to 1. adopt the Community Infrastructure Levy Charging Schedule (as set out at Appendix 1 to the head of policy and programmes’ report to Cabinet on 10 November 2022) and the Community Infrastructure Levy Instalments Policy (as set out at Appendix 2 to the same report), with implementation anticipated in early January 2023; and 2. authorise the head of policy and programmes, in consultation with the Cabinet member for planning, to make any necessary further minor changes to the documents or a change to the implementation date for the new Community Infrastructure Levy rates.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Interim Head of Policy and Programmes Author: Vicky Aston/Cathie Scotting Telephone: 01245 422600 Email: [email protected][email protected] Wards affected: All Cabinet member responsible: Anne-Marie Simpson Tel: [phone removed] E-mail: [email protected] To: CABINET Date: 10 November 2022
Community Infrastructure Levy (CIL) Charging Schedule - Adoption Recommendations To recommend Council to:
(a) Adopt the Community Infrastructure Levy (CIL) Charging Schedule (at Appendix 1) and the CIL Instalments Policy (at Appendix 2), with implementation anticipated in early January 2023.
(b) Delegate to the Interim Head of Policy and Programmes, in consultation with the Cabinet Member for Planning, any necessary further minor changes to the documents or a change to the implementation date for the new CIL rates.
Purpose of Report 1. To consider the Examiner’s report and recommendations (Appendix 3), following the independent Examination of the Community Infrastructure Levy (CIL) Charging Schedule, including the Examiner’s required modification to the Schedule.
2. To consider the CIL Charging Schedule (as amended) and the accompanying Instalment Policy for adoption by Council on 8 December 2022.
Corporate Objectives 3. Securing developer contributions through CIL and Section 106 Agreements will contribute towards achieving the corporate objective of ‘Homes and Infrastructure that Page 12 Agenda Item 7
meet local needs’ as set out under Theme 5 of the South Oxfordshire Corporate Plan 2020 to 2024.
Background 4. Funding for the infrastructure necessary to support new development across the district can be sought in a variety of ways. The council currently utilises the following main mechanisms for securing infrastructure contributions from developers:
Community Infrastructure Levy (CIL) Section 106 planning obligations (S106)
5. Our current CIL Charging Schedule and Developer Contributions SPD came into effect on 1 April 2016. The council subsequently adopted the South Oxfordshire Local Plan 2035 in December 2020, which included new site allocations and additional infrastructure requirements. There have also been changes to the Community Infrastructure Levy Regulations1, including:
the removal of pooling restrictions for S106 obligations (i.e. the now cancelled requirement that no more than five S106 obligations can fund a single infrastructure project); removing the need for a Regulation 123 list (i.e. a list of infrastructure projects to be funded by CIL as opposed to S106); and introducing a new requirement to produce an annual Infrastructure Funding Statement.
6. Furthermore, it is evident that the current CIL rates are not generating sufficient funds to help deliver the necessary infrastructure to support planned development. In particular, funding for education is falling short and it is now proposed, in the main, to secure education through S106.
7. In light of all the above, the council considered it was necessary to conduct a review of both the CIL Charging Schedule and Developer Contributions SPD. The CIL review has been carried out in accordance with the CIL Regulations 2010 (as amended) and a draft version of the Charging Schedule, together with associated viability evidence, was approved by Cabinet for public consultation on 3 February 2022. The review of the Developer Contributions SPD has been completed and is the subject of a separate report, which Cabinet will consider for adoption on 10 November.
Consultation and Independent Examination of the Draft Charging Schedule
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
South and Vale Local Development Schemea) To approve the revised Local Development Scheme, June 2026. b) To delegate the making of minor updates to the Join...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.