Didcot Northern Perimeter Road - Phase 3 (NPR3)

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 23 June 2022. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED to: (a) authorise the section 151 officer, or in their absence, the chief executive, to agree funding agreement terms which are equal to, or greater than, those imposed by the existing grant conditions to which the council is subject, for the transfer of funds to Oxfordshire County Council to support the delivery of the Didcot Northern Perimeter Road Phase 3 (NPR3); and (b) agree the addition of Didcot Northern Perimeter Road Phase 3 (NPR3) (fully funded by government grant funding) to the approved capital programme, in order to facilitate the transfer of funds to Oxfordshire County Council.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Agenda Item 8

Cabinet Report

Report of Head of Policy and Programmes Author: Jayne Bolton Telephone: 01235 422624 E-mail: [email protected] Wards affected: All wards within the Didcot Garden Town and “Area of Influence” boundaries: Cholsey, Didcot North East, Didcot South, Didcot West, Sandford and the Wittenhams wards in South Oxfordshire district. Cabinet member responsible: Cllr Robin Bennett E-mail: [email protected] To: CABINET Date: 23 June 2022

Didcot Northern Perimeter Road Phase 3 (NPR3) funding transfer Recommendations (a) Contingent on the approval of the amended Didcot Garden Town Delivery Plan, to delegate authority to the Section 151 officer, or in their absence, the Chief Executive, to agree funding agreement terms which are equal to, or greater than, those imposed by the existing grant conditions to which the council is subject, for the transfer of funds to Oxfordshire County Council (OCC) to support the delivery of NPR3.

(b) Contingent on the approval of the amended Didcot Garden Town Delivery Plan, to agree the addition of NPR3 (fully funded by government grant funding) to the approved capital programme, in order to facilitate the transfer of funds to OCC.

Purpose of Report 1. To seek the required delegated authority, to enable the transfer of funds which are currently being held by South Oxfordshire District Council, to the appropriate body (Oxfordshire County Council) as the highways authority responsible for delivery of the scheme.

Page 25 Agenda Item 8

Corporate Objectives 2. Agreeing the transfer of these funds will enable the progress and ultimate completion of the NPR3 scheme, thereby supporting multiple themes in the corporate plan such as:

a. Economic and Community Wellbeing - ECW3 – “plan for communities connected by walking and cycling networks with sustainable, accessible and affordable public transport and reliable broadband, learning the lessons from, the Covid-19 pandemic and enabling more home-working”

b. Homes and Infrastructure that meets local need – HILN1 – “Didcot Garden Town priority projects as identified by the advisory board, specifically a sustainable plan to redevelop the Didcot Gateway site, a public transport and active walking and cycling network, community facilities and accessible green spaces for Didcot residents”

Background 3. The NPR3 scheme will extend the existing A4130 Didcot Northern Perimeter Road (NPR), linking the A4130, Abingdon Road and B4016 junction to the A4130 and Hadden Hill junction.

4. The Department of Communities and Local Government (now Department of Levelling Up, Housing and Communities) provided capital funding of £6.2m in 2016/17 to South Oxfordshire District Council under Section 31 of the Local Government Act 2003 to “fund infrastructure works to support the delivery of Didcot Garden Town. Specifically, the grant is intended, though no conditions are attached to it, to meet the projected shortfall in funding for the build of phase three of the Northern Perimeter Road at Didcot”.

5. The funds are currently being held by South Oxfordshire District Council, we are now seeking to agree terms to transfer the identified funds (£6.2m) to OCC as the appropriate body charged with delivery of the scheme.

6. OCC estimates the timetable for delivery of the scheme to commence in Autumn 2022 with a planning application, followed by construction in Spring 2025 and completion in Summer 2026.

Considerations 7. The £6.2m being transferred is fully funded by way of an external grant which was given for the purpose of meeting the NPR3 projected shortfall. Therefore, consideration in this area is limited to the scope of that transfer.

8. To delegate authority to the Chief Executive and/or Section 151 Officer to agree terms which are equal to, or greater than, those imposed by the granting body, for the transfer of the funds to OCC thereby enabling the delivery of the Didcot Northern Perimeter Road (Phase 3).

Page 26 Agenda Item 8

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Didcot Northern Perimeter Road: Phase 3 (NPR3)Report 249 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 23 attended
DR
David RouaneChair, present
MF
Maggie Filipova-RiversVice-Chair, present
PB
Pieter-Paul BarkerCommittee Member, present
RB
Robin BennettCommittee Member, present
SC
Sue CooperCommittee Member, present
AP
Andrea PowellCommittee Member, apologies
LR
Leigh RawlinsCommittee Member, present
AS
Anne-Marie SimpsonCommittee Member, apologies
SC
Steve CullifordOfficer, present
PA
Patrick ArranOfficer, in attendance
HB
Harry Barrington-MountfordOfficer, in attendance
JB
Jake BassettOfficer, in attendance

All 23 on the meeting page

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. Noted Open
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies