Development of a Joint Community Cohesion Strategy
NotedExecutive1 paper
AI summarySouth Oxfordshire Cabinet backs a five-year joint community cohesion strategy with Vale of White Horse, commissioning Belong to lead on a fully funded 2027/28 action plan totalling £707,552.
Written from the decision and the officer reportPDF Pro
OutcomeNotedStrategy and Belong commission approved in principle
Money£707,552.00 totalAcross strategy, action plan and Be Together, 2026-28
What happens nextFinal strategy to Cabinet March 2027Action plan implementation begins April 2027
Who it affectsAll South Oxfordshire residents and wardsIncludes migrant cohorts and wider community
What was decided
Cabinet approved the development of a five-year Joint Community Cohesion Strategy with Vale of White Horse, supporting the Fair Treatment for All Residents and Sanctuary and Fair Treatment for All motions. Report P6, P12
Cabinet approved commissioning Belong to develop the strategy and a 2027/28 action plan, subject to the strategy being approved. Report P8, P89
Cabinet noted that the strategy will finalise a fully funded action plan for 2027/28, linking existing grant and National Lottery funding into one plan. Report P7, P51, P53
Why
Neither council currently has an integration plan that supports a long-term approach to building resilient and cohesive communities alongside the cost-of-living pressures residents face. Report P32, P79
Following council motions in October and December 2025, SODC set aside £50,000 a year ongoing and VWHDC approved £25,000 one-off for community cohesion work. Report P81
Officers argue Belong is the only organisation funded by the National Lottery and endorsed by the LGA working with 40 local authorities on cohesion strategies, and has confirmed capacity to deliver at pace. Report P89, P94
What happens next
Exploration phase runs June to August 2026, with Belong onboarded, key partners identified and a project timeline agreed. Report P103
Engagement September to October 2026 and strategy development November to December 2026, with partner feedback in January to February 2027. Report P104, P105, P106
Final strategy goes to Scrutiny and Cabinet in March and April 2027, with the 2027/28 action plan implemented from April 2027. Report P107, P108
The money
£707,552.00 Total project cost across strategy, action plan and Be Together, 2026-28 Report P126
£125,000.00 National Lottery funding for the Community Cohesion Strategy Report P126
£62,500.00 SODC revenue funding for the strategy Report P126
£25,000.00 VWHDC discretionary growth funding for the strategy Report P126
£100,000.00 Action Plan total (SODC £50,000, VWHDC £12,500, National Lottery £37,500) Report P126
£457,552.00 Be Together programme across SODC and VWHDC Report P126
£25,000 VWHDC one-off revenue budget approved February 2026 Report P81
Options considered
Chosen: Develop a five-year Joint Community Cohesion Strategy with Belong and produce a 2027/28 action plan. Provides a shared definition of cohesion linking economic, infrastructural and social factors, and coordinates existing revenue and grant funding Report P87, P88
Rejected: Continue current activity without a joint strategy or external partner. No current mechanism to engage all parts of the community, including police, health, VCS, business, faith leaders and citizens, to inform a long-term approach Report P79, P80
Implications
Financial: Total cost across 2026-28 is £707,552.00, with £125,000 from the two councils, £125,000 from the National Lottery, £167,552 from Dispersal and £237,500 from Afghan funding plus £90,000 in further Be Together funding. Report P126
Legal: Procurement advises that because Belong is the only supplier affiliated with the National Lottery match funder, the £125,000 council spend must follow the waiver route under the Council Constitution. Report P135
Equalities: An Equality Impact Assessment found the strategy and action plan should have positive impacts on groups with protected characteristics, covering integration, safety and equalities for all residents. Report P137, P138, P139
Risk: Local government reorganisation after 31 March 2028 means the successor authority may not adopt the strategy or continue the action plan, and any future decisions must be reviewed in light of restrictions in place at the time. Report P133, P134, P141
Risk: Risks of insufficient engagement, misinformation or negative media coverage, and safeguarding or GDPR failures are to be managed through working with Belong, proactive communications and clear escalation processes. Report P140, P142
Climate: A high-level Climate Impact Assessment is not appropriate at strategy level; each project will be assessed using the Climate Impact Assessment Tool as it comes forward, with the climate and biodiversity team engaged as internal consultees. Report P136
Who and where
All residents of South Oxfordshire and Vale of White Horse districts Report P3, P88
Migrant cohorts including Homes for Ukraine guests, dispersal asylum seekers, Afghan arrivals and Hong Kong BNO arrivals Report P26, P45
Voluntary and community sector, faith groups, businesses, police, health services and community leaders in both districts Report P79, P104
Future unitary authority/authorities created through local government reorganisation after 31 March 2028 Report P115, P141
Timeline
23 October 2025: SODC Full Council motion: Fair treatment for all residents Report P6, P152
10 December 2025: VWHDC Full Council motion: Sanctuary and Fair Treatment for All Report P6, P153
11 February 2026: VWHDC budget meeting approved £25,000 one-off for community cohesion motion Report P81, P155
12 February 2026: SODC budget meeting approved £50,000 per year ongoing for community cohesion Report P81, P154
14 May 2026: SODC Annual Meeting approved motion on Adoption of Socio-Economic Duty Report P82, P83, P156
June 2026 to August 2026: Exploration phase, onboarding Belong and identifying partners Report P103
2 July 2026: South Cabinet decision on Joint Community Cohesion Strategy Report P3
September 2026 to October 2026: Engagement phase with strategic meeting and monthly Engagement Group Report P104
November 2026 to December 2026: Strategy drafting by Belong with council officers Report P105
January 2027 to February 2027: Partner feedback and finalisation Report P106
March 2027 to April 2027: Final strategy to Scrutiny and Cabinet for approval Report P107
April 2027: Implementation of fully funded 2027/28 action plan begins Report P108
31 March 2028: End of current funded period; Be Together and current programme funding end; local government reorganisation takes effect Report P43, P51, P53, P141
Plain English for the jargon
Be Together: Two-year Community Wellbeing programme funded by external resettlement grants until 31 March 2028, with themes Be Active, Be Connected, Be Mobile and Be Skilled Together.
Belong (The Cohesion and Integration Network): Specialist third-sector organisation endorsed by the LGA and funded by the National Lottery, commissioned to develop the strategy and 2027/28 action plan.
HfU: Homes for Ukraine Scheme, launched March 2022.
ARAP / ACRS / ARP: Afghan Relocations and Assistance Policy, Afghan Citizens Resettlement Scheme, and the unified Afghan Resettlement Programme from 1 March 2025.
VPRS / UKRS: Vulnerable Persons Resettlement Scheme (from 2014) and the UK Resettlement Scheme (from March 2021).
BNO: British National (Overseas) status, with arrivals under a scheme that began January 2021.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item289
Resolved
That Cabinet: a) Note the existing community cohesion activity already being delivered across both councils through the Community Hub and Be Together programme. b) Approves the development of a five-year community cohesion strategy that supports the Councils motions for Fair treatment for all residents (South Oxfordshire District Council, 23 October 2025), and Sanctuary and Fair Treatment for All (Vale of White Horse District Council, 10 December 2025). c) Subject to (b) above being approved, that Cabinet note the strategy will finalise a fully funded action plan for the year 2027/28, linking all existing grant funding and National Lottery funding into a homogenous action plan. The strategy action plan will outline in principle further actions that any future authority council can consider to support community cohesion. d) Subject to b) above being approved, that Cabinet approve the commissioning of Belong, a specialist third-sector organisation with recognised expertise in developing cohesion strategies that link cultural, social and economic factors to deliver best practice, to develop a community cohesion strategy and action for the year 2027/28 for Cabinet approval.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Director of Communities Author: Charlotte Graham, Jaffa Holland Telephone: [phone removed], [phone removed] E-mail: [email protected], [email protected] Wards affected: All South Cabinet member responsible: Georgina Heritage E-mail: [email protected] Vale Cabinet member responsible: Helen Pighills E-mail: [email protected] To: CABINET Dates: 2 July 2026 (South) 3 July 2026 (Vale)
Page 97 Agenda Item 11
Development of a Joint Community Cohesion Strategy Recommendation(s) (a) That Cabinet note the existing community cohesion activity already being delivered across both councils through the Community Hub and Be Together programme.
(b) That Cabinet approve the development of a five-year community cohesion strategy that supports the Councils motions for Fair treatment for all residents (South Oxfordshire District Council, 23 October 2025), and Sanctuary and Fair Treatment for All (Vale of White Horse District Council, 10 December 2025).
(c) Subject to (b) above being approved, that Cabinet note the strategy will finalise a fully funded action plan for the year 2027/28, linking all existing grant funding and National Lottery funding into a homogenous action plan. The strategy action plan will outline in principle further actions any the future authority council consider to support community cohesion.
(d) Subject to (b) above being approved, that Cabinet approve the commissioning of Belong, a specialist third-sector organisation with recognised expertise in developing cohesion strategies that link cultural, social and economic factors to deliver best practice, to develop a community cohesion strategy and action for the year 2027/28 for Cabinet approval.
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes No Yes
Signing off Hannah Nick Bennett Kim Hall Ruth Lewin- officer Makins Leigh
Purpose of report 1. To update Cabinet on the wider community cohesion activity currently on-going across the districts for 2026/27.
2. To recommend to Cabinet to approve the creation of a five-year Joint Community Cohesion Strategy with South Oxfordshire and Vale of White Horse District Councils, which include a proposed community cohesion action plan for 2027/28.
Strategic priorities 3. These are:
South - Thriving, healthy, and inclusive communities
Vale - Providing healthy, sustainable, and inclusive communities
Page 98 Agenda Item 11
Background – National Context 4. In 2025, the Together Coalition launched an Independent Commission on Community and Cohesion to address issues of social disconnection and division in the UK. The Commission is led by former Conservative Home Secretary, Sir Sajid Javid, and former Labour MP, Jon Cruddas. In July 2025, the commission published its foundational report, The State of Us: Community Strength and Cohesion in the UK, developed by the think tank British Future and the Belong Network.
5. The State of Us Community Strength and Cohesion in the UK (2025) defined Community Cohesion as; “the glue that holds society together: trust, a sense of security and belonging, mutual support, shared norms and values, and community and democratic resilience. Economic and infrastructural factors such as employment and housing impact on community cohesion, as do social factors such as population change, civic participation, local leadership and social connectedness.”
Migration and Resettlement – Local Context
6. Prior to 2014 the number of supported resettlement and asylum seekers within South Oxfordshire District Council (SODC) and Vale of White Horse District Council (VWHDC) were extremely small, if any. Since 2014 this picture has changed and accelerated. In part driven by Russia’s invasion of Ukraine (February 2022) and the launch of the Homes for Ukraine Scheme (HfU) in March 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.