Resolved
That Cabinet approves the award of the contract for a new transfer station facility to handle the council’s dry mixed recycling (DMR) to the preferred bidder. The contract would run for a minimum of five years, starting in June 2026.
Cabinet approved this item on Thursday 28 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet approves the award of the contract for a new transfer station facility to handle the council’s dry mixed recycling (DMR) to the preferred bidder. The contract would run for a minimum of five years, starting in June 2026.
Agenda Item 13
Cabinet Report
Report of Head of Housing and Environment Author: William Maxwell Telephone: [phone removed]
E-mail: [email protected]
Wards affected: All South Cabinet member responsible: Cllr. James-Lawrie Tel: [phone removed] E-mail: [email protected] To: South Oxfordshire Cabinet Meeting Dates: 28 November 2024
Waste Transfer Station Contract Award Recommendation(s) (a) That Cabinet approves the award of the contract for a new transfer station facility to handle the council’s dry mixed recycling (DMR) to the preferred bidder. The contract would run for a minimum of five years, starting in June 2026.
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes Yes No
Signing off Emma Creed Nicholas Kim Hall Lorne Grove officer Bennett
Page 502 Agenda Item 13
Purpose of report 1. The purpose of this report is to seek approval to award a contract for the provision of a waste transfer station to the preferred bidder, as shown in confidential Appendix 1.
Corporate objectives 2.
South:
• Action on climate emergency
• Protect and restore our natural world
Background 3. The councils as waste collection authorities (WCA) operate a shared household waste collection service. This is currently subject to a contractual arrangement with Biffa which runs until the end of June 2026, who provide a vehicle depot and transfer station (a facility for bulking) at Culham. This site is earmarked for redevelopment and access to a new vehicle depot and transfer facility will therefore be required from June 2026. The provision of the two facilities has been split for operational and commercial reasons.
4. The current waste transfer facilities are only used for Dry Mixed Recyclate (DMR) which is the co-mingled recyclable waste stream collected from households. The non- recyclable (residual), garden waste and food waste all have existing in-district transfer points which are managed by Oxfordshire County Council as the waste disposal authority (WDA) and aren’t therefore included in this contract or as part of this report.
5. The transfer facility makes up a key piece of infrastructure required for the effective operation of waste collection services to residents. The transfer facility will handle DMR as it is transferred from the Rear Compaction Vehicles (RCVs), bulked up and then loaded onto Heavy Goods Vehicles (HGVs) to be transported to a Material Recovery Facility (MRF) for reprocessing. Without it, each collection vehicle would be required to deliver the collected DMR directly to a MRF. However, because there are no operating MRFs within Oxfordshire, this would make the service undeliverable due to the distances involved and increase in cost, time and carbon to the service.
6. The cabinet papers, dated: 3 February 2022 (South), delegated authority to the Deputy Chief Executive – Place to explore options to secure a waste depot and other necessary associated infrastructure. An ICMD in May 2024 outlined the reasons why a procurement should be undertaken rather than the councils develop their own transfer station and secured approval to go out to procurement for the provision of access to a transfer element and associated contract. South
7. The Waste Resources and Street Cleansing Strategy, the waste vehicle depot used to operate from in 2026, the contract for future household waste collection and street cleansing services, and the reprocessing of dry mixed recycling, are all separate pieces of work and therefore not included as part of this report, but together with the DMR transfer facility make up the key components of the future household waste and street cleansing services.
Page 503 Agenda Item 13
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Waste Transfer Station Contract AwardReport | 217 KB | DownloadRead as text |
Follow Cabinet at South Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. | Noted | Open |
| 17 Sep 2026 | Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. | Approved | Open |
| 17 Sep 2026 | Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... | Approved | Open |
| 17 Sep 2026 | Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... | Decided | Open |
| 2 Jul 2026 | Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.