Approved Executive 1 paper

AI summaryCabinet recommends to Council a £2.3m rise in the waste vehicle depot budget at Haseley Trading Estate, taking the total to £15.9m shared with Vale of White Horse, and (subject to that) to award the design and build contract to the only compliant bidder.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£2.3m increase, total £15.9m
What happens nextCouncil decision on 23 October 2025Full Council to consider the increased capital budget envelope
Who it affectsWaste collection service, all wardsNew depot needed to meet statutory waste duties for both councils

What was decided

Cabinet recommends to Council an increase of £2.3m to the capital budget envelope, giving a total of £15.9m with 50 per cent as this council's share of the waste vehicle depot project. Report P7, P68, P86

Subject to that Council approval, Cabinet awards the JCT Design and Build contract to the preferred bidder to deliver the vehicle depot on Haseley Trading Estate. Report P8, P41

Cabinet delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, authority to approve a direct contract with the District Network Operator for an upgraded electricity connection and to secure a temporary vehicle depot site as a contingency, including any leases and ancillary agreements binding the council jointly with Vale. Report P9, P10, P42, P53

Why

The current Culham Number One depot is leased from Biffa and the site is allocated for redevelopment in the South Oxfordshire Local Plan 2035, creating an urgent need for a new waste vehicle depot to meet statutory waste collection duties. Report P24, P25, P28

Of five bids, only one was compliant; that bidder scored highly on quality, social value and carbon reduction, but its bid of circa £7.5m exceeds the original construction budget of £5.507m. Report P30, P36, P40, P41

Since the December 2024 approvals, extra costs have arisen from enabling and asbestos works, higher stamp duty, planning and Section 278 works, the DNO network upgrade allowance and a higher design and build contract value. Report P54

What happens next

Council to consider the increased budget envelope on 23 October 2025, after the planning decision at Planning Committee on 8 October 2025. Report P4, P28, P47

If approved, complete contractor procurement by early November 2025 and finalise the JCT Design and Build contract with the preferred bidder. Report P49, P70

Construction is planned from 1 December 2025 to 24 July 2026, with handover between 13 and 24 July 2026; officers will continue to explore a contingency site if needed. Report P51, P52, P53, P88

The money

  • £2.3m Requested increase to the total available capital budget for both councils (about £1.15m per council) Report P68
  • £15.9m Total capital budget envelope sought across both councils, of which 50 per cent (about £7.95m) is this council's share Report P7, P68, P86
  • £13.7m Current capital budget envelope as approved by Councils in December 2024 Report P54
  • £13,652,000 Previous total capital outlay projection from November 2024 Report P66
  • £15,889,055 Updated total capital outlay projection Report P66
  • £5,500,000 Capital cost of site purchase (unchanged) Report P58, P59
  • £7,605,000 Previous outlay required to make the site operational Report P59
  • £9,832,555 Updated outlay required to make the site operational Report P59
  • £150,000 New estimate for planning conditions Report P64
  • £347,000 Previous SDLT and agents fees Report P65
  • £402,000 Updated SDLT and agents fees Report P65
  • £200,000 BNG estimate (off-site mitigations, with on-site works included above) Report P60
  • £5.507m Original construction budget, exceeded by the preferred bidder Report P30
  • circa £7.5m Price of the preferred bidder's bid Report P36
  • circa £3.75m Approximate financial commitment per council for the design and build contract Report P41

Options considered

  • Chosen: Award the JCT Design and Build contract to the preferred bidder (Supplier 1). Only compliant bidder of five; highest quality score with full marks on carbon reduction and energy; financial commitment split equally between the two councils Report P30, P34, P35, P40, P41, P85
  • Rejected: Award the contract to one of the other four bidders. None were compliant: four did not attend the mandatory site visit or did not satisfy the financial assessment Report P30
  • Chosen: Directly award a contract to the District Network Operator for the upgraded electricity connection. May be the better, more appropriate and efficient route; allows flexibility on phasing and exact costs Report P42, P87
  • Chosen: Secure a temporary vehicle depot site as a contingency if the new depot is not ready at contract start. Needed to ensure continued provision of the statutory waste service if delivery slips; to be funded from contingency if required Report P18, P53

Implications

  • Financial: Capital budget envelope to rise by £2.3m to £15.9m, with this council's 50 per cent share at about £7.95m; some of the increase may be part funded from each council's existing contingency budget. Report P7, P68, P86
  • Legal: Approval will help the council discharge its statutory duties as a waste collection authority; legal team have prepared a draft JCT Design and Build contract published with the tender documents. Report P70, P71
  • Climate: A Climate Impact Assessment has been completed and the preferred bidder scored full marks on carbon reduction and energy efficiency; an Equality Impact Screening found no equalities implications. Report P72, P76, P77
  • Risk: The new waste vehicle depot project is the most significant risk on the council's corporate risk register, mainly the risk of failing to deliver in time to meet waste operation requirements; contingency options are being explored. Report P80, P81

Who and where

  • South Oxfordshire and Vale of White Horse residents receiving waste collection services Report P24, P41
  • The Future Waste Services programme and statutory waste collection Report P19, P24
  • Communities near Haseley Trading Estate, engaged via meetings and Parish Council updates Report P26, P82
  • All wards in South Oxfordshire Report P3

Timeline

  • November 2024: Cabinet briefed on the project Report P23
  • December 2024: Council approved purchase of Haseley Trading Estate and the capital budget envelope Report P23
  • 9 June 2025: Planning application P25/S1653/FUL registered Report P27
  • 8 September 2025: Original target date for planning decision Report P28
  • 8 October 2025: Planning Committee decision now likely (subject to a verbal update to Cabinet) Report P28, P47
  • 9 October 2025: Cabinet decision Report P4
  • 23 October 2025: Council decision on the increased capital budget envelope Report P4
  • Early November 2025: Completion of contractor procurement (subject to approvals) Report P49
  • November 2025: Completion of enabling and asbestos works Report P50
  • 1 December 2025: Construction start Report P51
  • 13 July 2026 to 24 July 2026: Handover of the new depot Report P52
  • 24 July 2026: Planned end of construction Report P51
  • Summer 2026: Target delivery of the new waste vehicle depot Report P88

Plain English for the jargon

  • District Network Operator (DNO): The electricity distribution network operator responsible for upgrading the on-site substation to meet depot power needs as the fleet moves towards electrification.
  • JCT Design and Build: A standard form of construction contract published by the Joint Contracts Tribunal, used to appoint a contractor to design and construct the depot.
  • BNG (Biodiversity Net Gain): A requirement for development to leave biodiversity in a better state than before, here covered partly by off-site mitigations with on-site works included elsewhere in the cost plan.
  • Section 106 and Section 278 Agreements: Legal agreements under planning and highways law used to secure planning obligations such as off-site highway works.
  • RIBA Plan of Work Stages 3 and 4: Stages in the Royal Institute of British Architects' framework covering developed design and technical design, used here for the depot design process.
  • SDLT: Stamp Duty Land Tax, payable on the site purchase and the reason for the higher SDLT line in the updated cost projection.
  • Future Waste Services programme: The councils' programme for delivering new waste services, supported by the new depot.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item176

Resolved

RESOLVED : that Cabinet: b) subject to Council approval of the increased budget envelope, award the JCT Design and Build contract to the preferred bidder to deliver the vehicle depot on the Haseley Trading Estate c) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, to approve terms and conditions to directly award a contract to the District Network Operator (DNO) for an upgraded electricity connection d) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, authority to secure a temporary vehicle depot site, as a contingency plan, and enter into the necessary leases and any ancillary agreements which will bind the council (jointly with Vale) for an agreed period, to be funded from contingency if required.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Agenda Item 11

Cabinet Report

Report of Head of Development and Corporate Landlord Report Lead: Andrew Busby Report Author: Aileen Sparling, Place and Strategic Asset Management Team Leader E-mail: [email protected] Wards affected: All

Cabinet member responsible: Cllr Pieter-Paul Barker (Cabinet member for finance and property assets) E-mail: [email protected] To: CABINET Dates: 9 October 2025 To: COUNCIL Dates: 23 October 2025

Haseley Trading Estate

Recommendation(s) That Cabinet:

(a) recommends to Council to proceed with increasing the capital budget envelope by £2.3m to provide a total budget of £15.9m, with 50 per cent of this total budget being the council’s share of the costs associated with delivering the waste vehicle depot and making it operational within the required timeframes

(b) subject to Council approval of the increased budget envelope, award the JCT Design and Build contract to the preferred bidder to deliver the vehicle depot on the Haseley Trading Estate

(c) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, to approve terms and conditions to directly award a contract to the District Network Operator (DNO) for an upgraded electricity connection

(d) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, authority to secure a temporary vehicle depot site, as a contingency plan, and enter into the necessary leases and any ancillary agreements which will bind the council (jointly with Vale) for an agreed period, to be funded from contingency if required.

Page 367 Agenda Item 11

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes Yes Yes

Signing off Anna Winship Nick Bennett Heather Lorne Grove officer Saunders

Purpose of report 1. This report updates Cabinet on the latest position with respect to the delivery of a waste vehicle depot at the Haseley Trading Estate site, and seeks approval by the relevant bodies to:

• increase the budget envelope based on the latest assessment of costs

• award the JCT Design and Build contract

• delegate the approval of terms and conditions to enter into a direct contract with the DNO, and

• to secure a contingency plan, in the event that the new depot is not ready for occupation at contract start date to ensure continued provision of the statutory waste service.

Strategic priorities 2. The provision of a new waste vehicle depot will assist in the delivery of the Future Waste Services programme, meeting the following strategic priorities:

• Financial stability and innovative transformation

• Action on climate change and nature recovery, and

• Homes and infrastructure that meet local needs.

Background 3. Members were most recently briefed on work to deliver a new waste vehicle depot at Cabinet in November 2024 and Council in December 2024, where they approved the purchase of the Haseley Trading Estate as the preferred location for the waste vehicle depot. At the same time, members also approved the allocation of a capital budget envelope for site purchase costs, and the transfer of additional funds from the provisional to approved capital programme to continue delivery of the project.

4. Delivery of the depot at the Haseley Trading Estate is required to meet the council’s statutory responsibilities in respect of waste collection. At present, South Oxfordshire and Vale of White Horse District Councils do not own or operate a waste vehicle depot in either district, with the current depot at the Culham Number One site being leased and operated by Biffa. The Culham Number One site is due for redevelopment as an allocated strategic site in the South Oxfordshire Local Plan Page 368 Agenda Item 11

2035, and as such, there is a continued and urgent need to deliver a new vehicle depot to meet the council’s ongoing statutory responsibilities for waste collection.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haseley Trading EstateReport 320 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
NB
Nick BennettCouncil Staff, expected
IC
Ian ChisnellCouncil Staff, expected
BB
Becky BinsteadSecretary, expected
PB
Phil BarkerCouncil Staff, expected
DR
David RouaneChair, present
MF
Maggie Filipova-RiversVice-Chair, present, as expected, virtual
PB
Pieter-Paul BarkerCommittee Member, present
GH
Georgina HeritageCommittee Member, present
SJ
Sam James-LawrieCommittee Member, present
LR
Leigh RawlinsCommittee Member, present
AS
Anne-Marie SimpsonCommittee Member, present
TW
Tony WorganCommittee Member, present

All 13 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Haseley Trading EstateThis decision
  2. Haseley Trading EstateDecided

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. Noted Open
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies