie Adams Telephone: 01235 422142 Textphone: 18001 01235 422142 E-mail: [email protected] Wards affected: All Cabinet member responsible: John Cotton Tel: 01865 408105 E-mail: [email protected] To: CABINET Date: 3 August 2017
Corporate delivery plan Recommendation To approve the corporate delivery plan.
Purpose of Report 1. To seek Cabinet’s approval of the council’s corporate delivery plan attached, taking into account any views from Scrutiny Committee (meeting on 25 July 2017).
Corporate Objectives 2. The Corporate Plan sets out the Council’s corporate objectives and priorities for the period 2016 – 2020. The corporate delivery plan sets out in greater detail what actions the council will take to deliver these. We are committed to providing reports on performance against the corporate plan to Cabinet and Scrutiny Committee on a six- monthly basis. To enable us to do that Cabinet is recommended to agree the plan attached as the basis for those reports.
Background 3. The Council agreed its new Corporate Plan in 2016.
4. Since then officers, with relevant Cabinet members have been working on detailed planning and implementation of the plan. The corporate delivery plan sets out key actions under each corporate priority which provide a link between the high-level plan, team and individual work plans.
Page 11 Agenda Item 7
5. The corporate delivery plan is attached as appendix 1. It includes timescales for delivery and head of service or strategic management board member responsible for each of the actions.
6. The plan once agreed will form the basis of six-monthly progress reports to Scrutiny Committee and Cabinet. The plan will be a rolling one and the actions within it will be reviewed annually, with any actions not completed in year being rolled forward.
7. The first progress report is scheduled for November 2017.
Options 8. None
Financial Implications 9. There are no financial implications arising from monitoring and reporting on the corporate delivery plan. Delivery plan actions occurring in the 2017/18 financial year are budgeted for. Delivery plan actions scheduled for future years will be dependent on budget being approved.
Legal Implications 10. None for this paper however any legal implications associated with the individual actions will be dealt with at the appropriate time.
Risks 11. Should Cabinet decide not to approve the corporate delivery plan there is a risk that it will not be in place for the progress reporting to both Cabinet and Scrutiny Committee due in November 2017. As we are already a significant way through the lifetime of the plan this could lead to reputation damage or missed opportunities to manage performance against our priorities effectively.
Other implications 12. None
Conclusion 13. To fulfil obligations to report progress on the Corporate Plan twice a year, it is necessary to have an approved mechanism to facilitate this. The attached corporate delivery plan provides the link between the high level plan and team work plans.
14. The actions detailed in the attached corporate delivery plan have been agreed with individual heads of service and represent actions they intend to take to achieve the council’s objectives as set out on the Corporate Plan 2016 – 2020.
Background Papers None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 214 KB | Download |
PDF |
Corporate delivery planReport | 125 KB | DownloadRead as text |
Follow Cabinet at South Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. | Noted | Open |
| 17 Sep 2026 | Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. | Approved | Open |
| 17 Sep 2026 | Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... | Approved | Open |
| 17 Sep 2026 | Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... | Decided | Open |
| 2 Jul 2026 | Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.