AI summarySouth Oxfordshire Council approves £2.3m increase to Haseley depot budget, taking total to £15.9m for new waste vehicle depot, shared equally with Vale of White Horse.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedCapital envelope rises by £2.3m to £15.9m
Money£2.3m increase, total £15.9mCouncil's 50% share is £7.95m
What happens nextAward design and build contractSubject to Council approval, to preferred bidder
Who it affectsAll wards in South OxfordshireStatutory waste collection service users
What was decided
Council approved increasing the capital budget envelope by £2.3m to a total of £15.9m, with 50% being this council's share of the waste vehicle depot delivery and operational costs. Report P7
Cabinet was asked to recommend to Council that, subject to the increased budget, the JCT Design and Build contract be awarded to the preferred bidder for the Haseley depot. Report P8, P41
Cabinet was also asked to delegate to senior officers authority to directly award a contract to the District Network Operator for an upgraded electricity connection, and to secure a contingency temporary depot if needed. Report P9, P10
Why
A new depot is needed because the current leased Culham Number One site, operated by Biffa, is due for redevelopment as an allocated strategic site in the South Oxfordshire Local Plan 2035. Report P24, P25
Of five design and build bids received, only one was compliant; the compliant bid (circa £7.5m) exceeds the original £5.507m construction budget but includes previously excluded DNO network upgrade, biodiversity net gain and retained building costs. Report P30, P36, P41
Additional unexpected costs since December 2024 cover enabling and asbestos works, increased stamp duty, VAT, operational, planning, and Section 278 works, alongside the higher design and build contract value. Report P54
What happens next
Ongoing construction programme targets handover between 13 July 2026 and 24 July 2026, with enabling and asbestos works due for completion in November 2025. Report P49, P50, P51, P52
Officers will secure a contingency temporary depot site and continue exploring options if the new depot is not ready for occupation at contract start date. Report P10, P53, P88
Officers will monitor development costs and may use existing contingency budget to part fund the £2.3m increase, reporting back to Council and Cabinet as required. Report P67, P68, P69
The money
£2.3m Increase to capital budget envelope Report P7
£15.9m New total capital budget envelope across both councils Report P7, P68
£13.7m Existing capital budget envelope approved in December 2024 Report P23, P54
£7.95m Council's 50% share of total project budget Report P86
£1.15m Indicative increase per council Report P68
circa £3.75m Council's share of design and build contract cost Report P41
£5.507m Original construction budget Report P30
circa £7.5m Compliant bidder price Report P36
£5,500,000 Capital cost of site purchase (unchanged) Report P58
£7,605,000 Original estimate to make site operational Report P59
9,832,555 Updated cost projection to make site operational Report P59
200,000 Original BNG estimate (off-site) Report P60
4,500 Updated BNG figure with on-site works included elsewhere Report P60
13,652,000 Original total capital outlay Report P66
15,889,055 Updated total capital outlay projection Report P66
Options considered
Chosen: Award JCT Design and Build contract to preferred bidder (only compliant bid, scored 92/100, top rank). Only compliant bid; high quality score, including full marks on carbon reduction and energy Report P30, P34, P39, P40, P41
Chosen: Directly award a separate contract to the District Network Operator for upgraded electricity connection. Flexibility for phasing and exact cost confirmation once DNO quote received Report P9, P42
Chosen: Secure temporary depot site as contingency if new depot not ready at contract start. Ensure continued provision of statutory waste service if delivery delayed Report P10, P53
Rejected: Non-compliant bidders (Suppliers 2 to 5). Did not attend mandatory site visit or did not satisfy financial assessment Report P30, P33
Implications
Financial: Total project cost now estimated at £15,889,055 across both councils; South's 50% share rises to about £7.95m, an increase of roughly £1.15m. Report P66, P86, P68
Legal: A draft JCT Design and Build contract has been prepared and was issued with the tender; approval enables the council to better discharge its statutory waste collection duties. Section 106 or 278 agreements may be required before a planning Decision Notice is issued. Report P20, P21, P29, P70, P71
Equalities: Equality Impact Screening identified no implications associated with the recommendations. Report P77
Climate: A Climate Impact Assessment was completed in November 2024; the preferred bidder scored full marks on carbon reduction and energy experience. Report P72, P76
Risk: The new waste vehicle depot project is the most significant risk on the council's corporate risk register, mainly around failing to deliver in time for waste operation requirements and potential planning delays. Report P80, P81
Who and where
Residents across South Oxfordshire receiving waste collection services Report P3, P24, P25
Vale of White Horse District Council (joint delivery partner) Report P10, P24, P41
Biffa (current depot operator at Culham Number One) Report P24
Haseley Trading Estate site locality and parish councils Report P82
District Network Operator (electricity connection upgrade) Report P9, P42
Concertus (appointed professional team lead) Report P27, P44
Preferred design and build contractor Report P8, P30, P41
Timeline
November 2024: Cabinet briefed on depot delivery; Council in December 2024 approved site purchase and capital budget envelope of £13.7m. Report P23
9 June 2025: Planning application P25/S1653/FUL registered. Report P27
8 October 2025: Target date for Planning Committee decision on depot application. Report P28, P47
9 October 2025: Cabinet considered the report and recommended the budget increase to Council. Report P4, P6
23 October 2025: Council meeting to decide on capital budget increase. Report P4
Early November 2025: Target completion of contractor procurement. Report P49
November 2025: Target completion of enabling and asbestos works. Report P50
1 December 2025: Construction start targeted. Report P51
13 to 24 July 2026: Handover window targeted. Report P52
Summer 2026: Targeted completion of new waste vehicle depot delivery. Report P88
Plain English for the jargon
JCT Design and Build: A standard form of construction contract published by the Joint Contracts Tribunal, under which a contractor designs and builds the project.
DNO: District Network Operator, the electricity distribution company responsible for the local power network.
BNG: Biodiversity Net Gain, a planning requirement for development to deliver measurable improvements to biodiversity.
RIBA Plan of Work: The Royal Institute of British Architects' framework setting out stages of building design from conception to handover.
SDLT: Stamp Duty Land Tax, a tax paid on property purchases in the UK.
Section 106 / 278 Agreements: Legal agreements under the Town and Country Planning Act used to secure planning obligations or highway works from developers.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33
Resolved
RESOLVED : to proceed with increasing the capital budget envelope by £2.3m to provide a total budget of £15.9m, with 50 per cent of this total budget being the council’s share of the costs associated with delivering the waste vehicle depot and making it operational within the required timeframes.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Head of Development and Corporate Landlord Report Lead: Andrew Busby Report Author: Aileen Sparling, Place and Strategic Asset Management Team Leader E-mail: [email protected] Wards affected: All
Cabinet member responsible: Cllr Pieter-Paul Barker (Cabinet member for finance and property assets) E-mail: [email protected] To: CABINET Dates: 9 October 2025 To: COUNCIL Dates: 23 October 2025
Haseley Trading Estate
Recommendation(s) That Cabinet:
(a) recommends to Council to proceed with increasing the capital budget envelope by £2.3m to provide a total budget of £15.9m, with 50 per cent of this total budget being the council’s share of the costs associated with delivering the waste vehicle depot and making it operational within the required timeframes
(b) subject to Council approval of the increased budget envelope, award the JCT Design and Build contract to the preferred bidder to deliver the vehicle depot on the Haseley Trading Estate
(c) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, to approve terms and conditions to directly award a contract to the District Network Operator (DNO) for an upgraded electricity connection
(d) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, authority to secure a temporary vehicle depot site, as a contingency plan, and enter into the necessary leases and any ancillary agreements which will bind the council (jointly with Vale) for an agreed period, to be funded from contingency if required.
Page 52 Agenda Item 9
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes Yes Yes
Signing off Anna Winship Nick Bennett Heather Lorne Grove officer Saunders
Purpose of report 1. This report updates Cabinet on the latest position with respect to the delivery of a waste vehicle depot at the Haseley Trading Estate site, and seeks approval by the relevant bodies to:
• increase the budget envelope based on the latest assessment of costs
• award the JCT Design and Build contract
• delegate the approval of terms and conditions to enter into a direct contract with the DNO, and
• to secure a contingency plan, in the event that the new depot is not ready for occupation at contract start date to ensure continued provision of the statutory waste service.
Strategic priorities 2. The provision of a new waste vehicle depot will assist in the delivery of the Future Waste Services programme, meeting the following strategic priorities:
• Financial stability and innovative transformation
• Action on climate change and nature recovery, and
• Homes and infrastructure that meet local needs.
Background 3. Members were most recently briefed on work to deliver a new waste vehicle depot at Cabinet in November 2024 and Council in December 2024, where they approved the purchase of the Haseley Trading Estate as the preferred location for the waste vehicle depot. At the same time, members also approved the allocation of a capital budget envelope for site purchase costs, and the transfer of additional funds from the provisional to approved capital programme to continue delivery of the project.
4. Delivery of the depot at the Haseley Trading Estate is required to meet the council’s statutory responsibilities in respect of waste collection. At present, South Oxfordshire and Vale of White Horse District Councils do not own or operate a waste vehicle depot in either district, with the current depot at the Culham Number One site being leased and operated by Biffa. The Culham Number One site is due for redevelopment as an allocated strategic site in the South Oxfordshire Local Plan Page 53 Agenda Item 9
2035, and as such, there is a continued and urgent need to deliver a new vehicle depot to meet the council’s ongoing statutory responsibilities for waste collection.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
South and Vale Local Development Schemea) To approve the revised Local Development Scheme, June 2026. b) To delegate the making of minor updates to the Join...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.