RESOLVED ; to grant planning permission for application P18/S2434/FUL subject to the following conditions: 1. Commencement of development within three years of date of planning permission. 2. Development to be implemented as per approved plans. 3. Landscape Management Plan to be submitted to and approved by the Local Planning Authority prior to commencement of development. 4. Details of Landscaping of the site (including footpath access and any hardstanding) to be submitted to and approved by the Local Planning Authority prior to commencement of the development. 5. Details of surface water drainage to be submitted to and approved by the Local Planning Authority prior to commencement of the development. 6. Development must be accessed via the proposed pedestrian footpath provided from Shiplake College. 7. The existing riverside pitches (edged in blue) to be restored to previous state prior to the first use of the new pitches. 8. A construction traffic management plan should be submitted to and approved by the Local Planning Authority prior to commencement of the development. 9. A phased risk assessment shall be carried out in order to identify any potential contaminative uses, details of which shall be submitted to and approved by the Local Planning Authority prior to commencement of the development. 10. Tree Protection details to be submitted to and approved by the Local Planning Authority prior to commencement of the development. 11. No lighting shall be installed to serve the new pitches. 12. Removal of permitted development rights for the erection of any additional structures or new buildings.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
P18/S2434/FUL Agenda Item 8 South Oxfordshire District Council – Committee Report – 6 November 2019
Appendix 1 – Consultation responses in full
Shiplake Parish Council - Object The parish recognises the need and desire for the College to improve the rugby fields but object to the change of use as the fields in question are productive, irrigated farm land and removal of such a large acreage would seriously impact on the future viability of Shiplake Farm. The future viability of Shiplake College would not be seriously impacted by locating the rugby pitches on other land Landscape value of the open fields, reflecting the rural character of the village would be lost Approval would encourage other applications for developments on agricultural land Impact on local wildlife needs to be considered strongly as in recent months, since gravel extraction has begun closer to Shiplake the wildlife are seeking refuge in the environmentally safer fields
CPRE Oxfordshire - Fully support the arguments put forward by the current farmer of this site The fragmentation of the agricultural land as a result of this development will seriously affect the efficiency of the arable farming operation of Thames Farm Whilst the land is grade 3 agricultural value, the site can be irrigated and yield good harvests and the site is particularly important for the farm in times of summer drought By replacing the old drainage system on the existing pitches would more efficiently address the waterlogging problems Most flooding in this country occurs in the early months of the year and not in the autumn, when the College states the new pitches would be needed for rugby. In the event of extreme weather events, flooding should not be a problem in the autumn and if there were flooding in the autumn it would be likely that even the new pitches would be so wet as to be unusable. It would therefore seem a sensible step for the College to investigate a new drainage system before taking over nearly 10 hectares of good farmland and introducing non-agricultural features into this sensitive landscape Countryside Officer – The site is contiguous with Warren Wood Local Wildlife Site to the south-east. It is not anticipated that the change of use to playing fields will have an adverse impact on this area. The proposed ground works to the site to create level playing fields are supposed to be outside of the RPA of any trees. It is noted that the erection of 1.2metre high fencing along the southern boundary is permitted development and does not require planning permission. Due to intensive management to support monocultures, arable fields have a generally low ecological value. No lighting is proposed, the copse of trees in the centre of the site is being retained. It is recommended that a landscaping condition is applied to any permission granted, to secure the proposed planting shown on plan which would deliver a small biodiversity gain to the site. Drainage Officer - The site lies within flood zone 1 and therefore, we have no comments to make
12 Page 23 South Oxfordshire District Council – Committee Report – 6 November 2019
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED : to approve the minutes of the meeting held on 30 August 2026 as a correct record and agree that the Chair ...
Minutes of the previous meetingRESOLVED : to approve the minutes of the meeting held on 15 July 2026 as a correct record and agree that the Chair si...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.