Operational Net Zero Annual Progress Report

Noted Executive 1 paper

AI summarySouth Oxfordshire Cabinet notes progress on cutting its own carbon emissions, but warns that local government reorganisation limits further action before the 2030 target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the progress made on operational carbon emissions
MoneyNot stated
What happens nextTargets may move to mayorClimate targets may pass to a Mayoral Strategic Authority
Who it affectsCouncil operationsBuildings, waste fleet, leisure, land and vehicles

What was decided

Cabinet noted the progress made in reducing the council's operational carbon emissions.

The report sets out the council's current path to its 2030 operational net zero target and the risks to it, without committing new resources. Report P11, P13

The council confirmed it cannot commit to spending on carbon offsetting after 2028 because of local government reorganisation. Report P13

Why

The council must track progress against its operational net zero target for 2030. Report P3

Six significant risks are identified, including reorganisation delays, lack of funding, rising baseline emissions, grid capacity issues, lack of suitable electric waste vehicles, and rising carbon credit costs. Report P2, P3, P4, P5, P6, P7, P8, P9

Progress continues where funding is already secured, for example decarbonisation of some council buildings, but wider action is constrained by reorganisation and fleet electrification issues. Report P11

What happens next

The Climate and Ecological Emergencies Advisory Committee has recommended good practice principles to guide any future offsetting decisions. Report P14

The council is leading a joint project with the Local Nature Partnership, funded by Innovate UK, to develop a local market for nature based carbon credits. Report P15

Under the devolution white paper, setting climate targets may become a matter for the Mayoral Strategic Authority rather than the current council. Report P12

The money

  • £60,000 to £450,000 Range of illustrative electric vehicle costs, with an average of £260,000 Report P20
  • 34 percent Share of council land being managed for nature in 2025 Report P16

Implications

  • Risk: Six significant risks are listed against the 2030 target, covering reorganisation, funding, baseline emissions, grid capacity, electric vehicle supply and carbon credit costs. Report P2, P3, P4, P5, P6, P7, P8, P9
  • Legal: Climate targets may transfer to the Mayoral Strategic Authority under the devolution white paper. Report P12
  • Financial: The council cannot commit to spending on offsetting beyond 2028, and any future authority would have to agree its own budget for it. Report P13
  • Climate: Outside already funded projects, there are limited opportunities to increase the pace of decarbonisation work to meet the 2030 target. Report P11
  • Equalities: An Equality Impact Assessment has been completed and no implications were identified. Report P1

Who and where

  • The future unitary authority that will inherit climate and budget decisions after reorganisation Report P13, P26
  • The council's waste, grounds maintenance, buildings and leisure operations Report P20, P26, P27
  • The Local Nature Partnership, through a joint Innovate UK funded project on local carbon credit markets Report P15

Timeline

  • Sept 2024: A 12 tonne electric food truck became operational Report P21
  • 2025: 34 percent of council land is being managed for nature Report P16
  • Nov 2025: A small 3.5 tonne electric cage tipper is due to be operational Report P21
  • June 2026: The new waste depot is planned to be operational Report P20
  • 2026/27: Scenario 2 models replacing a further diesel panel van and an additional public conveniences vehicle with electric alternatives Report P26, P28
  • to 2027/28: Up to eight more electric vehicles are projected to be bought, bringing the total to ten, subject to budget and Cabinet approval Report P23
  • after 2028: The council cannot commit to spending on offsetting, pending local government reorganisation Report P13
  • 2030: Operational net zero target date Report P3
  • 2034/35: Scenario 5 assumes 100 per cent of vehicles transition to low carbon, aligning with the next procurement cycle Report P26

Plain English for the jargon

  • LGR: Local Government Reorganisation, the restructuring of councils in the area
  • PSDS: Public Sector Decarbonisation Scheme, a government funding programme
  • eRCV: Electric Refuse Collection Vehicle
  • TCO2e: Tonnes of carbon dioxide equivalent, a standard unit for emissions
  • Scope three emissions: Indirect emissions arising from a council's wider value chain, not from its own operations or purchased energy
  • NCAP: Net Zero Carbon Action Plan, focused here on 1 to 2 year actions
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item187

Resolved

RESOLVED : That Cabinet note the progress made in reducing the council’s operational carbon emissions.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Agenda Item 8

Cabinet Report

Report of Head of Policy and Programmes Author: Dominic Lamb E-mail: [email protected] Wards affected: All

South Cabinet member responsible: Sam James-Lawrie Tel: Cllr Sam James-Lawrie E-mail: [email protected]

To: CABINET Date: 16 October 2025

Operational Net Zero Annual Progress Report Recommendation That Cabinet notes the progress made in reducing the council’s operational carbon emissions. These have reduced by 14 per cent since the council’s Climate Action Plan baseline year of 2019/20 and by 49 per cent since Greenhouse Gas reporting commenced in 2009/10.

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) No No Yes No

Signing off Nicole Vivien Heather Lorne Grove officer Tyreman Williams Saunders

Page 4 Agenda Item 8

Purpose of report 1. This report reviews the council’s progress towards the 2030 target for achieving net zero carbon in its own operations.

2. This paper addresses the shifting context of the local government reorganisation (LGR) announced in HM Government’s white paper in 2024, and the implications for achieving the council’s targets. In line with the anticipated reorganisation timelines, it is important to maintain a positive outlook on the work that can be achieved to continue to reduce the council’s emissions over the next two years.

3. This paper includes five scenarios designed to present a review of the council’s trajectory to net zero, showing where we are currently in terms of emissions, and giving a realistic assessment of where we will be in 2030. The first four scenarios represent the position of the council at the current time, as is reflected in current capital and revenue budgets. Only the fifth scenario has been projected beyond 2028 to 2034/35, as this demonstrates the likely impact of a full transition to an electric vehicle (EV) waste fleet to coincide with the projected timing of the next cycle of vehicle procurement. Any future council will be looking at replacing the end-of-life fleet, and assumptions have been made regarding securing the necessary finance and sufficient advances in vehicle technology.

Strategic priorities 4. South Oxfordshire’s Council Plan 2025-29 outlines five key priorities for the future. One of these key priorities is supporting Climate and Nature Recovery.

5. This report meets our commitment in the joint Nature and Climate Action Plan (NCAP) 2025-29 to produce annual reports outlining progress towards the council’s operational net zero target and the predicted emissions pathway to 2030 (NCAP action ONZ1).

Background 6. South Oxfordshire declared a Climate Emergency in 2019 and therefore the baseline year used in this report is 2019/20.

7. This is the second operational net zero annual report, with the first paper in July 2024 initiating a review of the council’s climate targets. Cabinet subsequently adopted a revised target to be a carbon neutral council by 2030. This target is in line with other councils across Oxfordshire.

8. The first net zero report was designed to test the earliest possible date that the council could reach net zero in its own operations. This report however presents a more realistic appraisal of the council’s current position, with the emphasis on committed projects and consideration given to emerging factors such as local government reorganisation, government funding for decarbonisation and other issues influencing the decarbonisation of our waste fleet.

Page 5 Agenda Item 8

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Operational Net Zero Annual Progress ReportReport 718 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
NB
Nick BennettCouncil Staff, expected
IC
Ian ChisnellCouncil Staff, expected
BB
Becky BinsteadSecretary, expected
PB
Phil BarkerCouncil Staff, expected
DR
David RouaneChair, present
MF
Maggie Filipova-RiversVice-Chair, present
PB
Pieter-Paul BarkerCommittee Member, apologies
GH
Georgina HeritageCommittee Member, present
SJ
Sam James-LawrieCommittee Member, apologies
LR
Leigh RawlinsCommittee Member, present
AS
Anne-Marie SimpsonCommittee Member, present
TW
Tony WorganCommittee Member, present

All 13 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Operational Net Zero Annual Progress ReportThis decision
  2. Operational Net Zero TargetApproved

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. Noted Open
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open