Community Infrastructure Levy Funding for the Earth Trust Gateway to Nature Project
ApprovedCommittee4 papers
AI summarySouth Oxfordshire District Council allocated up to £500,000 of Community Infrastructure Levy funding to the Earth Trust for the junction, access road and car park elements of Phase 2a of its Gateway to Nature project.
What happens nextFunding agreement to followDelegated to head of finance and legal
Who it affectsEarth Trust and visitorsWittenham Clumps and Little Wittenham area
What was decided
Council allocated up to £500,000 of Community Infrastructure Levy funding to its approved capital programme for the junction, access road and car park elements of Phase 2a of the Earth Trust Gateway to Nature project. Report P5
Council authorised the head of finance, in consultation with the head of legal and democratic, to agree and enter into a funding agreement with the Earth Trust and to approve release of the funding subject to that agreement. Report P7, P8
The agreement must cover terms of use, instalments, timing, conditions, legal and financial due diligence, and compliance with subsidy control provisions. Report P7, P56
Why
The project supports the council's strategic priorities on climate change and nature recovery, homes and infrastructure that meet local needs, and thriving, healthy and inclusive communities. Report P15, P16
The Earth Trust manages the largest open-access green space in South Oxfordshire, including the Wittenham Clumps, with 200,000 visitors a year, and new housing nearby is expected to increase demand for access and parking. Report P23
Without CIL funding the trust said it would have to mortgage further property assets, putting the charity's financial sustainability at higher long-term risk and risking services and facilities provided to residents. Report P51, P99
What happens next
The head of finance, in consultation with the head of legal and democratic, will agree and enter into a third-party funding agreement with the Earth Trust covering terms, instalments and conditions. Report P7, P55
Funding will be released in staged payments linked to interim certificates for the junction, access road and car park works; no funds will be released if terms cannot be agreed. Report P55, P94
Officers will determine whether the award amounts to a subsidy under the four-limb test under the Subsidy Control Act 2022 before any funds are released. Report P56
The money
£500,000 CIL allocation to phase 2a junction, access road and car park Report P5, P46
£14,453 2025 capital grant for cycle parking and E-bike charging in phase 2a Report P32
£1,045,000 Total cost of the junction, access road and car park elements Report P67, P68
£2,000,000 Total cost of phase 2a centre development Report P63, P64
£1,000,000 Total cost of phase 2b adventure play-scape Report P65
£2,002,089.00 Forecast retained CIL balance 2026/27 before this allocation Report P59
£1,502,089.00 Forecast retained CIL balance 2026/27 after this allocation Report P61
£0.00 Forecast retained CIL balance 2027/28 after this allocation Report P61
Options considered
Chosen: Full £500,000 allocation to phase 2a as requested. Enables the critical junction, access road and car park elements to progress and avoids the trust having to mortgage further property assets Report P46, P51
Rejected: Part allocation of £400,000 to phase 2a. The trust could accommodate a reduced CIL allocation but Cabinet and Council chose to support the full request Report P47, P63, P64
Rejected: No CIL allocation, direct Earth Trust to apply to CIL grant scheme. Not recommended; Cabinet and Council instead chose to approve funding outside the grant scheme Report P48, P50
Implications
Financial: The retained CIL balance is forecast to be fully allocated by the end of 2027/28, limiting the council's ability to support other infrastructure projects or cost overruns in that period. Report P60, P61, P93
Legal: Officers will run a four-limb subsidy control test before release, and a third-party funding agreement is required; funding will not be released if terms cannot be agreed. Report P55, P56
Risk: There is a risk that other organisations may seek similar support from retained CIL, but the council is unlikely to be able to agree future similar requests in the short to medium term. Report P98
Risk: If not supported, the trust would face higher long-term financial risk and reduced service availability for residents, with knock-on effects on the open-access green space. Report P99
Equalities: The project includes disabled parking and toilets, way-marked routes, an education programme for special educational needs visitors, and targeted engagement to widen access. Report P82, P86, P89, P90
Climate: The scheme connects to the Ladygrove Greenway active travel route from Didcot, provides cycle parking and E-bike charging, and includes new hedgerows and sustainable drainage; visitor carbon impact will be measured and offset where possible. Report P75, P77, P78, P79
Other: The site sits within the Didcot Garden Town area of influence, and the Didcot Garden Town team supports the allocation to help manage increased footfall from new development. Report P101
Who and where
The Earth Trust, a registered charity (number 1095057) Report P24, P56
Visitors to the Earth Trust site and Wittenham Clumps, including around 200,000 visitors and 6,500 education visits per year Report P23
Residents of Little Wittenham, Didcot, Wallingford, Benson, Cholsey, Crowmarsh and Brightwell-Cum-Sotwell Report P22, P23
Other CIL-eligible infrastructure projects that may not receive funding as a result of this allocation Report P93
Future applicants for similar CIL support from the council's retained allocation Report P98
Timeline
April 2016: Council started charging CIL Report P17
July 2020: Planning permission P20/S1290/FUL secured Report P25
2019, updated April 2021: CIL spending strategy introduced and updated Report P17
30 January 2026 to 30 March 2026: CIL grant scheme open for applications of between £75,000 and £250,000 Report P50
5 February 2026: Cabinet meeting considered and recommended the funding Report P2
2026: Earth Trust plans to deliver phases 2a and 2b Report P26
12 February 2026: Council meeting approved the CIL allocation
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge on new development to fund local infrastructure
Phase 2a: Visitor hub, 0.6km access track, 80 new car parking spaces, landscaping, and walking and cycle routes
Phase 2b: Adventure play-scape
Section 106: Planning obligations secured from developers for specific local infrastructure
Subsidy control: Rules under the Subsidy Control Act 2022 governing public funding that may affect competition or trade
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68
Resolved
RESOLVED : to 1. allocate up to £500,000 of Community Infrastructure Levy (CIL) funding to the council’s approved capital programme for use towards the junction, access road and car park elements of Phase 2a of the Earth Trust Gateway to Nature project as set out in this report; 2. authorise the head of finance, in consultation with the head of legal and democratic, to: i. Agree and enter into a funding agreement with the Earth Trust regarding the terms of use of the CIL funding; the instalments in which the funding is paid; the timing of instalments; the conditions subject to which instalments are paid and to otherwise protect the interests of South Oxfordshire District Council as the provider of the funding by undertaking legal and financial due diligence including being satisfied that the funding is lawful and compliant with subsidy control provisions. ii. Approve the release of the funding to the Earth Trust subject to and in accordance with the funding agreement.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Cabinet Report Report of Head of Finance Author: Mark Hewer Telephone: 01235 422472 E-mail: [email protected] Wards affected: Cholsey and Sandford and the Wittenhams Cabinet member responsible: Councillor Pieter-Paul Barker – Cabinet member for finance and property assets E-mail: [email protected] To: CABINET Date: 5 February 2026
Community Infrastructure Levy Funding for the Earth Trust Gateway to Nature Project
Recommendation(s) For Cabinet to determine whether to recommend to Council:
(a) For an allocation of up to £500,000 of Community Infrastructure Levy (CIL) funding to be added to the council’s approved capital programme for use towards the junction, access road and car park elements of Phase 2a of the Earth Trust Gateway to Nature project as set out in this report.
(b) Should the funding allocation be approved, to delegate to the Head of Finance, in consultation with the Head of Legal, to:
i. Agree and enter into a funding agreement with the Earth Trust regarding the terms of use of the CIL funding; the instalments in which the funding is paid; the timing of instalments; the conditions subject to which instalments are paid and to otherwise protect the interests of South Oxfordshire District Council as the provider of the funding by undertaking legal and financial due diligence including being satisfied that the funding is lawful and compliant with subsidy control provisions.
ii. Approve the release of the funding to the Earth Trust subject to and in accordance with the funding agreement.
Page 114 Agenda Item 10
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report)
Signing off Simon Nick Bennett Dominic Lorne Grove officer Hewings Lamb
Purpose of report 1. To update Cabinet on the Earth Trust Gateway to Nature Project and request for funding support towards the delivery of the junction, access road and car park elements of phase 2a of the scheme through an allocation of up to £500,000 from the council’s CIL funds.
2. To invite Cabinet to determine if it recommends to Council to approve the CIL allocation to be added to the council’s approved capital programme and delegations to officers to act on the release of funds as set out in the recommendations section of this report.
3. To highlight the options, risks and implications both for and against supporting the funding request.
Strategic Priorities 4. The council’s strategic priorities are set out in the Council Plan 2025-29. The project, as demonstrated on pages 9 to 11 of the proposal (appendix one) would support the following priorities:
• Action on climate change and nature recovery: Leading in building climate resilient communities, reducing carbon emissions and restoring our natural environment. • Homes and infrastructure that meet local needs: Meeting local housing needs through sustainable development that is supported by appropriate infrastructure, protects green spaces, and mitigates the effects of climate change. • Thriving, healthy, and inclusive communities: Nurturing healthy, safe, and resilient communities in our rural and urban areas while being responsive to the impact of national changes on local need. Championing local businesses, local food production and a thriving, sustainable local economy and fostering community cohesion and inclusion.
Background 5. South Oxfordshire District Council started charging CIL in April 2016 which was followed by the introduction of a spending strategy in 2019. The strategy was subsequently updated in April 2021. The spending strategy acknowledges a 5 per cent allocation of CIL revenues to cover the administrative costs of CIL incurred by the council. A 15 or 25 per cent allocation, depending on neighbourhood plan status, is paid to the town and parish councils that have experienced CIL liable development in
Page 115 Agenda Item 10
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
South and Vale Local Development Schemea) To approve the revised Local Development Scheme, June 2026. b) To delegate the making of minor updates to the Join...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.