AI summarySouth Oxfordshire Cabinet noted a forecast £2.216 million revenue underspend for 2025/26, driven by £3.357 million higher investment income offsetting a £1.141 million service overspend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the April-September 2025 budget monitoring report
Money£2.216 million underspendForecast net revenue underspend for 2025/26
What happens nextContinue active monitoringOfficers to keep reviewing revenue and capital budgets
Who it affectsAll wards and servicesCouncil-wide revenue and capital budgets for 2025/26

What was decided

Cabinet noted the contents of the budget monitoring report covering April to September 2025. Report P4

The forecast position is a £2.216 million net revenue underspend, made up of a £1.141 million service overspend offset by £3.357 million of investment income above budget. Report P16

Cabinet noted the capital programme position of £7.039 million spent against a £36.278 million approved budget at the end of September 2025. Report P44, P48

Why

Service overspends of £1.141 million are forecast, with employee costs alone expected to overspend by £981,000 due to low vacancy levels and use of agency staff. Report P16, P18, P26

Investment income is expected to come in £3.357 million above budget, producing a favourable net position of £2.216 million. Report P16

What happens next

Finance and project managers will continue to actively review and monitor the capital programme through the year to keep profiling accurate. Report P47

Vacant posts across services are being actively filled, with some agency cover used in the meantime. Report P21, P24

A predicted £1.9 million underspend on disabled facilities grants will be profiled into future years. Report P57

The money

  • £25.547 million Original net revenue budget for 2025/26 agreed by Council on 13 February 2025 Report P11
  • £26.230 million Revised net revenue budget after carry forward of unspent one-off project budgets from 2024/25 Report P11
  • £1.141 million Forecast service overspend for the year Report P16
  • £3.357 million Treasury investment income expected above budget Report P16
  • £2.216 million Forecast net revenue underspend Report P16
  • £981,000 Forecast employee cost overspend Report P18
  • £11.211 million Original approved capital programme for 2025/26 Report P42
  • £35.356 million Original provisional capital programme (including Cabinet growth proposals) Report P43
  • £36.278 million Approved capital programme at end of September 2025 Report P44
  • £7.039 million Capital spend to end of September 2025 Report P44, P48
  • £29.2 million Capital variance against full year budget Report P48
  • £1.9 million Predicted underspend on disabled facilities grants Report P57
  • £30,000 Expected overspend on wheeled bins, to be funded by s106 receipts Report P59

Implications

  • Financial: A net revenue underspend of £2.216 million is forecast, while the capital programme is materially underspent against profile at the half-year point. Report P16, P48
  • Financial: Employee cost pressures of £981,000 reflect low vacancy levels; the budget assumes a vacancy factor of less than three per cent. Report P18, P26
  • Legal: No direct legal implications from the report. Report P61
  • Equalities: No equality impact assessment required; the report does not change policy, practice, service delivery or resource allocation in a way that affects protected groups. Report P64
  • Climate: No direct climate or ecological impact implications; Climate Impact Assessment Tool not required. Report P63
  • Risk: No risk implications identified; report is for information only and budgets are being actively managed by officers. Report P65

Who and where

  • All wards across South Oxfordshire Report P3
  • Council staff, with vacant posts being filled and some agency cover in use Report P21, P24, P26
  • Users of Cornerstone arts centre, with refurbishment delayed and income below budget Report P33
  • Disabled facilities grant applicants, with a predicted £1.9 million underspend to be re-profiled into future years Report P57

Timeline

  • 13 February 2025: Council agreed the 2025/26 net revenue budget and capital programme Report P11, P41
  • April 2025: Start of the 2025/26 financial year covered by this report Report P10
  • End of September 2025: Month 6 position; approved capital programme stood at £36.278 million with £7.039 million spent Report P44, P48
  • October 2025: Heads of service worked on year-end outturn forecasts on which this report is based Report P10
  • 18 December 2025: Cabinet meeting at which the report was noted Report P3

Plain English for the jargon

  • Vacancy factor: Budget assumption that a percentage of staff posts will be unfilled, used to reduce forecast pay costs
  • S106 receipts: Funds paid by developers under Section 106 of the Town and Country Planning Act to mitigate development impacts
  • Salix funds: Government grant funding used to support public sector decarbonisation projects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item222

Resolved

That Cabinet note the contents of the report.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Agenda Item 9

Cabinet Report

Report of Head of Finance Author: Anna Winship Telephone: [phone removed] E-mail: [email protected] Wards affected: All Cabinet member responsible: Pieter-Paul Barker Tel: Email: [email protected] To: CABINET Date: 18 December 2025

Budget monitoring April 2025 – September 2025 Recommendation(s) a) Cabinet is recommended to note the contents of the report

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes No No No

Signing off officer

Purpose of Report 1. To report the revenue and capital expenditure forecast for September 2025 as forecasted by heads of service.

Corporate Objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the council. The budget monitoring report shows how these resources have been allocated during the first six months of the financial year.

1 Page 33 Agenda Item 9

Background 3. This report reviews the council’s revenue and capital expenditure performance to the end of month six (September). Year-end outturn forecasts were worked on during October and are based on heads of service’s best knowledge at that time.

Revenue budget monitoring 4. On 13 February 2025, Council agreed a net revenue budget for 2025/26 of £25.547 million. This has subsequently increased to £26.230 million. This reflects the carry forward of unspent one-off project budgets from 2024/25.

5. Table 1 below shows, summarised at service level, the current forecast position at year end.

Table 1: Breakdown of forecast variance as at September 2025

Working Forecast Variance Employee Other budget full spend for costs Service year year

£000 £000 £000 £000 £000 Corporate Management Team 1,294 1,260 (35) 40 (75) Communities 2,304 2,520 217 129 87 Corporate Services 3,960 4,005 45 19 25 Development & Corporate Landlord 1,263 988 (275) (95) (181) Finance 1,167 1,345 178 206 (28) Housing & Environment 8,409 8,470 61 40 21 Legal & Democratic 1,630 1,893 263 63 200 Partnerships 3,213 3,213 0 0 0 Planning 1,022 1,417 394 269 125 Policy & Programmes 2,467 2,260 (207) (192) (15) Contingency (500) 0 500 500 0 Service Expenditure 26,230 27,370 1,141 981 160 Investment Income (7,345) (10,702) (3,357) 0 (3,357) Net Expenditure 18,885 16,669 (2,216) 981 (3,197)

6. The projected service overspend is forecast to be £1.141 million, and treasury income achieved in year is anticipated to be ahead of budget by £3.357 million leading to a favourable net position to the Council of a £2.216 million underspend.

Employee costs

7. As at the end of September 2025, employee costs are forecast to be overspent by £981,000. Key employee cost variances are as follows:

2 Page 34 Agenda Item 9

• Communities is predicting an overspend in the community hub. External government funding is expected to fill this gap; however, it has not yet been confirmed.

• Development and corporate landlord is forecasting an overall underspend. This is due to vacant posts following the corporate landlord model implementation and restructure of teams. These vacant posts are all being actively filled. Some of the underspend has been offset by agency staff covering the vacancies.

• Finance is forecasting an overspend due to additional resources required to cover long term absence.

• The projected overspend in Housing and Environment is due to additional temporary resources to cover long term absence.

• Planning is forecasting an overspend because of agency staff required to cover vacancies within the teams but to also cover the additional work due to a system implementation project.

• Policy and Programmes is projecting an underspend as a result of vacancies in the planning policy team that are in the process of being filled.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget monitoring April 2025: September 2025Report 219 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 13 attended
NB
Nick BennettCouncil Staff, expected
IC
Ian ChisnellCouncil Staff, expected
BB
Becky BinsteadSecretary, expected
PB
Phil BarkerCouncil Staff, expected
MF
Maggie Filipova-RiversChair, present
PB
Pieter-Paul BarkerCommittee Member, apologies
GH
Georgina HeritageCommittee Member, expected
LR
Leigh RawlinsCommittee Member, present
AS
Anne-Marie SimpsonCommittee Member, present
TW
Tony WorganVice-Chair, present
SH
Simon HewingsOfficer, expected
SC
Sue CooperCommittee Member, present

All 13 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Budget monitoring April 2025 – September 2025This decision
  2. Budget monitoring April 2026 - June 2026Noted
  3. Budget monitoring April 2025 - December 2025Noted
  4. Budget monitoring April 2025 - June 2025Noted
  5. Q3 Budget Monitoring reportNoted
  6. Q2 budget monitoring reportNoted

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. Noted Open
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open