RESOLVED : to (a) approve that the project becomes the phased but comprehensive enhancement and expansion of Berinsfield; (b) support the concept of Garden Village status and pursue this if it is demonstrated that this could enhance the ability to deliver the project; (c) define the council’s desired roles and responsibilities through initial joint progression with the main landowners, to set in motion collaborative working agreements, clarifying roles and responsibilities, with Oxfordshire County Council, the Mount Farm landowner and Soha Housing, and to explore the potential advantages and disadvantages of upfront investment from Homes England, all with a view to bringing a formal proposal to Cabinet later in 2019; (d) approve the principle of retaining some element of control over the Berinsfield project, while ensuring that the council does not take on too much responsibility and associated risk; (e) authorise the head of development and regeneration, in consultation with the Cabinet member for development and regeneration, ... view the full minutes text for item 72.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Head of Development & Regeneration Reporting Officer: Jayne Bolton Author: Charlotte Cottingham Telephone: 01235 422474 Textphone: 18001 01235 422474 E-mail: [email protected] Wards affected: Berinsfield Cabinet member responsible: Paul Harrison Tel: 0118 972 2665 E-mail: [email protected] To: CABINET Date: 31 January 2019
Berinsfield strategic review of progress to date and proposed way forward Recommendations That Cabinet agrees:
a) that the project becomes the phased but comprehensive enhancement and expansion of Berinsfield;
b) to support the concept of Garden Village status and that the council pursues this if it is demonstrated that this could enhance the ability to deliver the project;
c) to define the council’s desired roles and responsibilities through initial joint progression with the main landowners, to set in motion collaborative working agreements, clarifying roles and responsibilities, with Oxfordshire County Council, the Mount Farm landowner and Soha Housing and to explore the potential advantages and disadvantages of upfront investment from Homes England, all with a view to bringing a formal proposal to Cabinet later in 2019;
d) to the principle of retaining some element of control over the Berinsfield project while ensuring that the council does not take on too much responsibility and associated risk;
e) to delegate decisions on the procurement of any required professional and consultancy advice on the Berinsfield project to the Head of Development and Regeneration in consultation with the cabinet member for Development and Page 179 Agenda Item 13
Regeneration and in accordance with the council’s financial rules;
f) to undertake a review of the position in relation to land ownership in Berinsfield.
Purpose of Report 1. To update Cabinet on progress with the comprehensive regeneration of Berinsfield and to seek approval for the way forward as set out in the confidential appendix one, a strategic report prepared for the council by Cushman & Wakefield.
2. To provide options for the level of control that the council may wish to retain in the Berinsfield project.
3. To set out the background and seek approval in principle for initial work to be carried out and a formal proposal to be brought to Cabinet in 2019, including actions for strengthened partnership working and clarification of roles and responsibilities.
4. To seek delegation, to the Head of Development and Regeneration in consultation with the Cabinet Member and in accordance with council’s financial rules, decisions on the procurement of consultancy advice for the Berinsfield project.
5. To update cabinet members on the Berinsfield Community Services grants programme.
Corporate Objectives 6. The Berinsfield project aims to meet the following corporate objectives: Invest in the district’s future Homes and jobs for everyone Build thriving communities Services that reflect resident’s needs.
Background 7. Since the creation of the new management structure the council’s senior management team has collectively agreed the need for more transparency for key projects as they evolve. Following the creation of the Development and Regeneration service it is considered by the head of service that this is an appropriate juncture to review the approach to this project.
8. In September 2018, Cushman and Wakefield, the council’s strategic property advisors, were instructed to undertake a strategic review of the Berinsfield project to objectively consider the work progressed to date, current position and to recommend a proposed way forward. This report is attached in appendix 1. The key recommendation of the Cushman and Wakefield review was the need to confirm the project’s scale and content and the council’s desired roles and responsibilities. They recommended that the initial key aspects for the council to move the project forward should be:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.