RESOLVED, that the Mayoral Combined Authority: 1. Progression of Waverley Local Centre to full approval and award of up to £7m grant to Waverley Square ltd subject to the conditions set out in the Appraisal Panel Summary Table 2. Progression of Specialist VFX Training Equipment to full approval and award of up to £0.91m grant to DN College Group subject to the conditions set out in the Appraisal Panel Summary Table 3. Progression of Falstaff Phase 3 to full approval and award of up to £1.52m grant to Sheffield Housing Company subject to the conditions set out in the Appraisal Panel Summary Table 4. Progression of UK Atomic energy project to full approval and award of up to £2.2m grant to UK Atomic Energy Authority subject to the conditions set out in the Appraisal Panel Summary Table. 5. Progression of Company Ref. 0067 to full approval and award of up to £0.124m grant to Company Ref. 0067 subject to the conditions set out in the Appraisal Panel Summary Table 6. Progression of Company Ref. 0095 to full approval and award of up to £0.05m grant to Company Ref. 0095 subject to the conditions set out in the Appraisal Panel Summary Table 7. Progression of Company 0096 to full approval and award of up to £0.249m grant to Company 0096 subject to the conditions set out in the Appraisal Panel Summary Table 8. Delegates Authority to the Head of Paid of Service, in conjunction with the Section 73 and the Monitoring Officer, to enter into the contractual arrangements required as a result of the above approvals.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Purpose of Report This paper requests approval for seven schemes with a total value over all years of £12.05m and seeks delegated authority be given to the Head of Paid Service in consultation with the S73 and Monitoring Officer to enter into legal agreements for the schemes.
Thematic Priority Secure investment in infrastructure where it will do most to support growth.
Freedom of Information and Schedule 12A of the Local Government Act 1972 This paper will be available under the Combined Authority Publication Scheme however, appendices E – G are exempt from publication under paragraph 3, part 1, section 12A of the Local Government Act 1972.
Recommendations The SCR MCA consider and approve: 1. Progression of Waverley Local Centre to full approval and award of up to £7m grant to Waverley Square ltd subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix A 2. Progression of Specialist VFX Training Equipment to full approval and award of up to £0.91m grant to DN College Group subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix B 3. Progression of Falstaff Phase 3 to full approval and award of up to £1.52m grant to Sheffield Housing Company subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix C 4. Progression of UK Atomic energy project to full approval and award of up to £2.2m grant to UK Atomic Energy Authority subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix D 5. Progression of Company Ref. 0067 to full approval and award of up to £0.124m grant to Company Ref. 0067 subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix E 6. Progression of Company Ref. 0095 to full approval and award of up to £0.05m grant to Company Ref. 0095 subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix F 7. Progression of Company 0096 to full approval and award of up to £0.249m grant to Company 0096 subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix G 8. Delegated Authority to the Head of Paid of Service, in conjunction with the Section 73 and the Monitoring Officer, to enter into the contractual arrangements required as a result of the above approvals (1-7).
1. Introduction 1.1 This paper requests approval for seven schemes with a total value over all years of £12.05m and seeks delegated authority be given to the Head of Paid Service in consultation with the S73 and Monitoring Officer to enter into legal agreements for the schemes. 1.2 The LEP Board and MCA have approved revised governance arrangements and associated constitution with delegated approval authority for projects below £2m which came into effect on 1st April 2019, however it has not yet been possible to convene the first meetings of the new Executive boards. Rather than delay projects which are ready to proceed to full approval and delivery stage this paper presents approvals of projects both above and below the £2m delegated. This paper includes projects that would have been considered at four of the five new boards. It is expected that this will be the last time Leaders are asked to consider projects at the MCA for projects below the £2m LGF threshold.
2. Proposal and justification
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.