AI summarySouth Oxfordshire Cabinet approves the five-yearly Regulation 10A review of the Local Plan 2035 and decides the plan should be revised, with the timetable and format to be set later through an update to the Local Development Scheme.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRegulation 10A review of Local Plan 2035
MoneyNot stated
What happens nextLDS update to Full CouncilTimetable and format brought later
Who it affectsAll South Oxfordshire wardsAffects every ward in the district
What was decided
Cabinet approved the Regulation 10A review of the South Oxfordshire Local Plan 2035 and decided the Local Plan should be revised. Report P4, P62, P63
Decisions on the timetable and format of any revision are deferred to a later update of the Local Development Scheme, to be brought to Full Council via Cabinet. Report P5, P44, P47
Why
Legislation requires a five-yearly review of local plans, and the Local Plan was adopted on 10 December 2020, so a decision was due by 10 December 2025. Report P16, P17, P23
Policy STRAT2's 775 dwellings per year is only 63% of the current standard method figure of around 1,235 dwellings per year, so the housing requirement is no longer up to date. Report P33, P38, P39, P40
The Joint Local Plan with Vale of White Horse is uncertain after Inspectors wrote on 26 September 2025 recommending its withdrawal, so the Council cannot rely on the JLP as a replacement. Report P29, P30, P32
What happens next
An updated Local Development Scheme will be prepared, setting out either a revised timetable for the Joint Local Plan or alternative plan-making options. Report P43, P44, P47, P63
The updated LDS will go to Full Council (via Cabinet) for approval, as required by section 15 of the Planning and Compulsory Purchase Act 2004. Report P43, P44
If the JLP is not adopted, the Council will need to assess its housing land supply against the 1,235 dwellings a year standard method figure when determining planning applications. Report P61
Options considered
Chosen: Option 1: Approve the Regulation 10A review and decide the Local Plan should be revised, deferring format and timetable to a later LDS update. Meets the statutory five-yearly review duty, allows time for the JLP examination to resolve, and retains flexibility to respond to Government reforms Report P46, P47, P54, P63
Rejected: Option 2: Do not approve the Regulation 10A review. Would breach a statutory requirement and risk a legal challenge Report P48, P49, P53
Implications
Legal: Option 1 satisfies the five-yearly review duty in Regulation 10A; not approving it could risk a Judicial Review. Report P54, P60
Financial: No direct financial implications from the review itself; any cost of revisions would be considered through the LDS update. Report P6, P51, P52
Climate: No direct climate or ecological impact; impacts will be assessed when revisions or a replacement plan are prepared. Report P6, P55, P56
Equalities: No direct equalities implications; impacts will be assessed when revisions or a replacement plan are prepared. Report P6, P57, P58
Risk: Risk of legal challenge if the review is not completed by 10 December 2025; risk of housing land supply position changing if the JLP does not proceed. Report P23, P60, P61
Other: The Council will need to assess housing land supply against the 1,235 dwellings a year standard method figure if the JLP does not proceed to adoption. Report P61
Who and where
Residents and applicants across all wards of South Oxfordshire Report P3, P22
Developers and landowners with sites allocated or proposed in the district Report P22
Vale of White Horse District Council, as joint partner in the JLP Report P29
Oxford City Council, whose unmet housing need is addressed in Policy STRAT2 Report P33
Timeline
10 December 2020: South Oxfordshire Local Plan 2035 adopted by Full Council Report P21, P23
25 March 2021: Full Council decided to prepare a Joint Local Plan with Vale of White Horse Report P29
9 December 2024: Joint Local Plan submitted to Secretary of State for examination Report P29
3 to 5 June 2025: Initial hearing sessions for the JLP examination took place Report P29
26 September 2025: Inspectors wrote recommending the JLP be withdrawn Report P30
6 October 2025: The Councils responded to the Inspectors' letter Report P30
20 October 2025: The Councils wrote again asking the Inspectors to reconsider their conclusions Report P30
27 November 2025: Cabinet approved the Regulation 10A review and decided the Local Plan should be revised Report P3
10 December 2025: Statutory deadline for completing the five-yearly review under Regulation 10A Report P23
Plain English for the jargon
Regulation 10A: Provision of the Town and Country Planning (Local Planning) (England) Regulations 2012 requiring local plans to be reviewed at least every five years from adoption.
Local Development Scheme (LDS): A document setting out the timetable for preparing local planning documents, which must be approved by Full Council under section 15 of the Planning and Compulsory Purchase Act 2004.
Joint Local Plan (JLP): A plan being prepared jointly by South Oxfordshire and Vale of White Horse district councils to replace the South Oxfordshire Local Plan 2035.
Policy STRAT2: The strategic policy in the South Oxfordshire Local Plan 2035 that sets the district's housing requirement.
Standard Method: The national formula in the NPPF used to calculate a local authority's minimum housing need.
NPPF: The National Planning Policy Framework, the Government's planning policy guidance for England.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item212
Resolved
a) That Cabinet approve the Regulation 10A review of the South Oxfordshire Local Plan 2035 and decide that the Local Plan should be revised. b) That the timetable and format for the South Oxfordshire Local Plan 2035 revision is brought to Full Council (via Cabinet) at a later date through an update to the Local Development Scheme (LDS).
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Head of Policy and Programmes Author: Robyn Tobutt Telephone: 01235 422600 E-mail: [email protected] Wards affected: All Wards South Cabinet member responsible: Councillor Anne-Marie Simpson Tel: [phone removed] E-mail: [email protected] To: CABINET Dates: 27 November 2025
South Oxfordshire Local Plan 2035 Review Recommendation(s) (a) That Cabinet approve the Regulation 10A review of the South Oxfordshire Local Plan 2035 and decide that the Local Plan should be revised
(b) That the timetable and format for the South Oxfordshire Local Plan 2035 revision is brought to Full Council (via Cabinet) at a later date through an update to the Local Development Scheme (LDS)
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) No Yes No No
Signing off Nicole Nick Bennett Jessie Fieth Lorne Grove officer Tyreman
Page 35 Agenda Item 10
Purpose of report 1. To seek approval of the review undertaken on the South Oxfordshire Local Plan 2035, in accordance with Regulation 10A of the Town and Country Planning (Local Planning) (England) Regulations 2012 (as amended).
Strategic priorities 2. This report helps meet the Council Plan priorities by reviewing the South Oxfordshire Local Plan 2035, which contains a suite of policies, many of which are related directly to these priorities.
3. The related priorities are:
• Action on climate change and nature recovery
• Participation, accessibility, and accountability
• Homes and infrastructure that meet local needs
• Thriving, healthy, and inclusive communities
Background 4. Legislation introduced in 2018 requires that Local Plan reviews must be completed five years from the date of adoption – this ensures plans remain effective. Regulation 10A of the Town and Country (Local Planning) (England) Regulations 2012 (as amended) states that:
“10A. (1) A local planning authority must review a local development document within the following time periods – (a) in respect of a local plan, the review must be completed every five years, starting from the date of adoption of the local plan, in accordance with section 23 of the Act (adoption of local development documents).”
5. The National Planning Policy Framework (NPPF), paragraph 34 also draws attention to the regulatory requirements for five yearly reviews:
“34. Policies in local plans and spatial development strategies should be reviewed to assess whether they need updating at least once every five years, and should then be updated as necessary19. Reviews should be completed no later than five years from the adoption date of a plan, and should take into account changing circumstances affecting the area, or any relevant changes in national policy. Relevant strategic policies will need updating at least once every five years if their applicable local housing need figure has changed significantly; and they are likely to require earlier review if local housing need is expected to change significantly in the near future. 19 Reviews at least every five years are a legal requirement for all local
plans (Regulation 10A of the Town and Country Planning (Local Planning) (England) Regulations 2012).”
6. The South Oxfordshire Local Plan 2035 (Local Plan) was adopted at a meeting of Full Council on 10 December 2020. It sets out how development will be planned and delivered across South Oxfordshire to 2035, through a strategy and supporting policies Page 36 Agenda Item 10
promoting sustainable development. These policies are used to help determine planning applications across the district. The Plan identifies appropriate sites for development, including new homes, employment spaces, essential infrastructure, shops, and community facilities. It also sets out how the district’s valued historic and natural environments will be protected and enhanced.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.